Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Total station, describe in detail the various parts of a total station

describe in detail the various parts of a total station

Solid mensuration, If the diameter of the base remains constant, by what fa...

If the diameter of the base remains constant, by what factor should the altitude be multiplied to produce a cone with twice volume as the original

Atomic polarisability, what is the atomic polarisibility of argon its susce...

what is the atomic polarisibility of argon its susceptibility is 273k and 1 atm is 4.35*10^-4 and n is 2.7*10^25atoms/m^3

M.o.c, lime saturation factor meaning with simple english

lime saturation factor meaning with simple english

Discuss about the post-tensioning systems, Discuss about the post-tensionin...

Discuss about the post-tensioning systems In most of post-tensioning systems, when the cable is tensioned and the jack is released to transfer prestress to concrete, the fricti

Determine minimum radius that can used on horizontal curve, What is the min...

What is the minimum radius, R min , that can be used on a horizontal curve with a 70 mph design speed, a maximum superelevation, e max = 8%, and a side friction factor, f = 0.10?

Calculate the actual water cement ratio, Calculate the Actual Water Cement ...

Calculate the Actual Water Cement Ratio A jobsite delivery ticket is shown below for a grout mix.  The actual w/c ratio is most nearly: Solution:       Note, althou

Storm water, what are the roles of civil engineers in storm water managemen...

what are the roles of civil engineers in storm water management

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd