Increasing concrete cover beyond contractual, Civil Engineering

Assignment Help:

Question
If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion?

Answer
In contractual part, based on requirement of General Specification of Civil Engineering Works, tolerance of concrete cover is involving +5mm and -5mm and engineers must not believe sub-standard work as they do not possess an authority to change acceptance criteria. In that case where engineers think contractor suggestion acceptable in technical point of view, consent has to be required from employer regarding changes in receiving criteria.

From practical point of view, effect on cracking because of an enlarge in concrete cover have to be considered. In general, there are three major parameters which govern crack width, namely tensile damage at the point considered, distance of longitudinal bar to concerned point and depth of tension zone.

For second factor, as in proximity of longitudinal bars to point of part, closer a bar is to this point; smaller is crack width. So, closely spaced bars with smaller cover determination give narrower cracks than extensively spaced bars with larger cover. So, with an increase of concrete cover, crack width will add to that is undesirable.

 


Related Discussions:- Increasing concrete cover beyond contractual

Stiff or soft fenders be designed for berthing in piers, Question Is it...

Question Is it necessary that stiff or soft fenders be designed for berthing in piers? Answer Elasticity of fenders is related to ability to release stored energy duri

Physical deterioration - underwater inspection of bridges, Define Physical ...

Define Physical deterioration - underwater inspection of bridges Typical defects include: -   Scaling -   Cracking -   Spalling -   Disintegration -   Abrasion

Check rail on curve, Check Rail on Curve - Check Rails are basically p...

Check Rail on Curve - Check Rails are basically provided on sharp curves to reduce the lateral wear on the outer rail. They also prevent the outer wheel flange from mounting o

Element stiffness matrices, i have seen the example of the above topic on y...

i have seen the example of the above topic on your page and i would like to have a solution for it

Laplace transform, Using Laplace transfom, the following differential equat...

Using Laplace transfom, the following differential equation d y dy dt reduces to the algebraic equation of the form Resolve y(s) into partial fractions

Diffrence between concrete road and bituminous road, Q. Diffrence between C...

Q. Diffrence between Concrete road and bituminous road? Concrete road belongs to rigid pavement and they don't deflect under traffic loads. Quite the reverse, bituminous pavem

How to design shape of guide bunds, Q. How to design Shape of guide bunds? ...

Q. How to design Shape of guide bunds? Alignment of guide bunds converging on the upstream was considered by Bell, Spring and Gales to allow for the waterway obstructed by pier

Determine the project duration and critical path, Critical Path - Activity ...

Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start

Beam, Classification of beam

Classification of beam

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd