Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Do you mean by accelerated aging, Q. Do you mean by Accelerated Aging? ...

Q. Do you mean by Accelerated Aging? Accelerated ageing tests are conducted at elevated temperature of 100 o C to know the variation in hardness, UTS and elongation at break.

Magnitude of torque - bending moment, Magnitude of torque - bending moment:...

Magnitude of torque - bending moment: A prismatic bar of hollow circular cross-section along with outer and inner diameters 100 mm and 80 mm correspondingly, carries a bending

Determine the flow rate from the dewatering well, A construction project in...

A construction project involves excavation below grade. A 24 inch diameter dewatering well is installed from grade (EL 586) to 80 ft below grade to lower the water table. Soil bori

Define the meanings of texture, a) Define the meanings of 'texture' and 'st...

a) Define the meanings of 'texture' and 'structure' of a soil. b) Write the meaning of 'black cotton soil'? Indicate the geological and climatic conditions that tend to make

Determine the basic concepts of prestressing, Determine the Basic Concepts...

Determine the Basic Concepts  of Prestressing In the year 1904, Freyssinet tried to introduce prestresses in concrete to resist stresses developed due to external loads. Later,

Shear lag in typical box-girder bridge, Shear lag in typical box-girder bri...

Shear lag in typical box-girder bridge For multiple-cell box girders, there are normally two arrangements. First one is that independent cells are connected by their top flang

Permissible bearing pressure on poly tetra fluoro ethylene, Define Permissi...

Define Permissible Bearing Pressure on poly tetra fluoro ethylene? For the purpose of design, it is important to lay down permissible bearing pressure on PTFE sliding surfaces.

Obstacles, Obstacles which can be ranged

Obstacles which can be ranged

R.c.c square overhead tank, problems in estimating especially in reinforcem...

problems in estimating especially in reinforcement works

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd