Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Vectors, applications of vectors

applications of vectors

Deflection, solving problems with their answer

solving problems with their answer

What do you mean by settlement cracks, Q. What do you mean by Settlement Cr...

Q. What do you mean by Settlement Cracks? Settlement cracks normally take place in diagonal position. Sometimes vertical cracks may also take place (Figure (a)). Settlement cra

PLANKING AND STRUTING FOR SHALLOW EXCAVATION, DEFINITION TYPE STEP OF CON...

DEFINITION TYPE STEP OF CONSTRUCTION STEP OF SAFETY

Define masonry substructure- underwater inspection of bridge, Define Masonr...

Define Masonry substructure- underwater inspection of bridge? In early days, masonry, particularly stone masonry was extensively used for bridge piers and abutments. Typically,

Loss of prestress due to creep in concrete, Loss of Prestress due to Creep ...

Loss of Prestress due to Creep in Concrete Due to the phenomenon of creep, compressive prestress induced strains in concrete increase. Because of  it, strains of  tendons decre

Concrete technology, Sir, What is the dosage limit of densifier for SF...

Sir, What is the dosage limit of densifier for SFRC concrete

Key distinction in arranging pumps in series, Question What is key dist...

Question What is key distinction in arranging pumps in series and in parallel? Answer For same pumps with similar functions, if pumps arranged in series, total head

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd