Meter Field Testing - Sealing Points

The meter seal should be tamper proof. The consumer should be briefed about seals. The sealing of all metering systems should be completed at several points (as applicable) to prevent tampering. There should be at least one seal at all points described below (wherever applicable):

a) CT Secondary Boxes (further to locking arrangement)

b) PT Secondary Box (further to the locking arrangement)

c) Meter Cabinet

d) Meter Test Block

e) Meter Terminal Cover

f) Meter Cover

g) Panel doors where CT and PT secondary circuits are terminated or whereas possibility for shorting or breaking exists and fuses/links are given.

h) PT selector relay box where automatic change-over of potential supply to meter from one PT to another is given

i) CT Primary Links and Top Covers

j) MD Reset Push Button

k) Boxes/Cabinets containing terminals for remote transmission of metered data through communication channels, junction boxes in the system and boxes wherein interface devices are mounted.

l) Meter reading port.

Seals are essential to guard against the tampering of connections and internal elements of a meter. Tampering of seals will provide consumers access to the relevant part of a meter installation where s/he could manipulate the unit to record less energy leading to commercial loss. A seal is placed to detect unauthorized entry to the meter internals. The effectiveness of the seal depends on the category of seal (whether it is tamper proof or not, whether a duplicate could be acquired or not, etc.), and the procedures used in tracking the seals.


Related Discussions:- Meter field testing - sealing points

Compute the full-load speed, A 10 - hp, 250-V shunt motor has an armature c...

A 10 - hp, 250-V shunt motor has an armature circuit resistance of 0.5  and a ?eld resistance of 200 . At no load, rated voltage, and 1200 r/min, the armature current is 3 A. At

Points of verification, Points of Verification of Connection i) Phase...

Points of Verification of Connection i) Phase association ii) CT polarity iii) VT polarity iv) Phase angles v)  Phase sequence vi) System conditions - unbalanc

#title. electronic project for invention, I need assistance in building a c...

I need assistance in building a circuit for my invention ,I am a electronic tech with limited knowledge but designing and building a proto model is a little out of my expertise ce

Determine the parameters of the equivalent circuit, No-load and blocked-rot...

No-load and blocked-rotor tests are conducted on a three-phase,wye-connected inductionmotor with the following results. The line-to-line voltage, line current, and total input powe

generator, diagram of static generator

diagram of static generators

What is memory paging, What is memory paging? The memory paging mechan...

What is memory paging? The memory paging mechanism located inside the 80386 and above permits any physical memory location to be assigned to some linear address.

What is message demodulation, Q. What is Message Demodulation? The majo...

Q. What is Message Demodulation? The major advantage of the conventional (standard) DSB AMsignal transmission is the ease with which the signal can be demodulated. Themessage s

Determine IS in the given circuit, Q. Given that V 0 = 10 V, determine IS ...

Q. Given that V 0 = 10 V, determine IS in the circuit drawn in Figure.

\, Refer to Figure 100. Assume MKS units. Given: R1= 4, R2=14, R3= 9, I4...

Refer to Figure 100. Assume MKS units. Given: R1= 4, R2=14, R3= 9, I4= 8, I5= 7. Determine: Ieq, Req, and V3.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd