Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Timber, defects in timber?

defects in timber?

Matlab program, for calculating the bending moment in which the loading and...

for calculating the bending moment in which the loading and the length of continuous beam is taken from the user

Geotech, for zero air void line sr is

for zero air void line sr is

What do you mean by slip siding, Q.What do you mean by Slip Siding? If ...

Q.What do you mean by Slip Siding? If the Station yard is in a gradient steeper than 1 in 260 or there is a continuous falling gradient away from the station there is a possibi

Ranging, describe reciprocal ranging

describe reciprocal ranging

PRC, what is the bleeding of concrete?

what is the bleeding of concrete?

Explain dissolved impurities in water, Q. Explain Dissolved Impurities in w...

Q. Explain Dissolved Impurities in water? The impurities which are caused by the action of water and water forming Acids with organic matter and carbon dio

Write short notes on impact test, Q. Write short notes on Impact Test? ...

Q. Write short notes on Impact Test? Impact test for ballast shall be carried out using Impact testing machine. The test sample shall be prepared out of ballast so as to con

Main problems related with prestressed concrete piles, Question What ar...

Question What are main problems related with prestressed concrete piles ? Answer Origin of Daido piles comes from Japan where these prestressed actual piles are used

Load carrying element of min-piles, Q. A pipe or groups of bars be adopted ...

Q. A pipe or groups of bars be adopted as load carrying element of min-piles? The design of mini-piles someway differs from other traditional pile types. For example the design

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd