Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Common defects - bituminous roads, Common defects - bituminous roads: ...

Common defects - bituminous roads: Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt. If an overlay is to be laid on a cracke

Determine the types of losses of prestress, Determine the types of losses o...

Determine the types of losses of prestress A loss of prestress will affect the stress distribution on a section of the member. It is therefore necessary to estimate the probabl

Strength of rivet joints, Ask question #Minimum 100 Please help me to...

Ask question #Minimum 100 Please help me to write a c program to determine strength and efficiency of single cover butt joint, lap joint, double cover butt joint . words ac

Determine concentration of total solids and volatile solids, The following ...

The following test results were obtained for a 100 ml wastewater sample taken at the inlet to wastewater treatment plant.  The tests were performed using the standard methods. Dete

What is shock transmission unit in bridges, Q. What is Shock transmission u...

Q. What is Shock transmission unit in bridges? Shock transmission unit is fundamentally a device connecting separate structural units. It's characterized by its ability to tran

What is thermo-electric prestressing, What is Thermo-electric prestressing ...

What is Thermo-electric prestressing We know that, stretched tendons are used in prestressed concrete. Stretching of tendons may be accomplished by using jacks or by other mea

Urban transport systems, Urban Transport Systems: Urban Transport P...

Urban Transport Systems: Urban Transport Problem Rapid urbanisation is taking place in India. The current urban population proportion of 28 per cent may reach 40 per

Foundation depth and arrangement, Foundation Depth and Arrangement: Th...

Foundation Depth and Arrangement: There are two types of foundations, viz, (a) Shallow foundations, also known as open foundations, and (b) Deep foundations. Slab cul

Calculate the number of trucks for fleet working, A contractor was awarded ...

A contractor was awarded a Contract to excavate and haul 200,000-yds 3 of silty clay (USCS classification ML) with a bulking factor of 30%.  The contractor's fleet of dump trucks

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd