Given the following project to landscape a new building site.

Activity Immediate Predecessor Activity duration(days) Resources used

A: Get Plants - 2 X,Y
B: Get flowers A 2 X
C: Obtain soil A 3 X
D: Obtain Fertilizer B,C 4 X,Y
E: Select Labor D 3 W,X
F: Set date D 1 W,X,Y
G: BEGIN E,F 2 X,Y

(a) Determine the critical path and project duration in days.

(b) Given that each resource is assigned 100% to each task, identify the resource constraints.

(c) Level the resources and determine the new project duration and critical path

(d) Find what alternative solutions can be used to shorten the project duration and not over-allocate the resources.

Reference no: EM13363203

Questions Cloud

Given the following information for a one-year project : given the following information for a one-year project answer the following questions recall that pv is the planned
Difference between it project managers and traditional : difference between it project managers and traditional project managers.all projects are constrained by three factors
Emotional intelligence importance for project managersone : emotional intelligence importance for project managersone of the measurements of leadership is the eq emotional
Description of risk managementwrite a paper regarding a : description of risk managementwrite a paper regarding a project either real or fictitious where one is able to discuss
Given the following project to landscape a new building : given the following project to landscape a new building site.activityimmediate predecessoractivity
Project management of applicationsshow the role of the : project management of applicationsshow the role of the project manager in the in-house development of a customized
Project cash flow analysisyour company plans to produce a : project cash flow analysisyour company plans to produce a product for two more years and then to shut down production.
Earned value analysis - monitoring and controlling project : earned value analysis - monitoring and controlling project costonce your budget is planned and allocated across your
Question about milton manufacturing overhead activity based : question about milton manufacturing overhead activity based costingmilton manufacturing has four categories of

Reviews

Write a Review

Project Management Questions & Answers

  What do you understand by net present value

You are the project manager of a leading textile engineering company. The company opened its door in year 2000. Today, after 13 years of existence, it is being challenged with a loss in profitability approximating a 65% loss in net revenue

  Project requirements document

Prepare a Project Requirements Document for this project that answers the items - Project Requirements Document

  Calculating every contingency cost

Should you, as the project manager, try to control and calculate every contingency cost you can think of?

  Project acceptance and rejection

Project Acceptance and Rejection - Jackson Corporation is evaluating the following four independent, investment opportunities:

  Estimating completion of task

Each of the tasks needs an estimate of how long it will take.

  Explain about macro and micro projects

Prepare a paper presenting the overall project and how to establish the foundational areas for growth potential in data and user capability.

  Project management

Project Management - To achieve these objectives, the management team of Company A recognizes that a new organizational structure is required.

  Firm-s break-even point increase

Would the firm's break-even point increase or decrease if it made the change?

  Show the system design issues

System Design Issues - If a project is poorly designed and constructed, will a well-planned and well-executed implementation effort help the project to succeed?

  What is meant by mass customization

What is meant by mass customization? How can market conditions and consumer desires affect customization?

  Technology beneficial to manufacturing-service operations

Your process team has been requested to identify technology that would be beneficial to manufacturing and service operations clients.

  Accounting information system- communication

An organization's AIS should be able to communicate relevant decision-making information to both top management and operating management.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd