Assignment:
McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:
Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:
Activities
OT
MT
PT
Activity 1
4
6
14
Activity 2
5
12
16
Activity 3
7
15
23
Activity 4
13
28
Activity 5
17
20
35
Activity 6
32
50
Activity 7
You must also do the following:
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd