Assignment:
McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:
Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:
Activities
OT
MT
PT
Activity 1
4
6
14
Activity 2
5
12
16
Activity 3
7
15
23
Activity 4
13
28
Activity 5
17
20
35
Activity 6
32
50
Activity 7
You must also do the following:
Which company paid its employees to volunteer in their communities two days a week after a tsunami in Japan disrupted operations at its U.S. facilities?
Which of the following four projects should Mountain Ski Corp. choose? Compute the coefficients of variation to help you make your decision.
Project Planning and Management - In spite of their poor cost performance, why do you think these projects were supported to their conclusion?
Describe How Attitudes Can Affect your Communication with Non-Natives - Explain what are the prevailing attitudes in your culture
provide a brief description of the key elements of an employee appraisal system which will contribute to changes in
Why do all the business units in an organization that use technology need to be involved in developing management information systems. How does that relate to the goal that a "knowledge-management repository" can be used throughout the organizatio..
Describe the beneficial aspects of conflict on a project and identify at least three of the six step conflict resolution process that a project manager can use
Was the sample size adequate?
successful project risk management change request1.explain how should a project manager respond to a change request
Risk is present in nearly every human undertaking and projects are no exception. Recall a project that you have participated in and name at least one risk that was recognized before it happened. What effect did it have on the project
The management of risk is proving to be one of the most difficult tasks for the project management profession. How can risk be managed effectively and who should be responsible for this task?
Linear and integer programming modeling
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd