Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Method of construction of a bored cast-in-situ concrete pile, Q. Method of ...

Q. Method of construction of a bored cast-in-situ concrete pile? Ans. - Bored cast-in-situ concrete pile - A guide casing of 3 to 4 m length is provided on top of the bore hole

Brick masonry., an opening of width 3m and height 2.7 in a brick masonary h...

an opening of width 3m and height 2.7 in a brick masonary has to be provided with door cum window. plan, elevation, section and 2 joining details

Determine the grade rod reading at station, A section view of a proposed ro...

A section view of a proposed roadway is shown in Figure 1 with an existing grade point elevation of 100-ft. The proposed roadbed finish grade elevation at station 50+00 is 95.00-ft

Sulphate-resisting cement not used in marine concrete, Question Explain...

Question Explain the reason why is sulphate-resisting cement not used in marine concrete ? Answer Major components of Portland cement are tricalcium silicate, dicalciu

Levelling, what is the types of levelling

what is the types of levelling

Problems formed while design of pre-stressed concrete, Determine the proble...

Determine the problems formed while design of pre-stressed concrete Two types of problems are encountered by  the engineer engaged in the design of pre-stressed concrete membe

How the bursting tensile forces produced, How the Bursting Tensile Forces p...

How the Bursting Tensile Forces produced These are tensile forces produced due to concentrated longitudinally applied prestressing forces in the end zone of a post-tensioned co

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd