Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Define major ions present in the water, Define Major Ions present in the wa...

Define Major Ions present in the water  Cations:  Calcium, Magnesium, sodium, potassium Anions: Bicorabonate, sulfate, chloride Other ions present: Iron. Manganese, Fluor

Segmentally lined and sprayed concrete linings tunnels, Q. Segmentally line...

Q. Segmentally lined and Sprayed Concrete Linings tunnels? The fundamental difference between segmentally lined tunnels and SCL tunnels is that the sprayed concrete in SCL tunn

Joint filler in concrete expansion joints - a must, Joint filler in concret...

Joint filler in concrete expansion joints - a must?? Presence of joint filler is required to the proper functioning of concrete joints however some may doubt its value. For a c

Importance of geotextiles and sand in reclamation works, Question What ...

Question What is main importance of geotextiles and sand in reclamation works? Answer For geotextiles used in recovery, they serve mainly subsequent two purposes

Chemistry, scale and sludge formation in boilears

scale and sludge formation in boilears

What are the stresses on the plane of failure, A granular soil is subjected...

A granular soil is subjected to a minor principal stress of 200 kN/m 2 . If the angle of internal friction is 30°, verify the inclination of the plane of failure with respect to th

Plane table surveing, in plane table surveying which activity is done first...

in plane table surveying which activity is done first whether centering or levelling?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd