Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Thodolite, Ask queexplain about the essential parts of transisit ordinate o...

Ask queexplain about the essential parts of transisit ordinate or vernier theodolitestion #Minimum 100 words accepted#

IRC class 70R, What will be the structural weight per meter for IRC class 7...

What will be the structural weight per meter for IRC class 70r bridge

Measurements, Explain the concept of average velocity

Explain the concept of average velocity

Explain some important points for hazardous waste, Explain some Important P...

Explain some Important Points for Hazardous Waste The mixture rule prevents dilution of waste for the purposes of escaping RCRA regulation. Mixtures of a listed hazardous w

Transportatoin engineening, explain the construction while aligning roads o...

explain the construction while aligning roads on hilly areas

Shear lag in typical box-girder bridge, Shear lag in typical box-girder bri...

Shear lag in typical box-girder bridge For multiple-cell box girders, there are normally two arrangements. First one is that independent cells are connected by their top flang

Cross drainage work, Cross Drainage Work: Several natural streams, ri...

Cross Drainage Work: Several natural streams, rivers and canals cross the road. They have to be led across the road through culverts and bridges. That given structures is kno

Calculate roller production, Calculate Roller Production An excavating ...

Calculate Roller Production An excavating contractor determined through a test strip, that a smooth steel-wheel vibrating roller compactor operating at 3-mph can compact a 6-in

Slurry flow dynamics, how does the particle number and size affect the slur...

how does the particle number and size affect the slurry flow in a centrifugal pump?!

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd