Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Determine the uses of prestressed concrete poles, Determine the uses of Pre...

Determine the uses of Prestressed concrete poles Prestressed concrete poles are commonly mass produced and are used in most countries for power transmission, antenna masts etc

Explain the equation for a suppressed rectangular weir, Explain the Equatio...

Explain the Equation for a Suppressed Rectangular Weir If the approach velocity is negligible, velocity head can be excluded and the equation becomes the Francis weir equation

Explain equation for change interval, Explain equation for Change Interval ...

Explain equation for Change Interval y = t + v / 2a + 64.4G Where:  y = length of yellow interval (sec)     t = driver perception/reaction time (1.0 sec generally used)

What is function of mortar in brick walls, Q. What is Function of mortar in...

Q. What is Function of mortar in brick walls? A distinctive brick wall structure generally comprises the subsequent components:  (i)  Coping on top of the brick wall to prot

Wires in gabion walls, Gabions are wire mesh boxes that are filled with sto...

Gabions are wire mesh boxes that are filled with stones and they areplaced in an orderly pattern to act as a single gravity retaining wall. Meshes or Lacing wires are designed t

Use of primers in joint sealant, Q. Use of primers in joint sealant? Mo...

Q. Use of primers in joint sealant? Most of the joint sealants applied in concrete joints are adhesive and recommended joint width/depth of joint sealant is from 2:1 to 1:1 as

Levelling, the cooke''s reversible level

the cooke''s reversible level

Kerb overflow weirs – horizontal bars vs. vertical bars, Q. Kerb overflow w...

Q. Kerb overflow weirs – horizontal bars vs. vertical bars? Overflow weirs must be provided for steep roads (longitudinal gradient>5%), flat roads (longitudinal gradient Ess

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd