Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Vectors, how are vectors used in civil engineering

how are vectors used in civil engineering

Distance between concrete columns in 5 story building, distance between con...

distance between concrete columns in 5 story building and if there is distance 15 feet than what should be the column size and how many bars and diameter of each bar ?

Explain the shrink factor of soil, Explain the Shrink Factor of Soil In...

Explain the Shrink Factor of Soil In addition to the swell factor and its associated load factor, soil also has a shrink factor. While the first two relate the volume of an equ

Streams not wholly alluvial - alluvial streams, Streams Not Wholly Alluvial...

Streams Not Wholly Alluvial In streams which are not wholly alluvial, consisting of bed of pebbles, rock, etc. the liner waterway is kept equal to the actual surface width of

Rmc, about rmc and what are the safety measures taken and which licences ar...

about rmc and what are the safety measures taken and which licences are required

What is the loss of prestress due to shrinkage of concrete, What is the Los...

What is the Loss of Prestress due to Shrinkage of Concrete It is the loss of prestress due to shrinkage of concrete, which takes place in the initial stage of hardening of conc

Define the term - pre- tensioning, Define the term - pre- tensioning It...

Define the term - pre- tensioning It is a method of prestressing in which tendons are placed, inside ducts or passages provided in concrete, after concrete gains sufficient str

Explain the term - non-bonded prestressed concrete, Explain the term - Non-...

Explain the term - Non-bonded Prestressed Concrete It is a method of construction in which the tendons are not bonded to the concrete. Ducts, housing the tendons, are not grout

Bond performance of bar reinforcement, Question Does occurrence of rust hav...

Question Does occurrence of rust have adverse collision to bond performance of bar reinforcement ? Answer In fact, presence of rust in bars cannot have adverse impact to the bo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd