Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Define scour - underwater inspection of bridges, Define Scour - Underwater ...

Define Scour - Underwater Inspection of Bridges? Whenever a bridge crosses a waterway, even a small or intermittent one, scour is a dangerous effect that can damage bridge pier

Classification of timber based on modulus of elasticity, Classification Bas...

Classification Based on Modulus of Elasticity: Young's modulus is resolute by conducting bending test. On this basis timber is classified as following: Group A: E = 12.5 kN

Afflux in rivers with non scourable bed, Q. Afflux in rivers with non scour...

Q. Afflux in rivers with non scourable bed? Afflux is defined as rise of flood level of the river upstream of a bridge as a result of the obstruction to natural flow caused by

#title., desirable properties in green concrete

desirable properties in green concrete

Define the shrinkage limit and shrinkage ratio, The oven-dry weight of a pa...

The oven-dry weight of a pat of clay is 1.17 N and the weight of mercury displaced by it is 0.855 N. suppose the specific gravity of solids as 2.71, verify the shrinkage limit and

Determine the concept of resultant force at a section, Resultant force at a...

Resultant force at a section We can determine stresses at top and bottom fibres, at a section of a beam, due to pre-stressing force and external loads. Using them, we can draw

Grillage foundation, what are the advantages of grillage foundation and why...

what are the advantages of grillage foundation and why people prefers that?

Advantages of unbonded post-tensioning systems, Advantages of unbonded post...

Advantages of unbonded post-tensioning systems Similarly, some advantages of unbonded post-tensioning systems over bonded post-tensioning ones may be written as under :  (a)

Illustrate concept of filter design, Q. Illustrate Concept of filter design...

Q. Illustrate Concept of filter design? The material used for filter should satisfy the following normal criteria a. Filter material is more pervious than the base material

Dense Bituminous Macadam, What is DBM?Why use DBM where other binder course...

What is DBM?Why use DBM where other binder courses are available?What is composition and advantages of using DBM?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd