What is the safe bearing capacity of wide strip footing, Civil Engineering

Assignment Help:

A loading test was conducted with a 300 mm square plate at depth of 1 m under the ground surface in pure clay deposit. The water table is situated at a depth of 4 m below the ground level. Failure occurred at a load of 45 kN.

What is the safe bearing capacity of a 1.5 m wide strip footing at 1.5 m depth in the similar soil?

 


Related Discussions:- What is the safe bearing capacity of wide strip footing

Survey question, Sir morng..i know about WCB AND RB.With diagram..pls help ...

Sir morng..i know about WCB AND RB.With diagram..pls help me sir

Calculate the tension force in sling - lifting load, Calculate the Tension ...

Calculate the Tension Force in Sling The rigging configuration shown below will be used to lift a bridge girder using a 200-ton capacity luffing jib crane onto the foundation a

Show the benefits of adopting marine fill, In reclamation involving large v...

In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material?  There are two

Define the abrasion - underwater inspection of bridge, Define the Abrasion ...

Define the Abrasion - underwater inspection of bridge? Abrasion damage is caused by continuous action of external forces on the surface of the concrete element. Erosive action

Types of cross-drainge structures, Types of Cross-drainage Structures: ...

Types of Cross-drainage Structures: The following are the types of cross-drainage structures : (a) Culverts, having waterway upto 6 m. (b) Minor Bridges, having waterwa

Digit of cells for concrete box girder bridges, Question How does an engine...

Question How does an engineer determine digit of cells for concrete box girder bridges ? Answer If depth of a box girder bridge exceeds 1/6 or 1/5 of bridge width, then it is o

Calculate the uniformly distributed load, Given: pretensioned rectangula...

Given: pretensioned rectangular beam b=6" h=20" f'c=4000psi f'ci=3000psi fti=.165ksi fts=.38ksi fci=1.8ksi fcs=1.8ksi R=0.80 Required: (a)Pi and e to maximize Md+

Calculate the amount of concrete - construction management, An electrical c...

An electrical contractor is preparing to place the duct bank concrete encasement for the high voltage feeders between manhole # 11 and # 12, total distance is 323-ft. The duct bank

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd