Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Device of cavitations in pipes and drains, Question What is device of cavit...

Question What is device of cavitations in pipes and drains ? Answer Cavitations refer to arrangement of air foam in fluid in low-pressure condition that is lower than satura

Wires in gabion walls, Gabions are wire mesh boxes that are filled with sto...

Gabions are wire mesh boxes that are filled with stones and they areplaced in an orderly pattern to act as a single gravity retaining wall. Meshes or Lacing wires are designed t

Explain the hydraulic radius, Explain the Hydraulic Radius (R) A fluid'...

Explain the Hydraulic Radius (R) A fluid's cross-sectional area in flow divided by the wetted perimeter. For a circular channel flowing full and ½ full, R = D/4.

Angular messurement using total stations, write a short note on angular mes...

write a short note on angular messurement using stations?

Pumping at joints in concrete carriageway, Q. Pumping at joints in concrete...

Q. Pumping at joints in concrete carriageway? Pumping at joints in concrete carriageway takes place in the presence of the below factors: (i)  Fine-grained subgrade (ii)

Highway economics, What is highway economics and what are its main contents...

What is highway economics and what are its main contents to study ?

Explain the suppressed rectangular weir, Explain the Suppressed Rectangular...

Explain the Suppressed Rectangular Weir If the length of the weir (b) equals the width of the channel, i.e., the flow is not "contracted".

Erosion ocntrol, java program to design a SD-3 sediment pond per Georgia er...

java program to design a SD-3 sediment pond per Georgia erosion control manual

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd