Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Contractor to continue concreting works, Question If on-site slump test fai...

Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by

Best efficiency point and operating point for pumps, Q. Best efficiency poi...

Q. Best efficiency point and operating point for pumps? In a pumping system, a system curve can be derived based on static head needed to lift up the fluid and variable head be

Geotech, soil sample investigation

soil sample investigation

Hydraulics and Hydrology , A flow rate of 200 gpm of oil with u=1.5 x 10-3 ...

A flow rate of 200 gpm of oil with u=1.5 x 10-3 lb-sec/ft2 and p=1.7 slug/ft3 occurs in a 4-in pipe. Determine the Reynolds number. Classify the flow as laminar or turbulent. What

What are advantages and disadvantage of varnishing, Q. What are advantages ...

Q. What are advantages and disadvantage of varnishing? Varnish is a clear pale solution of a resinous substance ( like amber, common resin, copal, lac, or shellac 0 dissolved i

Advantages and disadvantages of water transport, Advantages and Disadvantag...

Advantages and Disadvantages of Water Transport: The following are the advantages of water transport: (a)        Since the vessels travel on water, no investment is needed

Estimation of design flood discharge, Q. Estimation of design flood dischar...

Q. Estimation of design flood discharge? These methods are also in vogue for estimating maximum discharge. Discharge estimated using the above three methods may be compared wit

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd