bridge engineering, Civil Engineering

Assignment Help:
long span bridge or continuous bridge which is more preferable and why ???
what is the major problem in continuous bridge and what would be its effect if there is any differential settlement?????

Related Discussions:- bridge engineering

How can we reduced frictional losses, How can we reduced frictional losses ...

How can we reduced frictional losses Frictional losses can be reduced by several methods, such as : (a) Over-tensioning the tendons by an amount equal to the maximum frictio

Aggregaters, What Aggregate''s class III

What Aggregate''s class III

What is the dry density, Q. The field density of a compacted fill is deter...

Q. The field density of a compacted fill is determined by means of a core cutter whose empty weight is 1000 g and volume is 1000 cm 3 . The cutter full of soil weights 2890 g. If

Assignment, Need assignment for structure concrete work

Need assignment for structure concrete work

Live project, any type of civil live project at hyderabad

any type of civil live project at hyderabad

Fixed and pinned connection between piles and pile caps, Q. Fixed vs pinned...

Q. Fixed vs pinned connection between piles and pile caps? The type of connection amid piles and pile caps affects the load carrying capacity of pile groups. Fixity of pile hea

Water or hydraulic horsepower (whp), Water Or Hydraulic Horsepower (whp) ...

Water Or Hydraulic Horsepower (whp) The work performed by a pump is a function of the head added by the pump (h A ), the flow rate required (Q) and the mass of the fluid (accou

Importance of racking load for a pre-stressed concrete beam, Importance of ...

Importance of racking load for a pre-stressed concrete beam Evaluation of cracking load for a pre-stressed concrete beam member is important for the following cases/reasons.

Graphics, 1. Draw the projections of a line AB that is 50 mm long and is pa...

1. Draw the projections of a line AB that is 50 mm long and is parallel to both the HP and the VP. The line is 40 mm above the HP and 25 mm in front of the VP. 2. A line AB, 50 mm

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd