Q1.
Table 1 indicates the sequence and interdependence of the 10 activities (A - K) which together are required to develop a bespoke system. The durations (in weeks) of each of the activities are given in the table
Activity
Description
Duration (wks)
Precedence
A
Requirement Gathering
27
-
B
Business Analysis
24
C
Systems Analysis
21
D
Coding
E
Unit Test
22
F
Module Testing
G
Systems Testing
H
User Acceptance Testing
G,E
J
Implementation
K
Handover
23
D, J
(a) Construct a network diagram identifying the following:
i. Earliest Start Time(EST)ii. Latest Finish Time (LFT)iii. Total Float on each activities D, F & Jiv. Critical Path for the project
b) Assume that there is a delay of 3 weeks in completing activityH. Analyseone action that the Operations Manager could take to avoid exceeding the current length of the critical path.
Q2.
The resource-based view of the firm is one of the most influential current theories in operations strategy (Slack, 2007). Critically evaluate and argue how firms' should consider resource based view during the location selection process?
Differentiate and accurately distinguish between the need for organised interaction between the role of design and management within operations strategy.
Word count:1500
Critically analyse the concept of risk; discuss how it can be measured and ranked and outline how a project risk management strategy may be constructed.
Formulate a reasonable Investment Policy Statement
Describe the features or characteristics of your product or service.
Write a paper which explore Results Based Management topic and how it plays the role of project management in development.
The Work Breakdown Structure (WBS) subdivides the scope of work into manageable work packages that can be reliably estimated and assigned to a responsible person for completion. Discuss five uses of a WBS in Project Management
What are the activities that are related to the Management of Project Execution? (b) Monitoring is an aspect of Project Management performed throughout the Project. What are the factors that influence the monitoring and control of project work?
Identify "Risk" in project management
Explain meaning of contingency fee.
Design an online system for the human resources department to manage available job positions.
Questionaire on Project Management
Write a report on Managerial Roles and Gap Analysis
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd