Determine the common ways to present the project schedule, Civil Engineering

Assignment Help:

Common ways to present the project schedule include all except:

a. Gantt charts

b. Milestone charts

c. PERT charts

D. Project Network Diagrams with dates added  

Solution:  A PERT chart represents task dependencies but does not represent activity durations or dates.


Related Discussions:- Determine the common ways to present the project schedule

Surveying, with a neat well labelled sketch, explain reciprocal ranging.

with a neat well labelled sketch, explain reciprocal ranging.

What is the pre-tensioned concrete, What is the Pre-tensioned concrete ...

What is the Pre-tensioned concrete In Pre-tensioned concrete tendons are kept stretched with suitable mechanisms and concrete is cast into the forms through which stretched ten

Determine the total stopping sight distance in feet, Determine the total St...

Determine the total Stopping Sight Distance in feet A motorist is travelling down a 6% grade at 65 mph and needs to stop because of a crash scene.  Assuming a 2.0 sec PRT and 1

Factors determining the stability of a single armour unit, Q. Factors deter...

Q. Factors determining the stability of a single armour unit There are mostly three major factors that govern the stability of an armour unit, viz gravity, intertangling and s

Cement Sand Plaster, How to use plaster cement in sand?  Cement sand pl...

How to use plaster cement in sand?  Cement sand plaster is a layer of cement & sand mortar that is applied over walls made of brickwork, cement block work, RCC walls and RCC co

What do you mean by plain elastomeric pads, Q. What do you mean by Plain el...

Q. What do you mean by Plain elastomeric pads? Plain pads are used for light or moderate loadings. Plain pads have a tendency to bulge under heavy loadings. In order to reduce

Define the cost of shock transmission unit, Define the Cost of shock transm...

Define the Cost of shock transmission unit? There is a keen competition among the few STU manufacturers. For the second Bassein Creek Bridge, the average cost of two STUs of ca

Explain the modular incinerators, Explain the Modular Incinerators 1. P...

Explain the Modular Incinerators 1. Prefabricated units with capacities of 4.5 to 107 tons of solid waste/day 2. Most use a system involving two combustion chambers.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd