What is the station at point b, Civil Engineering

Assignment Help:

What is the station at Point B?

70_What is the station at Point B.png

SOLUTION 3

Station at Point A = Sta 22+45 

Station at Point B = (Sta 22+45) + 1028' = 2245'+1028' =3273' 

= Sta 32+73


Related Discussions:- What is the station at point b

Drawing, how to draw an elipse

how to draw an elipse

Strenght of meterials 2, Difference between direct and bending stress diagr...

Difference between direct and bending stress diagrams

Explain the strength design (lrfd), Explain the Strength Design (LRFD)   ...

Explain the Strength Design (LRFD)   1. γ Factors are applied to loads and φ factors applied to resistance. 2. Unfactored service loads receive a load factor γ > 1.0

Hydraulics, In this question we consider a bended outlet of pipe flow AB. E...

In this question we consider a bended outlet of pipe flow AB. End A is attached to an incoming pipe by a flange connection. The pipe diameter at A is the same as the incoming pipe,

Describe types of spurs, Q. Describe types of Spurs? Spurs can be of va...

Q. Describe types of Spurs? Spurs can be of varied types. They may be either permeable or impermeable. Permeable spurs are open structures constructed by driving wooden balties

Consolidated undrained or consolidated drained analysis, Question In de...

Question In determining effectual stress parameters of a soil sample, which test is good, consolidated undrained analysis or consolidated drained analysis? Answer Effec

Explain the term - untensioned reinforcement, Explain the term - Untensione...

Explain the term - Untensioned Reinforcement In prestressed concrete construction, use of untensioned reinforcement also has to be made alongwith tendons. This is essential as

What is shock transmission unit in bridges, Q. What is Shock transmission u...

Q. What is Shock transmission unit in bridges? Shock transmission unit is fundamentally a device connecting separate structural units. It's characterized by its ability to tran

Concrete, Determine the quantity of materials required per batch and probab...

Determine the quantity of materials required per batch and probable output from a concrete mixing plant of 1200lts capacity. The design per 1000lts of mixed concrete is as follows

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd