Predecessor activities

Assignment Help Project Management
Reference no: EM13893029

1.Define predecessor, successor, and parallel activities. Give a real world example of each

Predecessor activities - those activities that must be completed before another activity can be started. Ex: Computer's OS must be installed before loading an application package.

Successor activities - activities that must follow a particular activity in some type of sequence. Ex: a program must be tested and then documented after it is compiled.

Parallel activities - an activity or task that can be worked at the same time as another activity. Ex: Design web page layouts and set-up server
 

2. In the context of critical chain project management, what is resource contention?  

3.Define the following and give a real world example of each (other than the ones described in the text book): Finish-to-Start; Start-to-Start; Finish-to-Finish; Start-to-Finish.  

4.     Assume the following activities for a project along with their estimated durations and predecessors. Describe how critical path analysis would be applied to this project, and calculate the critical path. Define the concepts: slack/float, expedite/crash, and fast tracking and explain what their implications are for this project?  

Hint: Start with the following steps:

a.       Draw AON diagram

b.       Calculate Possible Activity paths

c.       Identify critical path

 

Activity

Estimated Duration in Days

Predecessor

A

2

None

B

4

A

C

3

A

D

1

C,B

E

1

C,D

F

3

D,E

G

2

F

Critical Path: A-B-G-F-H

Slack/Float: amount of time an activity can be delayed before it delays the project Expedite/Crash: adding resources to an activity on the critical path to shorten duration Fast Tracking: completing activities in parallel to shorten critical path 

5.     What are the seven IT project risk management processes?  

6.     What is a risk response plan? What should be included? 

7.     Compare the three types of project risk: known, known-unknown, and unknown-unknown. Give an example (not discussed in the text book) of each

8.      Describe the qualities of a good project metric.  

9.       Given the following information, is the Project in trouble?

Calculate: 

a.       Cost Variance (CV) : (CV) = EV AC

b.      Schedule Variance (SV):  (SV) = EV PV

c.       Cost Performance Index  (CPI) : (CPI) = EV/AC

d.      Schedule Performance Index (SPI):  (SPI) = EV/PV 

10.  What are the key differences (4-5) between the Agile Project Management approach and Waterfall (Traditional Project Management) 

11.  What was your favorite topic in this course? 

Reference no: EM13893029

Questions Cloud

What are baseline dates based on : What are baseline dates based on? 2. What is variance, and how is it calculated? 3. What do positive and negative variance indicate? 4. What table do you apply to the task sheet to see baseline dates? What table do you apply to see actual dates? What..
Create a profile of the target consumer of tide : Explain how psychographic information is employed to create a profile of the target consumer of Tide. I need two hundred words with references.
Learning of employees and customers : In what ways has the learning of employees and customers changed as a result of their ability to use the Web, and how would this change the interaction between them during the purchasing process?
Implement a matrix class for two-by-two matrices : Implement a Matrix class for 2-by-2 matrices. Include a default constructor, a copy constructor, an inverse() function that returns the inverse of the matrix.
Predecessor activities : Predecessor activities - those activities that must be completed before another activity can be started. Ex: Computer's OS must be installed before loading an application package.Successor activities - activities that must follow a particular activit..
What is the p-value for the test : The life in hours of a battery is known to be approximately normally distributed, with standard deviation s = 1.25 hours. A random sample of 10 batteries has a mean life of x ¯=40.5 hours. Is there evidence to support the claim that battery life ex..
Historians rely on primary sources to construct a picture : Historians rely on primary sources to construct a picture of the past
Implement a point class for two-dimensional points : Implement a Point class for two-dimensional points (x, y). Include a default constructor, a copy constructor, a negate() function to transform the point into its negative, a norm() function to return the point's distance from the origin (0,0), an..
In analyzing the circumstances surrounding the war of 1812 : In analyzing the circumstances surrounding the War of 1812

Reviews

Write a Review

Project Management Questions & Answers

  What will be the frequency of the meetings

What will be the frequency of the meetings? Provide a rationale for your choice. What facilitation skills would you need to ensure each project meeting is productive, considering that you are working with a cross-functional team and team members are ..

  Explain what is the relative quality between toyota corolla

explain what is the relative quality between toyota corolla and rolls royce?too many people believe high quality is

  Show the capture unidentified risk

Capture Unidentified risk - Seeing risks that are not originally identified in a project is essential throughout the life of a project.

  Determining the business ethics and leaders

What is meant by the term "business ethics?" Compare and contrast business ethics to the actions of organizational leaders at Target Corporation.

  Project charter and project scope statement artifacts

Why are the Project Charter and Project Scope Statement artifacts critical to the success of a project? Describe some of the key elements of these artifacts.

  Managerial roles and gap analysis

What did you learn from completing the Managerial Roles and Gap Analysis?

  What is the projected revenue and costs

What is the projected revenue, costs, and potential profits would be over the next 10 years based on the current capacity,

  You understand why pmos fail and what you will do to

1.part 1 what are the basic principles behind the agile process?part 2 what is the pms role under the agile process?

  Project management of applications

Project Management of Applications - Show the role of the project manager in the in-house development of a customized application.

  Justifying the influence of stakeholders

Justify the influence of stakeholders in the project management plan and their role in communication planning.

  The pmo modelsuppose a medium size company that has decided

the pmo modelsuppose a medium size company that has decided to begin using project management in a wide variety of its

  How to successfully implement the given project

Issues brought out in the case include defining the PMO, and how to successfully implement it in what appears to be a resistant culture.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd