PERT/CPM problem with three (3) time estimates

A project is composed of 8 tasks. The three-time estimates (in days) for each activity plus the precedence requirement for each are shown in the table below:

Activity Activity Time Estimates
(in days) ImmediatePredecessor
A 2, 3, 4 None
B 3, 4, 11 None
C 1, 2, 3 A, B
D 4, 5, 12 C
E 3, 5, 7 C
F 2, 3, 4 E
G 2, 3, 10 C
H 2, 3, 4 D, G, F
I 2, 3, 10 D, F
J 1, 2, 3 H
K 1, 2, 3 I, J

A. Draw a network for the project using AON method.

B. Determines the critical path(s) and identify them by a) double lining the arrows connecting the activities on the CP (like ===) AND b) writing the letter representing the activities on the CP in the answer-sheet-set.

C. Do a complete path analysis and fill the table in the answer-sheet set

D. What are the chances that the project will finish within 25 days?

E. What are the chances that the project will take longer than 23 days to finish?

Reference no: EM13363235

Questions Cloud

Project proposalsits a busy monday morning and you have : project proposalsits a busy monday morning and you have work to assign to others and to complete yourself. of the tasks
Scheduling and project management of dellshow how project : scheduling and project management of dell.show how project management influences other departments and functions of
Project planning breakdown structure and controlshow what : project planning breakdown structure and controlshow what controlling measures should be taken during the planning
A project has several activities these activities are shown : a project has several activities. these activities are shown in the table below together with their time estimates in
Pertcpm problem with three 3 time estimatesa project is : pertcpm problem with three 3 time estimatesa project is composed of 8 tasks. the three-time estimates in days for each
Fortran corporation would you recommend that the project be : fortran corporation would you recommend that the project be adopted?suppose the going market rate of interest on high
Explain in your own words how heredity and environmental : explain in your own words how heredity and environmental forces have combined to affect your development. give one
Grainger manufacturing inc produces outdoor grills on march : grainger manufacturing inc. produces outdoor grills. on march 31 the company had 120 grills in inventory. the companys
What controlling measures should be taken during the : what controlling measures should be taken during the planning phase. then provide a generic method for creating a

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd