Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

How do you measure concrete, We can measure concrete by Cubic feet, Cubic y...

We can measure concrete by Cubic feet, Cubic yards, Cubic Meter

Surveying, closed traverse ABCDE form a regular polygon with fore bearing o...

closed traverse ABCDE form a regular polygon with fore bearing of line is 35 find the bearing of other lines

Uncompacted bedding for concrete pipes, Uncompacted bedding for concrete pi...

Uncompacted bedding for concrete pipes In the middle third of the base of precast concrete pipes, bedding layers are suggested to be left Uncompacted since it helps to decreas

Designing of watermain, Question In designing of watermain , regular p...

Question In designing of watermain , regular practice is to use supple iron for pipe size less than 600mm and to use steel for pipe size additional than 600mm. Give some speci

Levellng, introduction of levelling

introduction of levelling

Explain about noise absorptive materials, Q. Explain about Noise absorptive...

Q. Explain about Noise absorptive materials? The fundamental mechanism of noise absorptive material is to change the acoustic energy into heat energy. Amount of heat produced i

Building, individual wall methods benefits?

individual wall methods benefits?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd