Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Steel work design, 1) A building constructed from steelwork requires the fo...

1) A building constructed from steelwork requires the following sections to be designed: a. A beam carrying a characteristic permanent load of 11kN/m and a characteristic variable

Rainfall-runoff computation, hi sir. i hope every thing is fine with you. I...

hi sir. i hope every thing is fine with you. I want to have an information about the way how to compute stream flow from the rainfall over the catchment and anso need the way how t

Coatings at the back faces of abutments, Q. Coatings at the back faces of a...

Q. Coatings at the back faces of abutments? There are many views on the necessity of application of protective coatings (can be in the form of two coats of paint) to the back f

Mapping, how to understand maps easily?

how to understand maps easily?

What is the station at point b, What is the station at Point B? SO...

What is the station at Point B? SOLUTION 3 Station at Point A = Sta 22+45  Station at Point B = (Sta 22+45) + 1028' = 2245'+1028' =3273'  = Sta 32+73

Explain the term - loss of prestress, Explain the term - Loss of Prestress ...

Explain the term - Loss of Prestress At the transfer stage, tendons produce compressive stresses in concrete. Sooner or later, the magnitude of  these stresses experiences a re

Cantilever beam, The problem in the link below. ">http://www.expertsmind....

The problem in the link below. ">http://www.expertsmind.com/questions/plot-vertical-displacement-cantilever-beam-30134382.aspx#

Will water damage concrete, As far as only concrete is concerned i.e. plain...

As far as only concrete is concerned i.e. plain concrete, the effect of water seepage is very little (depending upon the grade of concrete) whereas for RCC (reinforced cement concr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd