Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Define design aspects of pot bearing, Define Design Aspects of Pot Bearing?...

Define Design Aspects of Pot Bearing? Basic elements of a POT bearing are: - POT or a shallow cylinder - An elastomeric pad - A set of sealing rings - A piston P

Ranging, defference between direct and indirect ranging..

defference between direct and indirect ranging..

Purpose of using capping layers in pavement construction, Q. Purpose of usi...

Q. Purpose of using capping layers in pavement construction? When California Bearing Ratio of subgrade is checked to be below a specific percentage (for example 5%), a capping

Stability of column, what is end condition how effected length is calculate...

what is end condition how effected length is calculated

Verify the magnification and transmitted force, The exciting force in a con...

The exciting force in a constant force type of excitation was 120 kN. The natural frequency of the machine foundation is 4 Hz. The damping factor is 0.36. Verify the magnificati

W/c ratio, first of all i want to think you for this helpful website , and ...

first of all i want to think you for this helpful website , and let me ask you this question . how to calculate w/c ratio ? thank you so much for you .

Determine length of guide bunds, Q. Determine Length of guide bunds? Leng...

Q. Determine Length of guide bunds? Length of a guide bund has to be such that the flow approaching even from behind the guide bund would pass through the bridge with minimum obl

What are probable solutions to rectify the situation, Question If in ca...

Question If in case mud waves occur during reclamation, what are probable solutions to rectify the situation? Answer (i) Option 1 - Complete Removal of All Disturb

Permanent magnets are made of what kind of materials, Permanent magnets are...

Permanent magnets are made of what kind of materials ? Answer: It is made of hard magnetic materials.

Engineering project control, need help with my assignment. An Asian Pacific...

need help with my assignment. An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Pref

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd