Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Define the process of eccentric prestressing, Define the proess of Eccentri...

Define the proess of Eccentric Prestressing In this form of prestressing, the centroid of cross-sectional areas of tendons is not located at the centroid of the cross-section.

#soil survey., Explian obstacles in chaining but not ranging.

Explian obstacles in chaining but not ranging.

Rcc lintel, how to make a leakproof joint with existing lintel

how to make a leakproof joint with existing lintel

Plumbing technology, This assessment will test Learning Outcomes 3 and 4 as...

This assessment will test Learning Outcomes 3 and 4 as well as the component of Learning Outcome 1 as it refers to waste disposal for the Plumbing Technology. The student is expect

Building, What quantity of cement will be needed to lay 2000 blocks of 9 in...

What quantity of cement will be needed to lay 2000 blocks of 9 inches using a mortar ratio of 1:6 with a thickness of 25mm in-between blocks.

Explain the unconfined compression strength of the clay, A square group of ...

A square group of 9 piles was driven into soft clay extending to a large depth. The diameter and length of the piles were 30 cm and 9 m respectively. If the unconfined compression

Assigning central pier and abutment as fixed piers, What are beneficial poi...

What are beneficial points of assigning central pier and abutment as fixed piers ?

Timber, uses of timber in civil engineering field and its physical state an...

uses of timber in civil engineering field and its physical state and chemical formula or symbol?

Fluid mechanics , i have three civil engineering fluid mechanics. 1 manomet...

i have three civil engineering fluid mechanics. 1 manometer problem 2 estimate the discharge for a channel 3 pipe system - direction of flow in line and what the value of flow in l

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd