Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Residual stresses in steel after welding, Q. Residual stresses in steel aft...

Q. Residual stresses in steel after welding? Considerable residual stresses are persuaded in connecting steel members after welding operation. Local temperature of steel where

Beams of uniform strength, determine the cross section of a rectangular bea...

determine the cross section of a rectangular beam of uniformly strength for a simply supported beam of 6m span subjected to central concentrated load of 20kN a)by keeping depth of

Control reinforcement corrosion, Crack width limitation ( In many stand...

Crack width limitation ( In many standards and code of practice of numerous countries, allowable size of crack width is generally limited to less than 0.5mm for reinforced conc

Determine about the post-tensioned concrete, Determine about the post-tensi...

Determine about the post-tensioned concrete The transfer stage may take place after a long time from the casting of concrete, in the case of post-tensioned,members, enabling th

Surveying, Describe the two fundamental purposes of surveying

Describe the two fundamental purposes of surveying

Calculate the required length of transition, Q  A transition curve is requi...

Q  A transition curve is required for a circular curve of 200-meter Φ radius, the gauge being 1.5 m. and max super elevation restricted to 15 cm. The transition restricted to 15 cm

Is codes for building materials and construction, IS CODES FOR BUILDING MAT...

IS CODES FOR BUILDING MATERIALS AND CONSTRUCTION The following is the list of some of the IS code giving requirements for building materials: IS 269-1989. Specification for ord

Atomic polarisability, what is the atomic polarisibility of argon its susce...

what is the atomic polarisibility of argon its susceptibility is 273k and 1 atm is 4.35*10^-4 and n is 2.7*10^25atoms/m^3

Shape factor, For a solid circular shaft transmitting torque, the shape fac...

For a solid circular shaft transmitting torque, the shape factor is

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd