Joints in concrete pavements, Civil Engineering

Joints in Concrete Pavements:

Concrete pavements in India are of the jointed plain (unreinforced type). The following types of joints are needed in them :

(a) Transverse Contraction Joints

(b) Longitudinal Joints

(c) Expansion Joints

Transverse contractions are provided at 3.5-5.0 m spacing for relieving the tensile stress induced when the temperature of the concrete falls below the laying temperature. The modern practice is to lay the slab continuously and cut the transverse joints to a depth of 1/3rd the slab thickness by a joint cutting saw, and allow the crack to travel downwards in due course. A dowel bar is provided to transfer the load. For low volume roads, the dowel bars are omitted and the load transfer takes place by aggregate interlock. A sketch of a contraction joint is given in Figure. The joint is sealed with a sealant.

1853_Joints in Concrete Pavements.png

Figure: Contraction Joint

Longitudinal joints are provided on pavements which are wider than one lane to relieve warping stresses. They are also cut by joint cutting saws. Tie rods are provided to prevent the adjoining slabs from separating. The joints also need to be sealed. A sketch of a longitudinal joint is given in Figure.

1809_Joints in Concrete Pavements1.png

Figure: Expansion Joint

Expansion joints are provided to allow for the expansion of slabs. The current practice is to provide expansion joints only at culverts and bridges. A typical expansion joint is shown in Figure.

549_Joints in Concrete Pavements2.png

Figure: Longitudinal Joint with Tie Bar

Posted Date: 1/22/2013 4:56:03 AM | Location : United States







Related Discussions:- Joints in concrete pavements, Assignment Help, Ask Question on Joints in concrete pavements, Get Answer, Expert's Help, Joints in concrete pavements Discussions

Write discussion on Joints in concrete pavements
Your posts are moderated
Related Questions
Cross-sectional Elements: The terms used in the cross-section of a road are : Carriageway The portion where traffic moves. Shoulder The portion outside the ca

Q. There is a railway colony of 500 house holds source of water is from a tube well 800 m away. The colony is 10 m higher then the ground at source. Tube well is 60 meters deep. De

IN CASE CUBE IS FAIL WHAT CAN IDO


Calculate the Total Area (acre) for Lot A 30-ft wide parabolic shaped stream divides the property as shown.  The total area (acre) for Lot 6 is most nearly: Solution:


Explain Some Points regarding to Hardness 1) Hardness removal using lime and soda is based on the solubility reactions of calcium carbonate, CaCO 3 and magnesium hydroxide, Mg

how tofind centroid of cercular arc

Define the Precedence Diagramming Methods a) Activity on Node (AON) with arrows for dependencies b) Uses all forms of precedence relationships

A wastewater plant is operating at 10MGD with a suspended solids concentration of 200mg/L. It has 6 clarifiers operating in parallel. Each clarifier is 40 foot in diameter and 10 f