Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Critical Path - Activity on Node
The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.
Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish. To clarify the situation, sketch the project network, showing activities, durations, and the critical path.
a) Total days to Finish = 41.
b) The critical path is as follows: START, A, B, C, D, F, G, FINISH
Variations of tendon stresses in pre or post-tensioned concrete Variations of tendon stresses in pre or post-tensioned concrete members, along the length of tendons, may be of
Question In a concrete compression test , usually 150mmx150mmx150mm concrete cube examples are used for testing. Why isn't 100mmx100mmx100mm concrete cube samples used in test in
Question Are there any dissimilarity in methods of compaction between clayey soil material and sandy material ? Answer The three key actions of compaction are static
Determine the moment of inertia with respect to the x axis for the shaded area shown (Figure 2) . The dimension is a = 2.00m .
Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was
I have a writing that needs to be corrected
Preparation for Underwater Inspection - Availability of Tools and Equipment The engineer-in-charge, before taking up the inspection, should list out the complete equipment req
what is the meaning of offset
Define Emerging Trends in Bearings? New innovations have taken place in the area of bridge bearings, notable among them are: (1) Shock Transmission Unit (STU) or Lock Up Dev
Tests on Limestones Practical tests are made on lime stones to decide their suitability is following: i. Physical tests ii. Heat test iii.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd