Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Sulphate-resisting cement not used in marine concrete, Question Explain...

Question Explain the reason why is sulphate-resisting cement not used in marine concrete ? Answer Major components of Portland cement are tricalcium silicate, dicalciu

Torque, A shaft 9 m long is subjected to a torque 30 t-m at a point 3 m dis...

A shaft 9 m long is subjected to a torque 30 t-m at a point 3 m distant from either end. The reactive torque at the nearer end will be?

Evaluate break even point, Evaluate break even point: A vehicle manufa...

Evaluate break even point: A vehicle manufacturing firm purchase axle from a shaft manufacturing industry at Rs.100 each. If it establishes the essential apparatus for the pro

Determine the water-cement ratio, A concrete batch plant provided the Desig...

A concrete batch plant provided the Design Strength for the engineer's mix design to match the project's specification requirement for a 4000 psi Tremie pump mix.  The Water-cement

R.c.c design, how to write the beam design using c -language

how to write the beam design using c -language

Simulink software, Using Matlab/ Simulink software to model the overall bui...

Using Matlab/ Simulink software to model the overall building fabric heat transmit characteristics, in order to estimate the maximum rate of heat loss (kW) from the building under

Determine the term - degree of prestressing, Determine the term - Degree of...

Determine the term - Degree of Prestressing Degree of Prestressing It is a measure of the magnitude of the prestressing force related to the resultant stress occurring in

Engineering mechanics, Characteristics of couple #Minimum 150 words accepte...

Characteristics of couple #Minimum 150 words accepted#

Advantages of using top-down approach, Question What are major advantag...

Question What are major advantages of using top-down approach in basement construction? Answer The main advantages of top-down approach are listed below- (i) Stru

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd