Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Passenger terminal building, Passenger Terminal Building: Importanc...

Passenger Terminal Building: Importance In a civil airport, the passenger terminal building is the centre of all activities. It services both inbound and outward boun

Offset(survey)., what is meant by the offsets and explain its type?

what is meant by the offsets and explain its type?

Earth fill dams, Ask question #Minimum 100E. The regulations and specificat...

Ask question #Minimum 100E. The regulations and specifications that followed for compaction works for earth dam in Oman words accepted#

Ductility test, Ductility Test: The ductility of a bituminous binder ...

Ductility Test: The ductility of a bituminous binder is its ability to deform under load and return to its original condition after removal of the load. The property is deter

Define the precedence diagramming methods, Define the Precedence Diagrammin...

Define the Precedence Diagramming Methods a) Activity on Node (AON) with arrows for dependencies b) Uses all forms of precedence relationships

Loading and unloading cycles for soil nails, In carrying out pull-out tests...

In carrying out pull-out tests for soil nails, it generally requires the unloading and loading of soil nails of several cycles up to 80% of ultimate tensile strength of soil nails.

Define types of deterioration in steel substructure, Define Types of Deteri...

Define Types of Deterioration in Steel Substructure There are 5 major types of deterioration in steel substructure in the marine environment: - Corrosion - Abrasion - Loo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd