Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Critical Path - Activity on Node
The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.
Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish. To clarify the situation, sketch the project network, showing activities, durations, and the critical path.
a) Total days to Finish = 41.
b) The critical path is as follows: START, A, B, C, D, F, G, FINISH
how are vectors used in civil engineering
distance between concrete columns in 5 story building and if there is distance 15 feet than what should be the column size and how many bars and diameter of each bar ?
Explain the Shrink Factor of Soil In addition to the swell factor and its associated load factor, soil also has a shrink factor. While the first two relate the volume of an equ
Streams Not Wholly Alluvial In streams which are not wholly alluvial, consisting of bed of pebbles, rock, etc. the liner waterway is kept equal to the actual surface width of
about rmc and what are the safety measures taken and which licences are required
What is the Loss of Prestress due to Shrinkage of Concrete It is the loss of prestress due to shrinkage of concrete, which takes place in the initial stage of hardening of conc
Define the term - pre- tensioning It is a method of prestressing in which tendons are placed, inside ducts or passages provided in concrete, after concrete gains sufficient str
Explain the term - Non-bonded Prestressed Concrete It is a method of construction in which the tendons are not bonded to the concrete. Ducts, housing the tendons, are not grout
Question Does occurrence of rust have adverse collision to bond performance of bar reinforcement ? Answer In fact, presence of rust in bars cannot have adverse impact to the bo
fly levelling
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd