Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Is codes for building design, IS CODES FOR BUILDING DESIGN The codes w...

IS CODES FOR BUILDING DESIGN The codes which help engineers to design buildings are following: 1. IS 456-2000. For the design of plain and reinforced concrete it is code

Roads in marshy areas, Roads in Marshy Areas: The Problems Encounte...

Roads in Marshy Areas: The Problems Encountered Roads passing through marshy and swampy ground and waterlogged areas have stable ground generally in a saturated condi

Define reinforcing steel - limitations of ultrasonic system, Define Reinfor...

Define Reinforcing Steel - Limitations of Ultrasonic System? The sound velocity measurement taken parallel to the reinforcing bars embedded in the concrete will be markedly hig

Explain the difference in elevation between bm and tp2, Based on the inform...

Based on the information provided in Figure, the difference in elevation between BM and TP 2 is most nearly: Solution: Set up a Table as shown below and insert the kno

How can we reduced frictional losses, How can we reduced frictional losses ...

How can we reduced frictional losses Frictional losses can be reduced by several methods, such as : (a) Over-tensioning the tendons by an amount equal to the maximum frictio

Velocity distribution and flow formulae, Q. Velocity distribution and flow ...

Q. Velocity distribution and flow formulae? Variation in velocity along a vertical in channel cross section is known to follow logarithmic distribution, maximum velocity being

Vectors, applications of vectors

applications of vectors

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd