Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Soil plug in marine piling system of steel tubular pile, Soil plug in marin...

Soil plug in marine piling system of steel tubular pile with reinforced concrete infill At the time of initial driving process, open-ended steel piles are driven through the s

Working from whole to part in survey, a clear illustration about working to...

a clear illustration about working to part principle and some examples

Explain the term- shrinkage of concrete, LOSS OF PRESTRESS DUE TO SHRINKAG...

LOSS OF PRESTRESS DUE TO SHRINKAGE OF CONCRETE We know that concrete shrinks in volume when it dries up. This volume reduction takes place in the form of reduction of all dime

Home, Ask question #Mindasfimum 100 words accepted#

Ask question #Mindasfimum 100 words accepted#

Inspection of girder bridge, Q. As an AEN in charge, what inspection will...

Q. As an AEN in charge, what inspection will you under taken at the time of inspection of Girder Bridge 3 x 60 feet. Please explain the important items to be o

Design Mix M35/C35, What is the actual mix propotion for M35/ C35 design mi...

What is the actual mix propotion for M35/ C35 design mix concrete

Constriction of waterway at bridges, Q. Constriction of waterway at bridges...

Q. Constriction of waterway at bridges? Constriction of waterway at bridges is effected by extending the approach banks to cover spill area or, in addition, part of active chan

Determine the station and elevation of turning point, A -3.00% grade inters...

A -3.00% grade intersects a +1.25% grade at Sta. 85+80 and elevation 210.00 ft.  A 350-ft vertical curve connects the two grades.  Determine the station and elevation of turning po

Slope protection, what is the type of slope protection that use rocks and p...

what is the type of slope protection that use rocks and put cements between those rocks??the concept is same as brick layer

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd