Water control for sheet pile walls, Civil Engineering

Assignment Help:

Q. Water control for sheet pile walls?

Ground water flow into excavations constructed by sheet pile walls must be minimized in order to save the cost of the provision of pumping systems or well points to lower water table inside the excavation. In case a layer of impermeable material such as clay is located slightly below the excavation, it can be desirable to drive the sheet piles further into this layer and cost of further driving can be less than cost of the provision of continuous pumping in the excavation.

Conversely if there is no impermeable layer underneath the excavation, engineers can consider driving the sheet piles further so as to increase flow path of groundwater into the excavation and this helps to decrease the amount of water flow into the excavation. In the same way a cost benefit analysis has to be carried out to compare the extra cost of driving further the sheet piles with the reduced pumping costs.


Related Discussions:- Water control for sheet pile walls

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Contractor to continue concreting works, Question If on-site slump test fai...

Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by

Calculate the amount put into saving account, Calculate the Amount put into...

Calculate the Amount put into Saving Account If you want to have $60,000 in 10 years, the amount that should be put into a 6.0% (effective annual rate) savings account now is m

Explain gap survey and adjustment of gap, Q. Explain Gap Survey and adjustm...

Q. Explain Gap Survey and adjustment of Gap? Gap survey and rectification of gaps is to be carried out, in stretches where track develops excessive creep jammed joints, sun kin

Key role of drilling fluid in rotary drilling, Question What is key rol...

Question What is key role of drilling fluid in rotary drilling in site search? Answer Drill fluid in rotating serves two main reasons. (i) Facilitate rotation of

Critical-depth relationship, If y1 and y2 are alternate depths of a rectang...

If y1 and y2 are alternate depths of a rectangular channel show that Yc³ =2y1²y2²/(y1+y2) Also specific energy E = y1²+y1y2+y2²/(y1+y2)

Survey, who to we calculate the RL at first point.

who to we calculate the RL at first point.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd