Given the following information for a one-year project

Assignment Help Project Management
Reference no: EM13363207

Given the following information for a one-year project, answer the following questions: Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $23,000; EV = $20,000; AC = $25,000; BAC - $120,000

Explain what is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?

Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

Use the schedule performance index (SPI) to estimate how long it will take to finish this project.

Reference no: EM13363207

Questions Cloud

Identify the risk the impact expected outcomethe course is : identify the risk the impact expected outcomethe course is corporate risk management.1 i have to make a risk register
Winsome manufacturing project scopeyou are a manager at : winsome manufacturing project scopeyou are a manager at winsome manufacturing company a company that produces plastic
Explanation of performance improvement projectshow a : explanation of performance improvement projectshow a performance improvement project you have been involved in or had
Is a project management certification without experience : is a project management certification without experience sufficient?if a person has been certified by a project
Given the following information for a one-year project : given the following information for a one-year project answer the following questions recall that pv is the planned
Difference between it project managers and traditional : difference between it project managers and traditional project managers.all projects are constrained by three factors
Emotional intelligence importance for project managersone : emotional intelligence importance for project managersone of the measurements of leadership is the eq emotional
Description of risk managementwrite a paper regarding a : description of risk managementwrite a paper regarding a project either real or fictitious where one is able to discuss
Given the following project to landscape a new building : given the following project to landscape a new building site.activityimmediate predecessoractivity

Reviews

Write a Review

Project Management Questions & Answers

  Best production plan for company selling antifreeze solution

pros or cons for a specific strategy in determining the best production plan for the company. Submit your answer by Tuesday, December 1, 2009 to this Discussion Area.

  Discuss about article obama administration criticizes

discuss about article obama administration criticizes jpmorgan over mortgagesthe article i chose this week obama

  State laws affected the employment selection process

How has the passage and enactment of numerous federal and state laws affected the employment selection process?

  Calculating production variable cost

Answer is following please explain how they calculated Production Variable cost 900, 2300,and 600.

  Disadvantages of using project management software

What do you see as the advantages and disadvantages of using project management software such as MS Project to organize a project

  Role of project manager and project sponsor

Role of the Project Manager and Project Sponsor - Explain what can the project sponsor do to help the project manager?

  Critical chain management and critical path management

Critical Chain Management vs. Critical Path Management: When is critical chain not critical path? Define how project and feeder buffers developed and how they are used.

  Types of contracts used in project management

How many types of contracts are used in project management, and which ones seem most fair and lucrative?

  Explain what degree of risk do you believe

Explain what degree of risk do you believe should be taken for a project and should there be a % cap rate, or bottom line value, or what?

  Explain how should a project manager handle a situation

Explain how should a project manager handle a situation in which the functional manager or employee appears to have more loyalty to his profession, discipline, or expertise than to the project

  Analyse and discuss differences between closing a project

Analyse and discuss the differences between closing a project that has met its objectives and closing one that was terminated early.

  Find the project sponsor we are allowed to use anyone even

find the project sponsor we are allowed to use anyone even make up a name amp customer. write 600-750 words about your

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd