Increasing concrete cover beyond contractual, Civil Engineering

Assignment Help:

Question
If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion?

Answer
In contractual part, based on requirement of General Specification of Civil Engineering Works, tolerance of concrete cover is involving +5mm and -5mm and engineers must not believe sub-standard work as they do not possess an authority to change acceptance criteria. In that case where engineers think contractor suggestion acceptable in technical point of view, consent has to be required from employer regarding changes in receiving criteria.

From practical point of view, effect on cracking because of an enlarge in concrete cover have to be considered. In general, there are three major parameters which govern crack width, namely tensile damage at the point considered, distance of longitudinal bar to concerned point and depth of tension zone.

For second factor, as in proximity of longitudinal bars to point of part, closer a bar is to this point; smaller is crack width. So, closely spaced bars with smaller cover determination give narrower cracks than extensively spaced bars with larger cover. So, with an increase of concrete cover, crack width will add to that is undesirable.

 


Related Discussions:- Increasing concrete cover beyond contractual

Reduced levelling, what is the theary of reduced levelling

what is the theary of reduced levelling

Diaphragms necessary in concrete box girder bridges, Are diaphragms necessa...

Are diaphragms necessary in designing of concrete box girder bridges ?

Construction of the building, a) Certain data for the materials used in the...

a) Certain data for the materials used in the construction of the building, e,g, insulation, building materials, air spaces, etc.  b)  Draw, with appropriate dimensions, the cro

Why does pipe jacking machine usually get stuck, Q. Why does pipe jacking m...

Q. Why does pipe jacking machine usually get stuck when the ground condition change from soil to very hard rock? When pipejacking machine moves from anarea of soil to very hard

Fixed end moments, For fixed beam(say for example fixed with a point load a...

For fixed beam(say for example fixed with a point load at midspan) how did we end up getting P*L/8...??

Compute the included angles, Example. With a surveyor compass the ang...

Example. With a surveyor compass the angles observed in traversing the lines AB, BC, CD, DE and EF are  as. Compute the included angles and indicate them in a neat sketch.

Calculate the annual cost of alum - coagulation, Incoming water contains 2....

Incoming water contains 2.5 mg/L as a substance of natural alkalinity (HCO 3 - ). The flow rate is 9.5 ML/day). (a) What feed rate is required if the alum dose is 7 mg/L and

Centroid, how tofind centroid of cercular arc

how tofind centroid of cercular arc

Concrete compaction in piling works, Question What is the reason that v...

Question What is the reason that vibrators not used in concrete compaction in piling works ? Answer Concrete for piles must be a high-slump self-compacting mix that i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd