Question 1 a member of a project team that is implementing

Assignment Help Computer Networking
Reference no: EM13383164

Question 1

A member of a project team that is implementing a new credit card payment process at a bank has direct responsibility to do all of the following EXCEPT:

be sensitive to conflicts between other team members and help resolve them.

ensure that the project has appropriate resources for the job to be completed.

help solve project problems that spill over into areas outside their expertise.

be called upon to share their expertise in credit card payment processes.

Question 2

Mike Multitask has three projects (A, B, and C) that are each four days long. Mike's supervisor suggests that he work first on project A, finish it, then work on project B until it is finished, and then on project C. Mike boldly declares, "My name isn't Multitask for nothing," so he decides to spend one day working on project A, one on B, one on C, then back to project A, and so on. There is no additional start up or shut down time required by splitting the projects this way. What is the difference in average completion time for all three projects when they are managed Mike's way when compared with his supervisor's suggestion?

There is no difference.

Mike's way is 3 days shorter.

Mike's way is 3 days longer.

Mike's way is 9 days longer.

Question 3

Slack time is routinely lost in a network:

at the point where multiple paths exit a common node.

at the point where multiple paths enter a common node.

at the point where the longest activity begins.

at the point where the shortest activity begins.

Question 4

Following are four sets of most optimistic, most likely, and most pessimistic times (in weeks) for an activity. Which one of the four sets will have a mean estimated time equal to the most likely time?

1, 9, 9

1, 5, 9

1, 1, 9

1, 5, 5

Question 5

You are responsible for managing a project with the following activities (times are given in days).

Activity      Expected Time    Immediate Predecessor(s)

A                 3                            ---

B                 6                            ---

C                 2                            ---

D                 5                             A

E                  2                            C

F                   7                            A

G                   4                         B, D, E

what is the critical path and expected completion time for this project?

A - F ; 12 days

A-D-G; 12 Days

B-G; 10 days

C, E, G; 10 days

Question 6

Assuming a beta distribution is being used, if the most pessimistic time for an activity increases by six weeks, what will happen to the expected time for that activity?


It will increase by one week.

It will decrease by one week.

It will increase by six weeks.

It will remain the same.

Question 7

If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?

50 percent

95 percent

100 percent

It cannot be determined.

Question 8

A project is currently scheduled to be finished on its normal earliest completion date. The project manager has the opportunity to earn a bonus if the project can be completed three weeks ahead of schedule. The increase in project direct costs related to crashing activities would be $40,000. Also, project indirect costs are $15,000 per week. What is the smallest bonus that the project manager should accept if he or she wants to avoid increasing overall project costs?

Less than or equal to $5,000

Greater than $5000 but less than or equal to $10,000

Greater than $10,000 but less than or equal to $15,000

Greater than $15,000

Question 9

You are given the following information about activity B:
Normal time = 9 weeks
Crash time = 5 weeks
Cost to crash per week = $2000
Crash cost = $41,000

What will it cost to complete activity B in 6 weeks?

Less than or equal to $34,000

Greater than $34,000 but less than or equal to $36,000

Greater than $36,000 but less than or equal to $38,000

Greater than $38,000

Question 10

You are given the following information about activity F:
Normal time = 16 weeks
Crash time = 10 weeks
Crash cost = $45,000
Cost to crash per week = $2,000

What is the normal cost for activity F?

Greater than or equat to $55,000

Less than $55,000 but greater than or equal to $47,000

Less than $47,000 but greater than or equal to $40,000

Less than $40,000

Reference no: EM13383164

Questions Cloud

Tasknbsp write a one page paper summarizing your : tasknbsp write a one page paper summarizing your thoughts.bob pierce a gentle man of about 50 is the president of abc
You are required to develop a social marketing plan for a : you are required to develop a social marketing plan for a social marketing problem and organisation of your choice.
Question 1which one of the following statements about : question 1which one of the following statements about lot-sizing rules is true? the periodic order quantity poq rule
Question 1 ten high-technology batteries are tested for 200 : question 1 ten high-technology batteries are tested for 200 hours each. one failed at 20 hours all others completed the
Question 1 a member of a project team that is implementing : question 1 a member of a project team that is implementing a new credit card payment process at a bank has direct
Write a report based on a management issue or potential : write a report based on a management issue or potential issue which they identify in the nominated case study on
Q1 define each of the following - pharmacokinetics - : q1 define each of the following - pharmacokinetics - pharmacodynamics - pharmacotherapeutics - toxicology q2common
Your client frank bearden owns an arkansas business that : your client frank bearden owns an arkansas business that brokers high-quality fresh fruits and vegetables to
Create a powerpoint presentation that will be communicated : create a powerpoint presentation that will be communicated to your manager and his fellow managers. as a group the

Reviews

Write a Review

Computer Networking Questions & Answers

  How many addresses are left

Create 3 subnets for this organisation with the first subblock of 250 addresses, the second subblock of 60 addresses and the third subblock of 12 addresses.

  Reason to pay attention to faulty terminations

What do you consider the single most important reason to pay attention to faulty terminations and excessive horizontal wiring spans? Why is it critical to label patch cables, ports, and data jacks?

  What is meant by a nondeterministic protocol

What is meant by a nondeterministic protocol and what are the various combinations of circuit switched and packet switched networks and connection-oriented and connectionless network applications?

  List host addresses

Subnet the following address - 130.4.8.74 The goal is to subnet the above address and to produce 7 subnets and 350 hosts/subnet. Please show all of your work. I am looking for the following: 1. List Custom Subnet Mask 2. List Network Addresses 3. ..

  You are required to set up a small network with network id

you are required to set up a small network with network id 200.100.50.16027. in this network there are three routers

  Explain the significance on the design and use of various

explain the significance on the design and use of various variables and attributes control charts of being based on

  Compute theoretical maximum channel capacity-telephone lines

Given the narrow (usable) audio bandwidth of the telephone transmission facility, nominal SNR of 56 dB (400,000), and a distortion level of

  What are the four addresses for network

If you have a class B network and want to divide it into subnets, each with 126 hosts, which subnet mask should you use? What are the four addresses (broadcast and network number) for the network starting at 131.204.18?

  Explain system gives protection using bell-lapadula policy

A computer system provides protection using the Bell-LaPadula policy. How would a virus spread if: The virus were placed on the system at system low (the compartment that all other compartments dominate)?

  Dns

problems of IPV, DNS server software, TCP SYN attack, Ping of Death, Land attack, Teardrop attack, Smurf attack, Fraggle attack

  What is still need to be completed main referencesr

7502ICT - Advanced Networking: Project. In order to keep track of the progress of the project, you will have to submit an interim progress report describing (a) brief overview of the project (b) what work has been completed so far and (c) what is s..

  Explain use of virtual private network-tunneling protocol

Can they use virtual private network and tunneling protocol, or is a better technique available? Justify your answer.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd