30,000-yd3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite. The soil has 28% swell and shrinkage of 18%. The final volume of the compacted soil is most nearly:
Solution: Shrinkage is measured with respect to the bank condition.
Apply the equation:
Vcompacted = [100% - % shrinkage/100%] Vbank
Vcompacted = [100% - 18%/100%] (30,000-yds3) = 24,600 - yd3
Landslides induced by rainfall After rainfall, groundwater pressure is built up and this elevates ground water table. Water inside the pores of soil reducesthe effective stres
Determine the quantity of materials required per batch and probable output from a concrete mixing plant of 1200lts capacity. The design per 1000lts of mixed concrete is as follows
physics meaning of permitivity
Enumerate the term - Failure Due to Crushing of Concrete Over reinforced pre-stressed concrete members, provided with a large amount of pre-stressing steel or relatively small
what is the classification of lintel
Define Physical deterioration - underwater inspection of bridges Typical defects include: - Scaling - Cracking - Spalling - Disintegration - Abrasion
Q. Settlement due to Increasing Load on Surrounding Soil? When any portion of the ground surface has been loaded, it causes the surface of adjacent soil also to tilt and set
what are port facilities
why water is necessary for concrete
how are vectors used in civil engineering
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd