Joints in concrete pavements, Civil Engineering

Joints in Concrete Pavements:

Concrete pavements in India are of the jointed plain (unreinforced type). The following types of joints are needed in them :

(a) Transverse Contraction Joints

(b) Longitudinal Joints

(c) Expansion Joints

Transverse contractions are provided at 3.5-5.0 m spacing for relieving the tensile stress induced when the temperature of the concrete falls below the laying temperature. The modern practice is to lay the slab continuously and cut the transverse joints to a depth of 1/3rd the slab thickness by a joint cutting saw, and allow the crack to travel downwards in due course. A dowel bar is provided to transfer the load. For low volume roads, the dowel bars are omitted and the load transfer takes place by aggregate interlock. A sketch of a contraction joint is given in Figure. The joint is sealed with a sealant.

1853_Joints in Concrete Pavements.png

Figure: Contraction Joint

Longitudinal joints are provided on pavements which are wider than one lane to relieve warping stresses. They are also cut by joint cutting saws. Tie rods are provided to prevent the adjoining slabs from separating. The joints also need to be sealed. A sketch of a longitudinal joint is given in Figure.

1809_Joints in Concrete Pavements1.png

Figure: Expansion Joint

Expansion joints are provided to allow for the expansion of slabs. The current practice is to provide expansion joints only at culverts and bridges. A typical expansion joint is shown in Figure.

549_Joints in Concrete Pavements2.png

Figure: Longitudinal Joint with Tie Bar

Posted Date: 1/22/2013 4:56:03 AM | Location : United States







Related Discussions:- Joints in concrete pavements, Assignment Help, Ask Question on Joints in concrete pavements, Get Answer, Expert's Help, Joints in concrete pavements Discussions

Write discussion on Joints in concrete pavements
Your posts are moderated
Related Questions
The stresses at failure on the failure plane in a cohesionless soil mass were: Shear stress = 4 kN/m 2 ; normal stress = 10 kN/m 2 . Verify the resultant stress on the failure plan

Define the Ignitability - Hazardous Waste - is a liquid with flash point - Not a liquid and capable of spontaneous and sustained combustion under normal conditions - Ign

Define the term - prestressing force It should be realized that the maximum amount of prestressing force which can be  transferred from tendons to concrete depends on the bond

WHAT IS RCC

My team has to construct a swimming pool at the back of the house. It’s interior dimensions are 10M x 3M and 1M at the shallow end and 2.5M at the deep end. The walls and the bas

elastic curve of a simply supported beam with triangular load

With a clear sketch indicate the system of protection of line for works of short duration where ‘ Stop dead restriction' need to be observed on a single line section on a BG track.


Explain the important factors affecting the design of pavement?

Q. Write short note on Stock Verification? It is desirable that there should be a frequent reconciliation of the balances as shown in the numerical ledgers kept by the subordin