Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Variations of tendon stresses in pre tensioned concrete, Variations of tend...

Variations of tendon stresses in pre or post-tensioned concrete Variations of tendon stresses in pre or post-tensioned concrete members, along the length of tendons, may be of

A concrete compression machine, Question In a concrete compression test , ...

Question In a concrete compression test , usually 150mmx150mmx150mm concrete cube examples are used for testing. Why isn't 100mmx100mmx100mm concrete cube samples used in test in

Dissimilarity in methods of compaction, Question Are there any dissimil...

Question Are there any dissimilarity in methods of compaction between clayey soil material and sandy material ? Answer The three key actions of compaction are static

Static, Determine the moment of inertia with respect to the x axis for the ...

Determine the moment of inertia with respect to the x axis for the shaded area shown (Figure 2) . The dimension is a = 2.00m .

Surveying, Distance ABC was measured with a 30m. Chain tested and found to ...

Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was

Seminar class, I have a writing that needs to be corrected

I have a writing that needs to be corrected

Preparation for underwater inspection - tool and equipment, Preparation for...

Preparation for Underwater Inspection - Availability of Tools and Equipment The engineer-in-charge, before taking up the inspection, should list out the complete equipment req

Offset, what is the meaning of offset

what is the meaning of offset

Define emerging trends in bearings, Define Emerging Trends in Bearings? ...

Define Emerging Trends in Bearings? New innovations have taken place in the area of bridge bearings, notable among them are: (1) Shock Transmission Unit (STU) or Lock Up Dev

Tests on limestones, Tests on Limestones Practical tests are made on li...

Tests on Limestones Practical tests are made on lime stones to decide their suitability is following:     i.       Physical tests    ii.        Heat test    iii.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd