Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Critical Path - Activity on Node
The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.
Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish. To clarify the situation, sketch the project network, showing activities, durations, and the critical path.
a) Total days to Finish = 41.
b) The critical path is as follows: START, A, B, C, D, F, G, FINISH
Question Comparing speed of "Formwork exceeding 300mm wide, horizontal and at any inclination up to and including 5o to horizontal" with speed of "Formwork exceeding 300mm wide, at
State the term - transverse force on concrete We know that in pre-stressed concrete, tendons are placed in a stretched condition and they always would try to regain their origi
Question What is major disparity between fasteners , bolts and screws ? Answer Fastener is a broad term to explain something that is used as a restraint for holding
Q. Minimum and maximum distance between bars? Minimum distance between bars and maximum distance between bars In some codes, a minimum distance amid bars is specified to
Q. How to design Marginal Embankments? Design aspects of marginal embankments are similar to those of approach banks. The aspects needing special attention are dealt with below
desirable properties in green concrete
Q. Energy absorbed in heeling during vessel berthing? When a vessel berths on a fender system at a pier, point of contact of berthing ship can be below or above the centre of
types of windows
A credit card advertises a nominal rate of 18% compounded monthly. If no monthly payments are made, the effective annual interest rate is most nearly: The actual rate is, (18%
Factors Affecting Location Decision: Mining, quarrying and heavy manufacturing have capital intensive facilities that are costly to build and cover large area and use large q
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd