Question
Comparing speed of "Formwork exceeding 300mm wide, horizontal and at any inclination up to and including 5o to horizontal" with speed of "Formwork exceeding 300mm wide, at any partiality more than 85o up to and including 90o to horizontal", which is advanced?

Answer
Item "Formwork exceeding 300mm wide, at any partiality additional than 85o up to and including 90o to horizontal" refers to formwork formed vertically and while compared with formwork erected in horizontal plane, quantity of false work required is lesser.

Item "Formwork exceeding 300mm wide, horizontal, at any inclination up to and including 5o to horizontal" refers to formwork to be vertical in horizontal position and in general it requires much false work to carry this type of formwork. Therefore, speed for this item is advanced than one mentioned in above section.


Related Discussions:- Comparing speed

Retaioning walls, what are the uses of retaining wall?!

what are the uses of retaining wall?!

Is cbr test is an arbitrary test, CBR Test is an arbitrary test', justify. ...

CBR Test is an arbitrary test', justify. Explain the procedure for conducting the CBR test in the field. Surcharge loads are used in the CBR test; Describe their significa

Purpose of the gap in the road on this bridge, What is the purpose of the g...

What is the purpose of the gap in the road on this bridge? Ans) Purpose of the gap in the road is to permit the road to expand and contract with temperature alters without causi

Physical tests on cement, Physical Tests on Cement (a) Soundness Test: ...

Physical Tests on Cement (a) Soundness Test: by sieve analysis, it is conducted. 100 gms of cement is taken and sieved throughout IS sieve No. 9 for fifteen minutes. Residue on

Determine the example of tendon splices, Determine the example of tendon s...

Determine the example of tendon splices Following are some examples of  tendon splices. (a) Torpedo splice (b) Clamp splice (c)  Screw connectors

Define pneumatic tools for underwater inspection of bridge, Define Pneumati...

Define Pneumatic Tools for Underwater Inspection of Bridge? These are more efficient than hand tools and cause less diver fatigue. The disadvantages are that below about 20 m,

Solid mensuration, a street light is 15 ft directly above the curb. a 6 ft ...

a street light is 15 ft directly above the curb. a 6 ft man starts 10 ft down the street from the light and walks directly across the street which is 10 ft wide. when he reaches th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd