Increasing concrete cover beyond contractual, Civil Engineering

Assignment Help:

Question
If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion?

Answer
In contractual part, based on requirement of General Specification of Civil Engineering Works, tolerance of concrete cover is involving +5mm and -5mm and engineers must not believe sub-standard work as they do not possess an authority to change acceptance criteria. In that case where engineers think contractor suggestion acceptable in technical point of view, consent has to be required from employer regarding changes in receiving criteria.

From practical point of view, effect on cracking because of an enlarge in concrete cover have to be considered. In general, there are three major parameters which govern crack width, namely tensile damage at the point considered, distance of longitudinal bar to concerned point and depth of tension zone.

For second factor, as in proximity of longitudinal bars to point of part, closer a bar is to this point; smaller is crack width. So, closely spaced bars with smaller cover determination give narrower cracks than extensively spaced bars with larger cover. So, with an increase of concrete cover, crack width will add to that is undesirable.

 


Related Discussions:- Increasing concrete cover beyond contractual

Advantages and disadvantages of water transport, Advantages and Disadvantag...

Advantages and Disadvantages of Water Transport: The following are the advantages of water transport: (a)        Since the vessels travel on water, no investment is needed

Premix road, plz tell me the ratio of sand,aggregate,and asphalt.pl tell me...

plz tell me the ratio of sand,aggregate,and asphalt.pl tell me the mm of aggregate

Consultant , how to convert a varying distributed load to a uniformly distr...

how to convert a varying distributed load to a uniformly distributed load

Process of installation of elastomeric bearing, The process of installation...

The process of installation of elastomeric bearing differs in case of precast vis-a-vis cast-in-situ girders. For precast girders, the bearing may be fixed to the underside of the

Pavement Drainage, What would be the best way to evaluate the field perform...

What would be the best way to evaluate the field performance benefits of subsurface drainage in a flexible pavement? Short term and long term, thick or thin HMA..

Harbour, typical layout showing dock,quay.jetties,turning circle,pier

typical layout showing dock,quay.jetties,turning circle,pier

Levelling, how to go about the collimation method.

how to go about the collimation method.

Jetties, JETTIES: A jetty is a structure projecting into the sea from ...

JETTIES: A jetty is a structure projecting into the sea from the shore line for receiving ships. They are made of RCC trestles with a deck to accommodate railway track and roa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd