Determine the common ways to present the project schedule, Civil Engineering

Assignment Help:

Common ways to present the project schedule include all except:

a. Gantt charts

b. Milestone charts

c. PERT charts

D. Project Network Diagrams with dates added  

Solution:  A PERT chart represents task dependencies but does not represent activity durations or dates.


Related Discussions:- Determine the common ways to present the project schedule

Concrete, if the slump of concrete drops how to rectify

if the slump of concrete drops how to rectify

Determine the basic concepts of prestressing, Determine the Basic Concepts...

Determine the Basic Concepts  of Prestressing In the year 1904, Freyssinet tried to introduce prestresses in concrete to resist stresses developed due to external loads. Later,

Show the purpose of granular bedding for concrete pipes, Q. Show the Purpos...

Q. Show the Purpose of granular bedding for concrete pipes? When designing the bedding for concrete drainage pipes, granular materials are generally specified in place of soils

Wrecked trusses and types of damages, Evaluation of various reports regardi...

Evaluation of various reports regarding the effects of earthquake on spatial trusses Types of damages According to the different types of damages, wrecked trusses can be d

The material that have lowest resistivity is , The material that have lowes...

The material that have lowest resistivity is Answer: Silver is the material

Explain foundation design discharge for a bridge, Q. Explain Foundation des...

Q. Explain Foundation design discharge for a bridge? To provide for an adequate margin of safety against any abnormal flood exceeding the design discharge (Q), the foundations,

Increasing concrete cover beyond contractual, Question If contractor sugges...

Question If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion? Answer In contractual part, based on requir

Preloading - control of settlements, Q. Preloading - Control of settlements...

Q. Preloading - Control of settlements? This method consists of loading the soil strata by a load intensity which will be equal to or higher than the expected load intensity. T

Chemical analysis of fe 415., in this chemical analysis what is the meaning...

in this chemical analysis what is the meaning of c% and s% and P%

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd