What do you mean by instrument transformers, Electrical Engineering

Assignment Help:

Q. What do you mean by Instrument transformers?

These are generally of two types, potential transformers (PTs) and current transformers (CTs). They are designed in such a way that the former may be regarded as having an ideal potential ratio, whereas the latter has an ideal current ratio. The accuracy ofmeasurement is quite important for ITs that are commonly used in ac circuits to supply instruments, protective relays, and control devices.

PTs are employed to step down the voltage to a suitable level, whereas CTs (connected in series with the line) are used to step down the current for metering purposes. Often the primary of a CT is not an integral part of the transformer itself, but is a part of the line whose current is being measured. In addition to providing a desirable low current in the metering circuit, the CT isolates the meter from the line, which may be at a high potential. Note that the secondary terminals of a CT should never be open-circuited under load. The student is encouraged to reason and justify this precaution. One of the most useful instruments for measuring currents in the ampere range is the clip-on ammeter combining the CT with one-turn primary and the measurement functions.


Related Discussions:- What do you mean by instrument transformers

Explain the operation of the counter, Q. Figure shows the mod-8 counter whi...

Q. Figure shows the mod-8 counter which counts from 010 to 710 before resetting. Explain the operation of the counter and sketch the timing diagram.

Derive the expression for steady state error, Derive the mathematical expre...

Derive the mathematical expression for steady state error of first order system with unit ramp signal. Discuss the following - proportional cum integral control - proporti

Which interrupt has the highest priority, TRAP has the maximum priority ...

TRAP has the maximum priority There are 2 types of interrupts external and internal. NMI has highest priority between all external interrupts,TRAP has highest priority between

E. mechanics, a train weight 5 megaN is taking a slope of 1 in 200 at 45 km...

a train weight 5 megaN is taking a slope of 1 in 200 at 45 kmper hour.the engine put in 100 kw.determine the power to be put in by the engine it the train take the slope up of 1 in

Repeatability , Reproducibility and repeatability are measures of closeness...

Reproducibility and repeatability are measures of closeness with which a given input may be measured over again. The two terms cause confusion. Therefore, a distinction is made bet

Determine the load voltage and the armature current, Q. Two shunt generator...

Q. Two shunt generators operate in parallel to supply a total load current of 3000 A. Each machine has an armature resistance of 0.05and a field resistance of 100. If the generat

Discuss in brief on combination clippers, Q. Discuss in brief on combinatio...

Q. Discuss in brief on combination clippers ? Combination clippers are a combination of biased positive and negative clippers. With a combination clipper, a portion of both pos

Define johnson counters to produce a time delay, Define Johnson Counters to...

Define Johnson Counters to Produce a Time Delay? The "serial in-serial out" shift register can be used as a time delay device. The amount of delay able to be controlled by:

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd