Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Relief features, characteristics of ridge characteristics of escarpment cha...

characteristics of ridge characteristics of escarpment characteristics of plateau characteristics of knoll characteristics of conical hill

Explain the critical depth, Explain the Critical Depth d c is the dept...

Explain the Critical Depth d c is the depth of flow in an open channel that has the lowest energy.  In rectangular open channels:  (d c ) 3 = Q 2 /g(w) 2 In nonrectang

Doors and windows, what are the actuall windows and door dimensions e.g AN ...

what are the actuall windows and door dimensions e.g AN ND4

Strength of Materials , Need to know about compressive strength test and te...

Need to know about compressive strength test and tensile strength test of cement

Solid mensuration, the base of an isosceles triangle and the altitude is dr...

the base of an isosceles triangle and the altitude is drawn from one of the congruent sides are equal to 18cm and 15cm , respectively . Find the lenghts of the sides of the triangl

State the term - post-tensioned concrete, State the term - Post-tensioned c...

State the term - Post-tensioned concrete In Post-tensioned concrete construction, as shown in Figure,  tendons are placed inside concrete and stretched after concrete has attai

Point of virtual fixity of lateral loading for piles, Point of virtual fixi...

Point of virtual fixity and critical length of lateral loading for piles Some engineers can get confused about the difference between the two terms which are point of virtual

Correction in bearing, write a c program To compute interior angles and cor...

write a c program To compute interior angles and correct them for observational errors and adjusting the bearing of remaining sides when the bearings taken on a closed compass trav

Bending stress in beams, can you give me example of bending equestion stres...

can you give me example of bending equestion stress as numerical?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd