Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Wet mix Macadam, Test required before laying or after laying.

Test required before laying or after laying.

Define the pre-tensioned concrete construction, Define the pre-tensioned co...

Define the pre-tensioned concrete construction We understand that in the pre-tensioned concrete construction, stretched tendons are provided in the concrete moulds at the time

Sub-base for concrete carriageway - non-strength provider, Sub-base for con...

Sub-base for concrete carriageway - non-strength provider Essentially sub-base for a concrete carriageway is provided for the below reasons: (i)  It provides aneven and smo

Pycnometer., To determine the specific gravity of fine aggregate (sand) by ...

To determine the specific gravity of fine aggregate (sand) by Pycnometer.

Maintenance of gravel roads, Maintenance of Gravel Roads: The mainten...

Maintenance of Gravel Roads: The maintenance consists of : filling up of potholes/depressions with fresh gravel and compacting after light sprinkling with water. g

Temperature requirements for bituminous material, Question In all-purpo...

Question In all-purpose Specification for Civil Engineering Works, it details temperature requirements for bituminous material all through and after mixing. What is cause beh

Effective span, what do u mean by effective span and its derivation?

what do u mean by effective span and its derivation?

Show the application of concrete crash barriers, Q. Show the application of...

Q. Show the application of Concrete crash barriers? Concrete crash barriers aren't considered as the best barrier design due to the following reasons when compared with flexibl

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd