Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

State about the prestressing steel, State about the Prestressing Steel ...

State about the Prestressing Steel For prestressed concrete members, the high-tensile steel, used generally, consists of wires, bars or strands. The high tensile strength of s

Survey, 3-d figure of line ranger

3-d figure of line ranger

What do you know about shallow piers, Q. What do you know about Shallow Pie...

Q. What do you know about Shallow Piers? In case of some of the existing bridges, piers may be shallow and grip may be found to be inadequate. Protection round piers is then re

Surveying, what do you understand by the term local attraction

what do you understand by the term local attraction

Define hand tools for underwater inspection of bridge, Define Hand Tools fo...

Define Hand Tools for Underwater Inspection of Bridge? Hand tools involve scrapers, wire brushes, chain and wire ropes. Tools of this kind are suited in which cleaning is confi

Differences between epoxy grout and cement grout, Differences between epoxy...

Differences between epoxy grout, cement grout and cement mortar? Epoxy grout comprises epoxy resin, epoxy hardener and aggregates/sand.As a matter of fact, there are various ty

Forces reactions at that point, Mad/Sir What would be the Horizontal and ve...

Mad/Sir What would be the Horizontal and vertical component from this acting force see diagram

Diferential equations, show that Y = 4e2x - 2e-3x is a solution of initia...

show that Y = 4e2x - 2e-3x is a solution of initial-value problem (d2y)/(dx2)+ (dy)/(dx) - 6y=0 ; y(0)=6 ; y’(0)=2 . is Y = 2e2x - 4e-3x also a solution of this proble

Explain horizontal circular curves - transportation, Explain Horizontal Cir...

Explain Horizontal Circular Curves - Transportation Horizontal circular curve is a circular arc between two straight lines known as tangents.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd