Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Explain the design of graded filter, Q. Explain the design of graded filter...

Q. Explain the design of graded filter? Use of graded filter has been traditionally used below the revetment and protection works. The material used in the granular / graded fi

Survey, underground installations

underground installations

Water retaining structure, Question Why do BS8007 specify permissible c...

Question Why do BS8007 specify permissible crack width of water retaining structure as 0.2mm for severe, extremely severe exposure? Answer For break width less than

Determine the stresses set up in the brass, Determine the stresses set up i...

Determine the stresses set up in the brass: A compound bar is constructed from three bars 50 mm wide by 12 mm thick fastened together to form a bar 50 mm wide by 36 mm thick.

Define the meaning of grout - concrete, Define the meaning of Grout - Concr...

Define the meaning of Grout - Concrete Grout should be made with any type of recommended cement and using water of a required quality. If very large size ducts are to be groute

Explain the term -tendon splices, Tendon splices Tendon splices are us...

Tendon splices Tendon splices are used to join tendons when continuous prestressed concrete , members require long tendons to achieve continuity. Several types of tendon splic

Door, types of door with sketches

types of door with sketches

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd