Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

#overhanging beams, How to calculate point of contraflexion on an overhangi...

How to calculate point of contraflexion on an overhanging beam with udl

Rectangular panel inside a false work, Question In erection of false work, ...

Question In erection of false work, for a rectangular panel inside a false work would it be braced all along two diagonals ? Answer While a rectangular panel is focus to the

Common building stones, Common Building Stones Here describe some commo...

Common Building Stones Here describe some commonly used stones are following: a. Granite       b. Basalt and trap c. Slate          d. Sand stone   e. Marble        f.

How can you design side slope of bank, Q. How can you design Side Slope of ...

Q. How can you design Side Slope of bank? Angle of bank should be flatter than angle of repose of pitching material. Angle of repose of sand is 2:1 while that of stone is about

WMM, gradation of materials used in wet mix macadam

gradation of materials used in wet mix macadam

Torsion, Asolid circular shaft of 25 cm diameter is to be replaced by a hol...

Asolid circular shaft of 25 cm diameter is to be replaced by a hollow shaft .The ratio of external to internal diameters being 2to1.Find the size of the hollow shaft if the maximum

Advantages of using top-down approach, Question What are major advantag...

Question What are major advantages of using top-down approach in basement construction? Answer The main advantages of top-down approach are listed below- (i) Stru

Darwing, construction the ellips in all method

construction the ellips in all method

How are freeway bridges built, After measuring the anticipated traffic for ...

After measuring the anticipated traffic for the bridge, cement/reinforced- with- rebar stanchions are spaced over the freeway to accommodate the bridge. An 'off-ramp' from the free

Physical evaluation of food grains, Q. Physical evaluation of food grains? ...

Q. Physical evaluation of food grains? Food grains are judged for quality by their physical, chemical and microbiological examination. The physical examination includes chec

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd