Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

How to determine the water content and bulk density, The wet weight of a sa...

The wet weight of a sample is missing in a Proctor test. The oven-dry weight of this sample is 189 N. The volume of the mould used is 1000 cm 3 . If the degree of saturation of

Friction dampers, what is friction damper and there types?

what is friction damper and there types?

Briefly explain about artificial cut offs, Q. Briefly explain about Artific...

Q. Briefly explain about Artificial cut offs? Alignment of a cut off is chosen so that approach and exit ends remain more or less tangential to the river course. A cut off can

Control reinforcement corrosion, Crack width limitation ( In many stand...

Crack width limitation ( In many standards and code of practice of numerous countries, allowable size of crack width is generally limited to less than 0.5mm for reinforced conc

State the ground water levels, Ground Water Levels The location of the...

Ground Water Levels The location of the ground water level is essential for deep excavation, water-logged areas. The existing wells in the nearby vicinity of the proposed site

High temperature in laying bituminous pavement, High temperature in laying ...

High temperature in laying bituminous pavement Generally bituminous materials are also broadly categorized into two types viz bitumen McAdamsand hot-rolled asphalts. At the ti

Explain Rapid Mixing Tank and Flocculation Basin , Explain Rapid Mixing Tan...

Explain Rapid Mixing Tank For the chemical reactions to occur, the chemicals must be mixed with water for both coagulation and softening we need mixing of chemical wi

Define ways of providing the anti slip device - by embedment, Define Ways o...

Define Ways of providing the anti slip device - By Embedment? A recess can be created in the bed block in which the elastomeric pad will be placed. The functioning of the reces

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd