Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Determine the station and elevation of turning point, A -3.00% grade inters...

A -3.00% grade intersects a +1.25% grade at Sta. 85+80 and elevation 210.00 ft.  A 350-ft vertical curve connects the two grades.  Determine the station and elevation of turning po

State the term - terminology, State the term - Terminology There are ma...

State the term - Terminology There are many technical terms whose understanding provides us with a good insight of  the subject. Some of  these terms are, indeed, general and t

Enumerate about the bonded member, Enumerate about the Bonded Member It...

Enumerate about the Bonded Member It is a concrete member in which tendons are bonded to the concrete. They may be directly bonded to the concrete as in the case of pre-tension

Whole base of mat, Question In modeling a nonrigid mat foundation by us...

Question In modeling a nonrigid mat foundation by using elastic springs, have a uniform modulus of subgrade reaction be used along whole base of mat ? Answer A bed of

Local vehicle parapet strong enough to contain vehicles, Q. Local vehicle p...

Q. Local vehicle parapet strong enough to contain vehicles? Majority of local parapets are 1.1m high in addition they are designed to resist impact from a 1.5ton car moving at

Necessity of air valves in pressurized pipelines, Q. Necessity of air valve...

Q. Necessity of air valves in pressurized pipelines? Air valves are broadly categorized into two major types: single air valves and double air valves. Single air valve comprise

Define recommendations for confined elastomeric pad, Define Recommendations...

Define Recommendations for confined elastomeric pad?  (a) Permissible limits for confined pressure on elastomer pad depends upon effectiveness of internal seal preventing it fr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd