Q1.
Table 1 indicates the sequence and interdependence of the 10 activities (A - K) which together are required to develop a bespoke system. The durations (in weeks) of each of the activities are given in the table
Activity
Description
Duration (wks)
Precedence
A
Requirement Gathering
27
-
B
Business Analysis
24
C
Systems Analysis
21
D
Coding
E
Unit Test
22
F
Module Testing
G
Systems Testing
H
User Acceptance Testing
G,E
J
Implementation
K
Handover
23
D, J
(a) Construct a network diagram identifying the following:
i. Earliest Start Time(EST)ii. Latest Finish Time (LFT)iii. Total Float on each activities D, F & Jiv. Critical Path for the project
b) Assume that there is a delay of 3 weeks in completing activityH. Analyseone action that the Operations Manager could take to avoid exceeding the current length of the critical path.
Q2.
The resource-based view of the firm is one of the most influential current theories in operations strategy (Slack, 2007). Critically evaluate and argue how firms' should consider resource based view during the location selection process?
Differentiate and accurately distinguish between the need for organised interaction between the role of design and management within operations strategy.
Word count:1500
Distribution strategy and project management
Identify "Risk" in project management
What do you understand by the term Scheduling? Explain how the following ways for duration compression of a project can be achieved- Fast tracking Crashing
Criticism of traditional measures of performance
You are the project manager of a leading textile engineering company. The company opened its door in year 2000. Today, after 13 years of existence, it is being challenged with a loss in profitability approximating a 65% loss in net revenue
To evaluate the performance of each project proposal with respect to their Overall
Discuss relevance of Re-Work in Project Management.
Critically analyse the concept of risk; discuss how it can be measured and ranked and outline how a project risk management strategy may be constructed.
Analysis of the overall project risk
You are required to submit a written assignment relating to New Product Development.
Norman Harvey Bank in order to immediately invest the entire $20,000 into the West Bank term deposit account being offered.
Using a relevant product within the hospitality or tourism sector answer the three following questions. Define the term product. Describe the four main product levels that applies to your chosen product.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd