Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Structures, What is the economic span of a bridge

What is the economic span of a bridge

Beams, how to convert uniformly varying loads to point loads

how to convert uniformly varying loads to point loads

Define the categories of corrosion of steel structures, Define the Categori...

Define the Categories of Corrosion of steel structures? Corrosion of steel structures can be classified as under: -   Atmospheric corrosion -   Underwater corrosion -

Paint, Description of paint

Description of paint

Bricks, BRICKS Brick is obtained by moulding good clay into a block, wh...

BRICKS Brick is obtained by moulding good clay into a block, which is dried and then burnt. It is the oldest building block to replace stone. Manufacture of brick started havin

Permissible bearing pressure on poly tetra fluoro ethylene, Define Permissi...

Define Permissible Bearing Pressure on poly tetra fluoro ethylene? For the purpose of design, it is important to lay down permissible bearing pressure on PTFE sliding surfaces.

Doors and windows, important considerations in case of doors and windows

important considerations in case of doors and windows

Increase in velocity of water due to afflux, Q. Increase in velocity of wat...

Q. Increase in velocity of water due to afflux? Specific energy E f in m per m 3 of flow is the energy measured with respect to bottom and hence comprising potential head D a

Zones of smear around vertical drains, Zones of smear around vertical drain...

Zones of smear around vertical drains Smear zones are produced during the installation of vertical drains in that zone of soils surrounding the band drains are disturbed. Soil

Main functions of slip joints in block work seawalls, Question What are...

Question What are main functions of slip joints in block work seawalls ? Answer Slip joints are joints that are formed during a complete vertical plane from cope

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd