Increasing concrete cover beyond contractual, Civil Engineering

Assignment Help:

Question
If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion?

Answer
In contractual part, based on requirement of General Specification of Civil Engineering Works, tolerance of concrete cover is involving +5mm and -5mm and engineers must not believe sub-standard work as they do not possess an authority to change acceptance criteria. In that case where engineers think contractor suggestion acceptable in technical point of view, consent has to be required from employer regarding changes in receiving criteria.

From practical point of view, effect on cracking because of an enlarge in concrete cover have to be considered. In general, there are three major parameters which govern crack width, namely tensile damage at the point considered, distance of longitudinal bar to concerned point and depth of tension zone.

For second factor, as in proximity of longitudinal bars to point of part, closer a bar is to this point; smaller is crack width. So, closely spaced bars with smaller cover determination give narrower cracks than extensively spaced bars with larger cover. So, with an increase of concrete cover, crack width will add to that is undesirable.

 


Related Discussions:- Increasing concrete cover beyond contractual

Concrete pavement - thickness, Concrete Pavement: Thickness T...

Concrete Pavement: Thickness The thickness of concrete pavements is determined from the stresses induced due to loads and temperature. The thickness adopted is genera

Define the alternate depths - hydrologic system, Define the Alternate Depth...

Define the Alternate Depths In open channels, two alternate depths of flow have the same energy for the same flow rate. As shown in the figure, the hyperbolic plot of energy (x

Surveying, working from whole to part

working from whole to part

Of obstacles to both chaining and ranging.., #questof obstacles to both cha...

#questof obstacles to both chaining and ranging. ion..

Instruments, description and details about distomat

description and details about distomat

Ocf, location of hydrolic jump

location of hydrolic jump

Surveying, explain operations of direct and indirect leveling?

explain operations of direct and indirect leveling?

What are aquifers - hydraulics system, What are Aquifers? Water bearing...

What are Aquifers? Water bearing, underground geologic formations. The subsurface formations are composed of soils and rocks with voids saturated with water.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd