Protection of lorry on the line, Civil Engineering

Assignment Help:

i. On single line by one or two men as required following and proceeding the lorry at a distance of 600 m. on the BG and 400 m. on the MG & NG carrying a banner flag across the track and another man plainly showing a stop hand signal at a distance of not less then 1200 m. on the BG and 800 m. on the MG & NG from the lorry on either side.

ii. Each man shall be provided with detonators and place three on the line 10 m. apart immediately the lorry comes to a stand & fix the Banner flag across the track.

iii. In all cases where flag man in advance or in rear can not be kept in view from the lorry additional intermediate flag man shall be posted to relay the signals.


Related Discussions:- Protection of lorry on the line

Enumerate the term - superposing the stress variations, Enumerate the term ...

Enumerate the term - superposing the stress variations If the case of concentric pre-stressing is considered, we can appreciate that stress at any section of the beam is compr

Sieve analysis - soil mechanics and foundations, Sieve Analysis - Soil Mech...

Sieve Analysis - Soil Mechanics and Foundations a. Sieve Analysis used to obtain the grain size distribution of coarse-grained soils (sands and gravels) larger than 0.075 mm (r

Calculate benefit cost ratio for government project, Calculate the Benefit-...

Calculate the Benefit-Cost Ratio for Municipal Government Project With interest at 10%, the benefit-cost ratio for this municipal government project is most nearly:   Initia

What is the liquidity index, A soil has a plastic limit of 25% and a plasti...

A soil has a plastic limit of 25% and a plasticity index of 30. If the natural water content of the soil is 34%, what is the liquidity index and what is the consistency index? H

#title, define distribution factor and shape factor

define distribution factor and shape factor

Bituminous macadam, Bituminous Macadam: Bituminous Macadam (BM) is a ...

Bituminous Macadam: Bituminous Macadam (BM) is a base course in which coarse aggregates are mixed with a bituminous binder. The mix is open-graded with 20-25 per cent voids.

Road pavement, whatis difference between premix asphalt carpeting and aspha...

whatis difference between premix asphalt carpeting and asphalt concrete pavement

Force systems and equlibrium, write short notes about force systems and equ...

write short notes about force systems and equilibrium

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd