Concrete surround for drainage pipes, Civil Engineering

Assignment Help:

Concrete surround is generally adopted for rigid drainage pipes to resist high traffic loads (for instance under shallow covers) and to allow for using pipes with lower strength. Furthermore the use of concrete surround can minimize settlement of adjacent structures. Additionally the highest possible accuracy in levels and gradient can be achieved by using concrete surround as considerable settlement is expected in other categories of beddings such as granular bedding. 

The distribution of reinforcement in concrete pipes can't be uniform due to the occurrence of tensile stresses in different locations around the circumference of pipes. For illustration tensile stresses are highest at the inner face of pipes at invert and crown levels and at outer face of two sides of pipes. An elliptical cage can be designed in order to optimize the usage of steel reinforcement.

381_Concrete surround for drainage pipes.png

Fig: Concrete surround of drains


Related Discussions:- Concrete surround for drainage pipes

Calculate the amount put into saving account, Calculate the Amount put into...

Calculate the Amount put into Saving Account If you want to have $60,000 in 10 years, the amount that should be put into a 6.0% (effective annual rate) savings account now is m

What is the cost of phoenix activity, Q. What is the cost of phoenix activi...

Q. What is the cost of phoenix activity? Phoenix activity has a range of impacts on the Australian economy. Employees lose entitlements when phoenix activity has occurred and w

What is ceramic mosaic and chequered cement tiles, Q. What is Ceramic mosai...

Q. What is Ceramic mosaic and Chequered Cement tiles? Chequered Mosaic tiles - Repairs to steps of F O Bs should be done only with Chequered Mosaic tiles. Ceramic m

Explain total dynamic head (tdh), Total Dynamic Head: (TDH) y-axis plo...

Total Dynamic Head: (TDH) y-axis plot point related to each x-axis flow rate along the system curve plot. TDH = h a = TSH + h f + v 2 /2g       v 2 / 2g usually small

Design of flexible pavements - road pavements, Design of Flexible Pavements...

Design of Flexible Pavements: The design of flexible pavements is done by the CBR method. The CBR test, described further, gives an indication of the supporting power of the

Determine the late start time for activity, For the project network shown, ...

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

Calculate the amount of cubic yards of soil, A proposed building site requi...

A proposed building site requires 135,000-ft 3 of imported fill.  A borrow site is located 5-miles Northeast of the project site where the soil has a shrinkage of 16%.  The amount

Determine about the tensile stresses, Determine about the tensile stresses ...

Determine about the tensile stresses Unifody prestressed members designed for equal flexure in opposite directions,without permitting tensile stresses under working loads, requ

Premix road, plz tell me the ratio of sand,aggregate,and asphalt.pl tell me...

plz tell me the ratio of sand,aggregate,and asphalt.pl tell me the mm of aggregate

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd