Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Levelling, how to establish temporary benchmark

how to establish temporary benchmark

Joints in concrete pavements, Joints in Concrete Pavements: Concrete ...

Joints in Concrete Pavements: Concrete pavements in India are of the jointed plain (unreinforced type). The following types of joints are needed in them : (a) Transverse C

What do you mean by distressing, Q. What do you mean by Distressing? Di...

Q. What do you mean by Distressing? Distressing is the operation under taken with or with out rail tensors to secure stress free condition in the LWR at a desired rail temperat

Surveying, Describe the two fundamental purpose of surveying.

Describe the two fundamental purpose of surveying.

Explain the signalized intersections - transportation, Explain the Signaliz...

Explain the Signalized Intersections Cycle length - the time required for one complete sequence of all signal indications Phase - the right-of-way (green), change (yellow),

Design the transverse reinforcement, Figures (a) and (b) respectively give ...

Figures (a) and (b) respectively give details of a simply-supported bridge beam and its (idealised) cross-section. In addition to the dead load of 25 kN/m (including self weight),

Explain in brief about the term - anchorage, Explain brief about the term -...

Explain brief about the term - Anchorage A device used to anchor tendons at the end of a concrete member is called as an anchorage in the case of post-tensioned concrete. In th

Rectangular panel inside a false work, Question In erection of false work, ...

Question In erection of false work, for a rectangular panel inside a false work would it be braced all along two diagonals ? Answer While a rectangular panel is focus to the

Culverts - causeway and bridges, Culverts, Causeway and Bridges: Roads...

Culverts, Causeway and Bridges: Roads have to cross several natural streams like - rivers and canals. They also have to cross railway lines and cross-roads. The structures nee

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd