Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Concrete with crush sand, what precaution taken during the mixing of crush ...

what precaution taken during the mixing of crush sand in winter season

Theory of structure, How to convert uniformly varying load to point load

How to convert uniformly varying load to point load

Determine the ruthann graphical method, A retaining wall with a vertical ba...

A retaining wall with a vertical back 5 m high supports cohesion less backfill of unit weight of 19 kN/m 3 . The upper surface of the backfill rises at an angle of 10° with the hor

Brigdes, infomation about differnt brigdes

infomation about differnt brigdes

Structure analysis II, To determine a trusses ,beams and frames of two degr...

To determine a trusses ,beams and frames of two degree by compatibility equations and by castiglanoes theorem

Design of elastomeric bearings, Q. Design of elastomeric bearings? The ...

Q. Design of elastomeric bearings? The standard drawings of bridge bearings issued by RDSO are on the basis of UIC 772-R. To maintain uniformity of approach, the design of elas

Define scour - underwater inspection of bridges, Define Scour - Underwater ...

Define Scour - Underwater Inspection of Bridges? Whenever a bridge crosses a waterway, even a small or intermittent one, scour is a dangerous effect that can damage bridge pier

Resting on several raking piles, Question Should dolphins be designed i...

Question Should dolphins be designed in a rigid manner such as resting on several raking piles? Answer While designing dolphins, they are normally supported on a syste

What do you mean by synoptic coverage, Q. What do you mean by Synoptic Cove...

Q. What do you mean by Synoptic Coverage? Depending upon the area of interest, areas covering few hundred sq m to thousands of sq km can be suitably collected and studied. Phot

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd