Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Masonry, Sketches for English bond, Stretcher bond, Header bond, Flemish bo...

Sketches for English bond, Stretcher bond, Header bond, Flemish bond in first & second layer plan, elevation and 3 dimensional view of brick bond.

Determine minimum radius that can used on horizontal curve, What is the min...

What is the minimum radius, R min , that can be used on a horizontal curve with a 70 mph design speed, a maximum superelevation, e max = 8%, and a side friction factor, f = 0.10?

Verify the total active thrust on the wall per lineal metre, A smooth backe...

A smooth backed vertical wall is 6.3 m high and retains a soil with a bulk unit weight of 18 kN/m 3 and φ = 18°. The top of the soil is level with the top of the wall and is horiz

Explain rcra and hswa - hazardous waste regulations, Explain RCRA and HSWA ...

Explain RCRA and HSWA - Hazardous Waste Regulations 1. In 1976, Congress passed the Resource Conservation and Recovery Act (RCRA) and directed EPA to establish hazardous waste

Major compensation of using hdpe as compared with cast iron, Question N...

Question Now, mainly flap valves are ended of HDPE. What is the major compensation of using HDPE as compared with cast iron? Answer (i) It has no response with sewage a

Report, report on lintels and arches

report on lintels and arches

Bond breaker for joint sealant, Joint sealant must be designed and construc...

Joint sealant must be designed and constructed to allow free extension and compression during the opening and closure of joints. In case joint sealants are attached to joint filler

Bearing capacity, which kind of pile can increase the bearing capacity, if ...

which kind of pile can increase the bearing capacity, if the water level high in sang soil surface?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd