Common ways to present the project schedule include all except:
a. Gantt charts
b. Milestone charts
c. PERT charts
D. Project Network Diagrams with dates added
Solution: A PERT chart represents task dependencies but does not represent activity durations or dates.
pariods of one hundred years
to find height difference between two or more points in different conditions
How to calculate economic span of ss bridge
Define Cast iron substructure - Inspection of bridge? Cast Iron also has the problem of corrosion due to atmosphere, which is similar to that of steel. However, in acidic or br
For a system or Net Work Done = Net Heat Added
Q. Explain about Overhauling of Level xing? Each level crossing except those laid with PSC sleepers must be opened out and the condition of sleepers and fittings, rails and fas
Question Would a sub-base layer be served as a drainage layer to take away water from pavement? Answer As well providing load distribution in post-construction stage a
What practical steps can one take to mitigate the adverse effects in using aggregates with higher than specified flakiness index in the production of concrete
Question What is the reason that vibrators not used in concrete compaction in piling works ? Answer Concrete for piles must be a high-slump self-compacting mix that i
what are the characteristics of the beam to column connection?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd