Increasing concrete cover beyond contractual, Civil Engineering

Assignment Help:

Question
If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion?

Answer
In contractual part, based on requirement of General Specification of Civil Engineering Works, tolerance of concrete cover is involving +5mm and -5mm and engineers must not believe sub-standard work as they do not possess an authority to change acceptance criteria. In that case where engineers think contractor suggestion acceptable in technical point of view, consent has to be required from employer regarding changes in receiving criteria.

From practical point of view, effect on cracking because of an enlarge in concrete cover have to be considered. In general, there are three major parameters which govern crack width, namely tensile damage at the point considered, distance of longitudinal bar to concerned point and depth of tension zone.

For second factor, as in proximity of longitudinal bars to point of part, closer a bar is to this point; smaller is crack width. So, closely spaced bars with smaller cover determination give narrower cracks than extensively spaced bars with larger cover. So, with an increase of concrete cover, crack width will add to that is undesirable.

 


Related Discussions:- Increasing concrete cover beyond contractual

Explain some points regarding to hardness, Explain Some Points regarding to...

Explain Some Points regarding to Hardness 1) Hardness removal using lime and soda is based on the solubility reactions of calcium carbonate, CaCO 3 and magnesium hydroxide, Mg

Boundaries of rational method in calculating runoff, Question What are main...

Question What are main boundaries of Rational Method in calculating runoff? Answer Calculation of runoff is compound matter that depends on a lot of factors similar to ground

Determine the grade rod reading at station, A section view of a proposed ro...

A section view of a proposed roadway is shown in Figure 1 with an existing grade point elevation of 100-ft. The proposed roadbed finish grade elevation at station 50+00 is 95.00-ft

Bridge design, criteria for economical span length in bridge

criteria for economical span length in bridge

Foundation, difference between piles and pier

difference between piles and pier

Barometric leveling, what are advantages and disadvantages of barometric le...

what are advantages and disadvantages of barometric levelling

Complete embedment of pipelines into thrust blocks, Q. Complete embedment o...

Q. Complete embedment of pipelines into thrust blocks For unreinforced concrete thrust blocks in bends and tees for pressurized pipelines, it's recommended that contact surfac

Construction equipments, what is preventive maintenance and state its advan...

what is preventive maintenance and state its advantages

Determine the late start time for activity, For the project network shown, ...

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

Determine the density index in the natural state, A soil sample with a grai...

A soil sample with a grain specific gravity of 2.67 was filled in a 1000 ml container in the loosest possible state and the dry weight of the sample was found to be 14.75 N. It was

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd