Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

How the bursting tensile forces produced, How the Bursting Tensile Forces p...

How the Bursting Tensile Forces produced These are tensile forces produced due to concentrated longitudinally applied prestressing forces in the end zone of a post-tensioned co

Functions of cap block drive cap and pile cushion, Question What are ma...

Question What are main functions of cap block drive cap and pile cushion in driven piles? Answer Cap block is fit amid hammer end and drive cap to manage hammer bl

Strength of rivet joints, Ask question #Minimum 100 Please help me to...

Ask question #Minimum 100 Please help me to write a c program to determine strength and efficiency of single cover butt joint, lap joint, double cover butt joint . words ac

What do you mean by manhole loss, Q. What do you mean by Manhole loss? ...

Q. What do you mean by Manhole loss? Manholes are provided in locations where there are changes in direction, size and gradient of gravity pipelines. Generally practice for str

Reduced levelling, what is the theary of reduced levelling

what is the theary of reduced levelling

Estimating, a 45 cm deep roof beam is provided on 30 cm wall of a room size...

a 45 cm deep roof beam is provided on 30 cm wall of a room size 3.0m*5.0m . calculate the quantity of steel required in beam on percentage basis.

Turbines, How do we get electricity even when the gates of a dam were close...

How do we get electricity even when the gates of a dam were closed?

Explain remote sensing technique, Q. Explain Remote sensing technique? ...

Q. Explain Remote sensing technique? Remote sensing is a science or an art of obtaining the information about an object, area or a phenomenon through analysis of data acquired

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd