Given the following project to landscape a new building

Assignment Help Project Management
Reference no: EM13363203

Given the following project to landscape a new building site.

Activity Immediate Predecessor Activity duration(days) Resources used

A: Get Plants - 2 X,Y
B: Get flowers A 2 X
C: Obtain soil A 3 X
D: Obtain Fertilizer B,C 4 X,Y
E: Select Labor D 3 W,X
F: Set date D 1 W,X,Y
G: BEGIN E,F 2 X,Y

(a) Determine the critical path and project duration in days.

(b) Given that each resource is assigned 100% to each task, identify the resource constraints.

(c) Level the resources and determine the new project duration and critical path

(d) Find what alternative solutions can be used to shorten the project duration and not over-allocate the resources.

Reference no: EM13363203

Questions Cloud

Given the following information for a one-year project : given the following information for a one-year project answer the following questions recall that pv is the planned
Difference between it project managers and traditional : difference between it project managers and traditional project managers.all projects are constrained by three factors
Emotional intelligence importance for project managersone : emotional intelligence importance for project managersone of the measurements of leadership is the eq emotional
Description of risk managementwrite a paper regarding a : description of risk managementwrite a paper regarding a project either real or fictitious where one is able to discuss
Given the following project to landscape a new building : given the following project to landscape a new building site.activityimmediate predecessoractivity
Project management of applicationsshow the role of the : project management of applicationsshow the role of the project manager in the in-house development of a customized
Project cash flow analysisyour company plans to produce a : project cash flow analysisyour company plans to produce a product for two more years and then to shut down production.
Earned value analysis - monitoring and controlling project : earned value analysis - monitoring and controlling project costonce your budget is planned and allocated across your
Question about milton manufacturing overhead activity based : question about milton manufacturing overhead activity based costingmilton manufacturing has four categories of

Reviews

Write a Review

Project Management Questions & Answers

  Describing the possible risk events for the project

Describe the possible risk events for the project. Identify the high probability, high impact risk events. For each of those risk events, identify the possible actions to mitigate the risk.

  Feel is the proper length of time for a project

How have the projects you have been involved in been concluded and what do you feel is the proper length of time for a project?

  Extimate project effort

Explain how to estimate effort. Discuss why it is so important to estimate projects correctly, and why overestimating projects can be just as detrimental as underestimating them.

  Describing phases of the project management

Process Phases and Knowledge Areas. Describe each of the phases of the project management process and its related knowledge areas. List the major activities in each phase.

  Virtual team and managing team

What are some ways to overcome the fear of losing control in these situations and what are some suggestions you can give when it comes to working in teams and dealing with communication in a virtual team?

  Keystone xl oil pipeline project corporation - income

keystone xl oil pipeline project corporation - income taxesyou have taken a job with the keystone xl oil pipeline

  Compare aon and gert techniques

Essay Question:  You are the project manager working on your project’s schedule. You are reviewing leads and lags. What are leads and lags? Please provide an example of each

  Extroversion quality of big five personality factors

In the Big Five personality factors, extroversion is considered a "good" quality to have. Why might introversion be an equally positive quality?

  Explain how increasing scrutiny and demand

Explain how increasing scrutiny and demand for accountability by the public has influenced reporting for not-for-profit and governmental entities

  Project managers facilitate procurement

How can project managers facilitate procurement?

  Prepare a project scope and schedule

Develop Project Scope and Schedule for Project Management - How would a consultant develop the project scope and schedule for Wal-mart?

  Stakeholders not communicate politely as project leader want

Stakeholders may not communicate as frequently or politely as a project leader prefers.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd