Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Determine the uses of full prestressing, Determine the uses of Full Prestre...

Determine the uses of Full Prestressing A prestressed concrete structural member is said to be fully prestressed if sufficient prestresses are introduced so that  tensile stres

Explain the primary treatment for wastewater, Explain the Primary Treatment...

Explain the Primary Treatment for Wastewater Primary Treatment: to remove the pollutants that floats or settles. Typically 60% of suspended solids and 35% of BOD 5 are removed

Spun pipes, what is flush joint and confined joint in rcc spun pipes?

what is flush joint and confined joint in rcc spun pipes?

How to do deflection calculations, How to do deflection calculations Ba...

How to do deflection calculations Basic values of span to effective depth ratios for spans upto 10m may be taken as 7, 20 and 26 for cantilever, simply supported and continuous

Soils, how to classify soils materials

how to classify soils materials

#soil survey., Explian obstacles in chaining but not ranging.

Explian obstacles in chaining but not ranging.

Constraction, sir what is means by share force

sir what is means by share force

State the angle of inclination of the failure plane, The stresses at failur...

The stresses at failure on the failure plane in a cohesionless soil mass were: Shear stress = 4 kN/m 2 ; normal stress = 10 kN/m 2 . Verify the resultant stress on the failure plan

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd