Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Elastic curve, elastic curve of a simply supported beam with triangular loa...

elastic curve of a simply supported beam with triangular load

Foundation, what are factors that affect bearing capacity of a shallow foot...

what are factors that affect bearing capacity of a shallow footing

Colour code, in colour working drawing what are the colour code?

in colour working drawing what are the colour code?

Dynamic force transfer test of shock transmission unit, Define Dynamic Forc...

Define Dynamic Force Transfer Test of Shock Transmission Unit? This test mainly prove the lock up capability of the device. The STU shall be loaded in tension from zero to the

Explain the unconfined compression strength of the clay, A square group of ...

A square group of 9 piles was driven into soft clay extending to a large depth. The diameter and length of the piles were 30 cm and 9 m respectively. If the unconfined compression

Loss of prestress due to elastic shortening, Loss of prestress due to elast...

Loss of prestress due to elastic shortening At the transfer of prestress, tensile stresses of tendons are transferred to concretc in the form of compressive stresses. Due to t

Large scale integration chips have between the components, Large scale int...

Large scale integration chips have between the  components? Answer : It is between 100 and 1000 components.

Workshop drawings, Workshop Drawings  (Contractor Scope) 1. Air Co...

Workshop Drawings  (Contractor Scope) 1. Air Conditioning and Ventilation Systems: Builder work drawings Enlarged scale double line HVAC System Duct & piping layouts

Meaning of driving succession of driven piles, Question What is meaning...

Question What is meaning of driving succession of driven piles? Answer In Basement construction, if piles are driven from centre to perimeter, there is a propensity o

Stress strain curves, stress strain curves for any materials with an explan...

stress strain curves for any materials with an explanation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd