Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Dam, types of dam

types of dam

Deep foundation, At what places deep foundation are made?

At what places deep foundation are made?

Importance of poles in critical load combinations, Importance of poles in c...

Importance of poles in critical load combinations The poles are generally designed for the following critical load combinations  : (a)  Bending due to wind load on the cable

Surveying, Distance ABC was measured with a 30m. Chain tested and found to ...

Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was

Define electrical tool for underwater inspection of bridge, Define Electric...

Define Electrical tool for underwater inspection of bridge? Electrical equipment like Rebar Scanner for scanning of rebars; underwater sonic and ultrasonic equipment for observ

Pavement width - geometric design of roads, Pavement Width: The pavem...

Pavement Width: The pavement widths commonly adopted are : Single lane                 :           3.75 m Intermediate lane     :           5.5 m Two lane

Cement, uses of heavy weight aggregate

uses of heavy weight aggregate

Surveying, obstacles in chain surveying

obstacles in chain surveying

Define influence lines, Define Influence lines Provides information...

Define Influence lines Provides information at a single point on a beam Can be used for: - Reactions - Internal shear forces - Internal moment Indicate

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd