Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

What is the unit weight of water, In a pipette analysis, 0.5 N of dry soil ...

In a pipette analysis, 0.5 N of dry soil (fine fraction) of specific gravity 2.72 were mixed in water to form half a litre of uniform suspension. A pipette of 10 ml capacity was

Engineering Mechanics, the jet transport B is flying north with a velocity ...

the jet transport B is flying north with a velocity vB = 600 km/h when a smaller aircraft A passes underneath the transport headed in the 60 degree direction shown. To passengers i

Explain the term - non-bonded prestressed concrete, Explain the term - Non-...

Explain the term - Non-bonded Prestressed Concrete It is a method of construction in which the tendons are not bonded to the concrete. Ducts, housing the tendons, are not grout

State an expression for zero air-void line, State an expression for 'zero a...

State an expression for 'zero air-void line' and illustrate the line for a specific gravity of 2.65. What are the various factors that affect the compaction of soil in the field

How can a temporary diversion to laid, Q. How can a temporary diversion to ...

Q. How can a temporary diversion to laid a cross flowing river in case of disruption to rail traffic over a major bridge lasting over 6 months. Ans.- Temporary diversion

Methods of contouring by grid points, the elevations of grid points for an ...

the elevations of grid points for an area as follows: 1 2 3 4 5 6 7 8 F 690 709 726 732 735 740 743 747 E 696 715 729 736 740 737 739 740 D 702 723 733 742 737 737 745 747 C 707 72

Steel design, have a beam with one lateral restraint at bottom and top flan...

have a beam with one lateral restraint at bottom and top flange and load on top flange, should I use 2 segments or one segment of the beam ignoring bottom restraint as it is not in

Question, The state of stress at a point is given by the stress components ...

The state of stress at a point is given by the stress components sx = 70 MPa, sy = 10 MPa and ?xy = - 40 MPa. Using Mohr''s circle, find (i) Principal stresses, and (ii) Principal

Example for productivity analysis and improvement, Example for Productivity...

Example for Productivity Analysis and Improvement An excavator with a bucket capacity of 3-yd 3 has a standard production rate of 2,160-yd 3 for an 8-hour day.  The job site

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd