Common ways to present the project schedule include all except:
a. Gantt charts
b. Milestone charts
c. PERT charts
D. Project Network Diagrams with dates added
Solution: A PERT chart represents task dependencies but does not represent activity durations or dates.
what will be the w/c ration and cement/fly ash ration for the particular mix design
classification of foundation
On-line storage vs. off-line storage Design of storage pond is commonly divided into off -line storage and on-line storage. The on-line storage concept includes inclusion of s
A masonry retaining wall is 1.5 m wide at the top, 3.5 m wide at the base and 6 m high. It is trapezoidal in section and has a vertical face on the earth side. The backfill is leve
Q. Show the Settlement due to Vibration? The foundation resting on cohesionless soil and subjected to vibrations will result in settlements of higher magnitude. In sandy soil
Explain the Anti Slip Devices - Bridge Bearing? It has been explained earlier that elastomeric bearings have a tendency to slip if the minimum normal pressure is less than 2 MP
3-d figure of line ranger
how to make a home
Explain the term - Uniaxial - Biaxial -Triaxial Prestressing These terms refer to cases when the concrete is prestressed in only one direction, in two mutually perpendicular di
define couple
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd