You are preparing a project to lay fiber optic cable...
You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week and cost $3000. The second task is to lay the cable. This will take three weeks and will cost $45,000. The total length of the cable is 15 miles. The last task, which will take one week, is to Terminate and test the cable. You budget $5000 for this. At the end of the first week, you have completed mobilization, but it cost a total of $4500. At the end of the third week, you have completed five miles of cable at a total cost of $28,000. It takes you a total of 10 weeks to complete the entire project, for a total cost of $65,000.
a. At the end of week 1:i. What is your SPI?ii. What is your CPI?iii. What is your EAC?
b. At the end of week 3:i. What is your SPI?ii. What is your CPI?iii. What is your EAC?
c. At the end of the project:i. What is your SPI?ii. What is your CPI?iii. What is your EAC?
project scope driversa. what were the project drivers in terms of problems and opportunities and go beyond what is
Distinguish between capital project funds and debt service funds. How are they related and how are they different?
Challenges of managing projects involving teams with members from multiple ethnic and sociopolitical backgrounds
Explain what do you feel are the most important qualities for a leader to possess to be effective and do you feel that a person can be both a leader and a manager, or are they mutually exclusive roles
important information about project management questions1.you are the project manager for a project included in the
Compute the takt time for a system where the total time per shift is 400 minutes, there is one shift, and workers are given two 20-minute breaks and 30 minutes for lunch
The main purpose of aggregate operations planning is to specify the optimal combination of which of the following?
question 1 preparation is considered to be a key process in project management. examine the key areas which form part
List and describe the basic makeup for a computer and the function each performs. Identify and describe the two types of software.
What form of business organization would you choose for this venture, and why? Outline the advantages and disadvantages of each of the three major types of business in this particular context.
Why is it reasonable to use a balanced scorecard system to measure staff performance? How does this approach mitigate concerns about measurement dysfunction?
Multitasking has become the norm in our everyday society and why is it important for a project manager to be aware of multitasking during a project?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd