PERT/CPM problem with three (3) time estimates

A project is composed of 8 tasks. The three-time estimates (in days) for each activity plus the precedence requirement for each are shown in the table below:

Activity Activity Time Estimates
(in days) ImmediatePredecessor
A 2, 3, 4 None
B 3, 4, 11 None
C 1, 2, 3 A, B
D 4, 5, 12 C
E 3, 5, 7 C
F 2, 3, 4 E
G 2, 3, 10 C
H 2, 3, 4 D, G, F
I 2, 3, 10 D, F
J 1, 2, 3 H
K 1, 2, 3 I, J

A. Draw a network for the project using AON method.

B. Determines the critical path(s) and identify them by a) double lining the arrows connecting the activities on the CP (like ===) AND b) writing the letter representing the activities on the CP in the answer-sheet-set.

C. Do a complete path analysis and fill the table in the answer-sheet set

D. What are the chances that the project will finish within 25 days?

E. What are the chances that the project will take longer than 23 days to finish?

Reference no: EM13363235

Questions Cloud

Project proposalsits a busy monday morning and you have : project proposalsits a busy monday morning and you have work to assign to others and to complete yourself. of the tasks
Scheduling and project management of dellshow how project : scheduling and project management of dell.show how project management influences other departments and functions of
Project planning breakdown structure and controlshow what : project planning breakdown structure and controlshow what controlling measures should be taken during the planning
A project has several activities these activities are shown : a project has several activities. these activities are shown in the table below together with their time estimates in
Pertcpm problem with three 3 time estimatesa project is : pertcpm problem with three 3 time estimatesa project is composed of 8 tasks. the three-time estimates in days for each
Fortran corporation would you recommend that the project be : fortran corporation would you recommend that the project be adopted?suppose the going market rate of interest on high
Explain in your own words how heredity and environmental : explain in your own words how heredity and environmental forces have combined to affect your development. give one
Grainger manufacturing inc produces outdoor grills on march : grainger manufacturing inc. produces outdoor grills. on march 31 the company had 120 grills in inventory. the companys
What controlling measures should be taken during the : what controlling measures should be taken during the planning phase. then provide a generic method for creating a

Reviews

Write a Review

Project Management Questions & Answers

  Concept of change management process in a projectexplain

concept of change management process in a projectexplain the concept of the change management process within a

  Explaining critical path of a pert chart

In terms of creating a timeline, what is meant by the critical path of a PERT chart?

  Identify the technical challenges by project leader

Recommend three actions that the project leader should take in order to identify and understand the technical challenges and issues facing the project

  Critical issues for the success of a project

Show the areas that you consider your strengths, and what areas would be hard for you to manage. Use specific examples to support your answer

  How to respond to risks

How to Respond to Risks - As a project manager, the risk assessment is one of the most important pieces of project documentation.

  What was salems expected net present value for this project

Present value information is given below so what was Salem's expected net present value for this project

  Checklist versus weighted factor method of selecting project

Discuss the pros and cons of the checklist versus the weighted factor method of selecting projects.

  Optimizing project budgetwhat does it mean to crash a

optimizing project budgetwhat does it mean to crash a project and what are some ways to save money? is it possible to

  Risk assessment in project documentation

As a project manager, the risk assessment is one of the most important pieces of project documentation.

  Management related training documentation

Make project management related training documentation - Describe each of the phases of the project management process and its related knowledge areas. List the major activities in each phase.

  What are the pros and cons of great lakes coating''s

What are the pros and cons of great lakes coating's not having formalized policies regarding employees behavior?

  Objectives for a pro shop in a football stadium

Project Goals and Objectives - Explain what are the Project goals and Objectives for a pro shop in a football stadium.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd