Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

English, Features of literary writing

Features of literary writing

Design a water supply scheme for new railway colony, Q. Design a water supp...

Q. Design a water supply scheme for new Railway colony based on the following data's. i. Requirement of Loco and domestic consumption 5 lacs gallon per day. ii. Source of wat

Shear lag in typical box-girder bridge, Shear lag in typical box-girder bri...

Shear lag in typical box-girder bridge For multiple-cell box girders, there are normally two arrangements. First one is that independent cells are connected by their top flang

Surving, describe the methods of reducing the levels,and their relative adv...

describe the methods of reducing the levels,and their relative advantages and disadvantages.

Physics, A point charge q2 = -2.3 µC is fixed at the origin of a co-ordinat...

A point charge q2 = -2.3 µC is fixed at the origin of a co-ordinate system as shown. Another point charge q1 = 4.0 µC is is initially located at point P, a distance d1 = 6.0 cm fro

Mortar mechanism vs stone contact mechanism, "Mortar mechanism" vs. "stone ...

"Mortar mechanism" vs. "stone contact mechanism" in bituminous materials 'Stone contact mechanism' applies to well graded aggregates coated with bitumen (for example dense bit

Sewerage, what is the manhole to manhole joining preferences? why it is joi...

what is the manhole to manhole joining preferences? why it is joined crown to cron, not crown to invert?

Best efficiency point and operating point for pumps, Q. Best efficiency poi...

Q. Best efficiency point and operating point for pumps? In a pumping system, a system curve can be derived based on static head needed to lift up the fluid and variable head be

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd