Q1.

Table 1 indicates the sequence and interdependence of the 10 activities (A - K) which together are required to develop a bespoke system. The durations (in weeks) of each of the activities are given in the table

Activity

Description

Duration (wks)

Precedence

A

Requirement Gathering

27

-

B

Business Analysis

24

-

C

Systems Analysis

21

-

D

Coding

21

A

E

Unit Test

22

B

F

Module Testing

27

C

G

Systems Testing

22

F

H

User Acceptance Testing

22

G,E

J

Implementation

22

H

K

Handover

23

D, J

(a) Construct a network diagram identifying the following:

i. Earliest Start Time(EST)
ii. Latest Finish Time (LFT)
iii. Total Float on each activities D, F & J
iv. Critical Path for the project

b) Assume that there is a delay of 3 weeks in completing activityH. Analyseone action that the Operations Manager could take to avoid exceeding the current length of the critical path.

Q2.

The resource-based view of the firm is one of the most influential current theories in operations strategy (Slack, 2007). Critically evaluate and argue how firms' should consider resource based view during the location selection process?

Differentiate and accurately distinguish between the need for organised interaction between the role of design and management within operations strategy.

Word count:1500

Reference no: EM135245

Reviews

Write a Review

 

Project Management Questions & Answers

  Distribution strategy and project management

Distribution strategy and project management

  Identify Risk in project management

Identify "Risk" in project management

  What do you understand by the term scheduling

What do you understand by the term Scheduling? Explain how the following ways for duration compression of a project can be achieved- Fast tracking Crashing

  Criticism of traditional measures of performance

Criticism of traditional measures of performance

  What do you understand by net present value

You are the project manager of a leading textile engineering company. The company opened its door in year 2000. Today, after 13 years of existence, it is being challenged with a loss in profitability approximating a 65% loss in net revenue

  Evaluate the performance of each project proposal

To evaluate the performance of each project proposal with respect to their Overall

  Discuss relevance of re-work in project management

Discuss relevance of Re-Work in Project Management.

  Evaluate the use of complex models of project risk

Critically analyse the concept of risk; discuss how it can be measured and ranked and outline how a project risk management strategy may be constructed.

  Analysis of the overall project risk

Analysis of the overall project risk

  New product development

You are required to submit a written assignment relating to New Product Development.

  Time value of money related finance methods

Norman Harvey Bank in order to immediately invest the entire $20,000 into the West Bank term deposit account being offered.

  Define the term product

Using a relevant product within the hospitality or tourism sector answer the three following questions. Define the term product. Describe the four main product levels that applies to your chosen product.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd