Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Discuss about the term - end zone, Discuss about the term - End Zone It...

Discuss about the term - End Zone It is the length of a post-tensioned concrete member, at the end, which is required to get a distribution of prestress over the whole of the c

Compass survey, define compass survey and mention its objectives

define compass survey and mention its objectives

Retaioning walls, what are the uses of retaining wall?!

what are the uses of retaining wall?!

Marine pilling, what are the problems in traditional marine pilling system ...

what are the problems in traditional marine pilling system of steel tubular pile with concrete infill

Timber, uses of timber in civil engineering field and its physical state an...

uses of timber in civil engineering field and its physical state and chemical formula or symbol?

Movement accommodation factor for joint sealant, Movement accommodation fac...

Movement accommodation factor is normally specified by manufacturers of joint sealants for designers to design dimension of joints. It is stated as the total movement that a joint

Stairs, what are the basic reqiureents for stairs. explain the basic proced...

what are the basic reqiureents for stairs. explain the basic procedures for stair construction

Two way slab, how can i design reinforcement for a two way slab

how can i design reinforcement for a two way slab

How to design marginal embankments, Q. How to design Marginal Embankments? ...

Q. How to design Marginal Embankments? Design aspects of marginal embankments are similar to those of approach banks. The aspects needing special attention are dealt with below

Helical reinforcement designed instead of regular links, Question For colum...

Question For column reinforcements, why is helical reinforcement sometimes designed instead of regular links with reasons? Answer The utilization of links for column designi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd