Comparing speed of "Formwork exceeding 300mm wide, horizontal and at any inclination up to and including 5o to horizontal" with speed of "Formwork exceeding 300mm wide, at any partiality more than 85o up to and including 90o to horizontal", which is advanced?

Answer
Item "Formwork exceeding 300mm wide, at any partiality additional than 85o up to and including 90o to horizontal" refers to formwork formed vertically and while compared with formwork erected in horizontal plane, quantity of false work required is lesser.

Item "Formwork exceeding 300mm wide, horizontal, at any inclination up to and including 5o to horizontal" refers to formwork to be vertical in horizontal position and in general it requires much false work to carry this type of formwork. Therefore, speed for this item is advanced than one mentioned in above section.


Related Discussions:- Comparing speed

Lintel, what is the classification of lintel

what is the classification of lintel

Determine the head added by the pump, Primary effluent wastewater at 60 o F...

Primary effluent wastewater at 60 o F (v = 1.217 x 10 -5 ) is pumped to the top of a trickling filter (TF) a total of 75 vertical feet through schedule-40 welded steel pipe. The fl

What is load carrying capacity of a pile, Q-  What are loads and forces ta...

Q-  What are loads and forces taken into account for designing a pile and what is load carrying capacity of a pile. Ans. For designing a pile the following loads and force ar

Design of flexural members, Design of Flexural Members: Here you have ...

Design of Flexural Members: Here you have learnt how to design simple steel beams of rolled steel sections subjected to transverse loading. You have also known how to take

Chain survey, Instruments used in chain survey

Instruments used in chain survey

Explain the departure of a line - transportation, Explain the Departure of ...

Explain the Departure of a line - Transportation Departure of a line is the distance that the line extends in an east or west direction. A line that runs towards east has a pos

Marine pilling, what are the problems in traditional marine pilling system ...

what are the problems in traditional marine pilling system of steel tubular pile with concrete infill

Flow, what is maximum flood level

what is maximum flood level

Tack rivet, tack rivet figures with connections

tack rivet figures with connections

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd