Given the following project to landscape a new building

Assignment Help Project Management
Reference no: EM13363203

Given the following project to landscape a new building site.

Activity Immediate Predecessor Activity duration(days) Resources used

A: Get Plants - 2 X,Y
B: Get flowers A 2 X
C: Obtain soil A 3 X
D: Obtain Fertilizer B,C 4 X,Y
E: Select Labor D 3 W,X
F: Set date D 1 W,X,Y
G: BEGIN E,F 2 X,Y

(a) Determine the critical path and project duration in days.

(b) Given that each resource is assigned 100% to each task, identify the resource constraints.

(c) Level the resources and determine the new project duration and critical path

(d) Find what alternative solutions can be used to shorten the project duration and not over-allocate the resources.

Reference no: EM13363203

Reviews

Write a Review

 

Project Management Questions & Answers

  Project manager are not allow to change to baseline

When would a project manager not allow changes to a baseline?

  Develop 48 acres land into mixed-use buildings

Your clients have secured the financing to develop 48 acres land into mixed-use buildings. They have asked you to draft a high-level project plan to begin the more detailed discussions. Forty percent of the site is an undeveloped field, and the proje..

  Specify the performance criteria for the project

Project Performance: List the desired outputs from the project and specify the performance criteria for the project.

  What can you do to eliminate the risk

What is impacted if this risk occurs? What is the extent of the impact and what can you do to eliminate the risk

  Problem on project analysis

Problem on Project Analysis - McGilla Golf has decided to sell a new line of golf clubs

  Culture in project management

Explain culture in project management - Why is it important to assess an organization's culture before you begin a project

  What would be new productivity

Explain They have discussed reassigning work so the flow through the shop is smoother. They think they can increase crate production to 155 per day. What would be their new productivity?

  Important issue facing private security

What do you believe the most important issue facing private security today is?

  Part 1come up with a goal calculate constraints and

part 1come up with a goal calculate constraints and formulate a reasonable investment policy statement.part 2select

  Enhancing steps associated with reengineering

Select the PERT technique you consider LEAST valuable when altering or enhancing steps associated with reengineering. Explain your choice. Describe and analyze how the two techniques you chose influence the Critical Path Method.

  Evaluating potential projects before implementing it

Why do you think it is important to evaluate potential projects before proceeding with implementation?

  Explain and describe a mitigating strategy

Briefly explain and describe a mitigating strategy for the risks below- Over budgeting/excessive spending/lack of financial support during campaign.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd