Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Design Mix M35/C35, What is the actual mix propotion for M35/ C35 design mi...

What is the actual mix propotion for M35/ C35 design mix concrete

Water treatment, The transmission main from the well field to the community...

The transmission main from the well field to the community is 2500 ft, the velocity of flow at peak pumping capacity is 3.5 fps, water temperature is 10oC, and pH is 7.5. If free c

Effect of footing size on stress zone, Q. Effect of Footing Size on Stress ...

Q. Effect of Footing Size on Stress Zone? The modulus of elasticity of the soil may be determined by plotting stress-strain diagram based on triaxial test or plate load test.

Designing water storage tank, Question While designing water storage t...

Question While designing water storage tank , has movement joints be installed? Answer While designing water storage tanks , group joints can be set up in similar w

Physics, about lenses & mirrors for assignment

about lenses & mirrors for assignment

Functions of water stops in joints of box culverts, Question What will func...

Question What will functions of water stops in joints of box culverts and drainage channels ? Answer Principal function of water stops is to stop liquids, water-borne materials

Designing of access ramps for drainage channels, Question Designing of ...

Question Designing of access ramps for drainage channels, why must direction of access ramps is sloping down on the way to downstream ? Answer In designing of access

Explain detention or retention ponds - hydrology, Explain Detention or Rete...

Explain Detention or Retention Ponds Detention/Retention Ponds: Designed to reduce and contain the peak runoff from developed areas (more impervious). Attempt to limit the runo

Soil Mechanics, Good evening. I have two homework projects from the Soil Me...

Good evening. I have two homework projects from the Soil Mechanics. I am interesting if anybody can solve them.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd