Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Comparing speed, Question Comparing speed of "Formwork exceeding 300mm wide...

Question Comparing speed of "Formwork exceeding 300mm wide, horizontal and at any inclination up to and including 5o to horizontal" with speed of "Formwork exceeding 300mm wide, at

State the term - transverse force on concrete, State the term - transverse ...

State the term - transverse force on concrete We know that in pre-stressed concrete, tendons are placed in a stretched condition and they always would try to regain their origi

Disparity between fasteners, Question What is major disparity between ...

Question What is major disparity between fasteners , bolts and screws ? Answer Fastener is a broad term to explain something that is used as a restraint for holding

Minimum and maximum distance between bars, Q. Minimum and maximum distance ...

Q. Minimum and maximum distance between bars? Minimum distance between bars and maximum distance between bars In some codes, a minimum distance amid bars is specified to

How to design marginal embankments, Q. How to design Marginal Embankments? ...

Q. How to design Marginal Embankments? Design aspects of marginal embankments are similar to those of approach banks. The aspects needing special attention are dealt with below

#title., desirable properties in green concrete

desirable properties in green concrete

Energy absorbed in heeling during vessel berthing, Q. Energy absorbed in he...

Q. Energy absorbed in heeling during vessel berthing? When a vessel   berths on a fender system at a pier, point of contact of berthing ship can be below or above the centre of

Calculate the effective annual interest rate, A credit card advertises a no...

A credit card advertises a nominal rate of 18% compounded monthly. If no monthly payments are made, the effective annual interest rate is most nearly: The actual rate is, (18%

Factors affecting location decision, Factors Affecting Location Decision: ...

Factors Affecting Location Decision:   Mining, quarrying and heavy manufacturing have capital intensive facilities that are costly to build and cover large area and use large q

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd