Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Telecommunication, Blocked process list is not maintioned in priority order...

Blocked process list is not maintioned in priority order why

Theorem of three moments, Theorem of three moments: You have been intr...

Theorem of three moments: You have been introduced to the analysis of one of the important class of structures, namely Statically Indeterminate Structures. You have been intro

Pumping at joints in concrete carriageway, Q. Pumping at joints in concrete...

Q. Pumping at joints in concrete carriageway? Pumping at joints in concrete carriageway takes place in the presence of the below factors: (i)  Fine-grained subgrade (ii)

Proctor test for GSB material, what is the procedure for gsb proctor test f...

what is the procedure for gsb proctor test for matrial sampling for lab density

STRUCTURAL DYNAMICS, Consider a diver weighing 200 Ib at the end of a divin...

Consider a diver weighing 200 Ib at the end of a diving board that cantilevers out 3 ft. The diver oscillates at a frequency of 2 Hz. What is the flexural rigidity E I of the divin

Concrete structure be entirely free of expansion joints, Question Would a c...

Question Would a concrete structure be entirely free of expansion joints and contraction ? Answer Consider that concrete structure is not subject to problem of disparity settlem

What do by diaphragm wall, Q. What do by Diaphragm wall? For the constr...

Q. What do by Diaphragm wall? For the construction of diaphragm walls adjacent to buildings, former experience showed that excess slurry head above groundwater level had to be

Relief features, characteristics of ridge characteristics of escarpment cha...

characteristics of ridge characteristics of escarpment characteristics of plateau characteristics of knoll characteristics of conical hill

Define the meaning of circular prestressing, Define the meaning of circular...

Define the meaning of circular prestressing In circular prestressing, tendon wires are wrapped under tension over the concrete pipes which are pre-cast. The tension in the ten

Show the probable type of clay mineral, The liquid limit and plastic limit ...

The liquid limit and plastic limit of clay are 100% and 25%, respectively. From a hydrometer analysis it has been found that the clay soil having of 50% of particles smaller than 0

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd