The owner of a downtown parking lot has employed a civil engineering consulting frim to advise him on the economic feasibility of constructing an office building on the site. bill samuels, a newly hired civil engineer, has been assigned to make the analysis. he has assembled the following data

alternative total investment total net annual revenue

sell parking lot 0 0

keep parking lot 200,000 22,000

build 1 story building 400,000 60,000

build 2 story building 555,000 72,000

build 3 story building 750,000 100,000

build 4 story building 875,500 105,000

build 5 story building 1,000,000 120,000

the analysis period is be 15 years. for all alternatives, the property has an estimated resale(salvage) value at the end of 15 years equal to the present total investement.

(a) constuct a choice table for interest rate from 0% to 100%

(b)if the MARRR is 10%, what recommendation should bill make?

Reference no: EM13557086

Questions Cloud

Determine the force p in the coupling between the trailer an : The hydraulic braking system for the truck and trailer is set to produce equal braking forces for the two units. If the brakes are applied uniformly for 5 sec to bring the rig to a stop from a speed of 20 mph while moving down a 10 percent grade
Determine the rate of heat exchange between the human : A human with a surface area of 2 m^2 and a surface temperature of 27 degrees celcius radiates into a large room (which acts as a black body),
What is the exit state of the water : Water flows through a tube at a rate of 7.5 kg/min while heat is added to it at a rate of 4.5 kW. If water entered at 20 degrees celcius, determine the exit temperature. Assume the pressure remains constant at 1 atm throughout.
Estimate the standard deviation of the population : A sample of 10 television tubes produced by a company showed a mean lifetime of 1200 hours and a standard deviation of 100 hours. Estimate
Constuct a choice table for interest rate from 0% to 100% : The owner of a downtown parking lot has employed a civil engineering consulting frim to advise him on the economic feasibility of constructing an office building on the site. bill samuels, a newly hired civil engineer, has been assigned to make the a..
What maximum force can this person apply with this jack : A container of petrol on a set of scales is used to measure the rate at which fuel is used by an engine under test. In one test the weight measured by the scales decreases by 25.0 N in 1 hour. (Assume the specific gravity of petrol is 0.720 and g is ..
What is its speed at the point that the force resisting : This problem models an insertion process. Block A (mA = 2kg) is acted on by a horizontal force F (F = 12 N). As A moves to the right, it gets pressed more and more tightly in the channel.
How long will it take for the pce to reach the well : The water is pumped out of the aquifer at a rate of 2000 gpd, treat it with activated carbon and then put it back into the aquifer. At the flow rate how long until al the PCE is removed, assume carbon removed 100% of the PCE (ans. 54 days)
How long will it take the water in the aquifer to travel : A truck spils 1 gallon of benzene into an aquifer with an area= 50ft^2 Benzene has a solubility of 1750 ppm, and a specific gravity of 0.873. The aquifer ahs a porosity of 0.25, a hydraulic gradient of 0.004 and a hydraulic conductivity of 1000 gpd/f..

Reviews

Write a Review

Civil Engineering Questions & Answers

  Define concentration of pollutant in the effluent leaving

A lagoon with volume 1200 m^3 has been receiving a steady flow of a conservative waste at a rate of 100m^3/day for a long enough time to assume that steady-state conditions apply

  Determine the mass of the earth knowing that the mean radius

Determine the mass of the earth knowing that the mean radius of the moons orbit about the earth is 238.910mi and that the moon requires 27.32 days to complete one full revolution about the earth

  What the meaning of steady state

could you please help me to figure out what the meaning of steady state in the pavement management system preservation and rehabilitation.

  Calculate what is the volume of rock in the rock pile

A storage pile of crushed rock is 100ft by 100ft square at its base and 50 ft by 50 ft square on the top. The pile is 25 ft high. What is the volume of rock in the rock pile

  Determine a composite scs runoff curve number

Determine a composite SCS runoff curve number for a 600-acre basin that is totally within soil group C. The land use is 40 percent contoured row crops in poor hydrologic condition and 60 percent native parture in fair hydrologic condition.

  Ehermal conductivity of the radioactive wastes

The outer surface of the tank is cooled by air at 300 K with a heat transfer coefficient of 100 W/m2K. Determine the maximum temperature in the tank. Take the thermal conductivity of the wastes as 2.0 W/mK.

  What error results from curvature and refraction

Successive plus and minus sights taken on a downhil line of levels are listed below. the values represent the horizontal distances between the instrument and either the plus or minus sights. What error results from curvature and refraction?

  What is the minimum time it will take for all the taxol to

The molecular diffusion coefficient of taxol in fluid blood is Dab=1.0*10^-6 cm2/s. A) what is the convective mass transfer coefficient, kc around the outer surface of the cylindrical portion of the stent, for the solute Taxol?. B) what is the minimu..

  Determine what is the channel and flow classification

An obstruction is lodged in a 10-ft wide rectangular channel (n = 0.022) that has a botom slope of 0.005. The depth of the channel just upstream of the obstruction is 5.0 ft. If the flow rate is 325 cfs, what is the channel and flow classification

  Determine the centroid for the region bounded by x-axis

Determine the centroid for the region bounded by the x-axis, the curve y=x^3, and the line x=3

  How to calculate the minimum length of the curve

The minimum clearance between the roadway and the waterline must be 6 feet. The PVI is located at station 19+00.00 with elevation 420.50 feet. The design speed of the curve is 55 mph, g1 is +3%, and g2 is -3.0%. PRT= 2.5 sec, 0.35 = friction facto..

  Determine the minumum coeffeicient of friction

A water jet of diameter 2 inches and speed of v=60 ft/s is filling a tank at a 70 degree angle. The tank has a mass of 25 lbm and contains 6 gallons of water. The water temperature is 70 degrees F.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd