Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Hydraulics and Hydrology , A flow rate of 200 gpm of oil with u=1.5 x 10-3 ...

A flow rate of 200 gpm of oil with u=1.5 x 10-3 lb-sec/ft2 and p=1.7 slug/ft3 occurs in a 4-in pipe. Determine the Reynolds number. Classify the flow as laminar or turbulent. What

Describe principles of river protection works, Q. Describe Principles of ri...

Q. Describe Principles of river protection works? Determination of design discharge for a bridge is sometimes required to be based on flood marks left during unprecedented abno

Heat and work, How to prove that heat and work are the path functions?

How to prove that heat and work are the path functions?

Define unit hydrograph - hydrology, Define Unit Hydrograph UNIT HYDROGR...

Define Unit Hydrograph UNIT HYDROGRAPH: The hydrograph developed for a drainage basin (watershed) from the runoff of a 1 in or 1 cm storm. It is the base hydrograph from which

Machanics, differentiate between moment & couple

differentiate between moment & couple

Principle of adding cooling pipes, Question What is key principle of a...

Question What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation? Answer These methods aim at reducing placing tem

Determine the Critical Euler Buckling Load, a) Determine the critical Eule...

a) Determine the critical Euler buckling load of a solid aluminium rod of 12 mm diameter if it has a length of 1.0 m between pin-ended supports. (E = 70000 N/mm2)       b) A

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd