Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Pumping for concreting works, Question What are the key problems if use pu...

Question What are the key problems if use pumping for concreting works ? Answer In pumping operation , force exerted by pumps have to overcome friction involving concrete an

Recognize the losses of prestress, Recognize the losses of prestress Re...

Recognize the losses of prestress Recognising the losses of prestress which take place after the prestressing OF concrete structural elements, it is to be appreciated that pres

Geodesy, what is the difference between geodesy and plane survey

what is the difference between geodesy and plane survey

Chain survey, what are the obstacles in chain survey in brief

what are the obstacles in chain survey in brief

Pressure distribution under rigid and flexible footings, Pressure distribut...

Pressure distribution under rigid and flexible footings For rigid and thick footings, pressure distribution under the footings is generally presumed to be linear. If symmetric

Biological wastewater engineering, a. We put a lot of time and effort into ...

a. We put a lot of time and effort into cultivating our activated sludge microbial community. So why do we waste sludge out of it? b. A wastewater discharges to Puget sound, a mari

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd