How to design banks, Civil Engineering

Assignment Help:

Q. How to design banks?

When approach banks are of medium height upto 3 m, the material may be homogeneous. For bigger heights zoned section with impervious core and pervious outer sections may be desirable.

Foundation should provide a stable support for overlaid bank and should resist harmful percolation. Unconsolidated material in foundation is liable to settlement and percolation of water. Cut off trenches backfilled with rolled impervious material, sheet pile cut off, grouting, clay blanket on upstream side and inverted filter on downstream side are helpful in minimising harmful effect of percolation.


Related Discussions:- How to design banks

Define emerging trends in bearings, Define Emerging Trends in Bearings? ...

Define Emerging Trends in Bearings? New innovations have taken place in the area of bridge bearings, notable among them are: (1) Shock Transmission Unit (STU) or Lock Up Dev

3 wire leveling, can you give me some examples and problems in 3-wire level...

can you give me some examples and problems in 3-wire leveling?

What is contact pressure, What is 'contact pressure'? How does it depend on...

What is 'contact pressure'? How does it depend on the type of structure and type of soil? What is 'active zone' in soil? Define it with reference to the pressure bulb concept.

Determine minimum radius that can used on horizontal curve, What is the min...

What is the minimum radius, R min , that can be used on a horizontal curve with a 70 mph design speed, a maximum superelevation, e max = 8%, and a side friction factor, f = 0.10?

Obstacle measurement.., ..describe how u can obtain the length of an inacce...

..describe how u can obtain the length of an inacceble length of a land when a river cross it

Moment of inertia, i dont know how to calculate moment of inerta

i dont know how to calculate moment of inerta

Determine the maximum pressure at the base of the wall, A masonry retaining...

A masonry retaining wall of trapezoidal section with the vertical face on the earth side is 1.5 m wide at the top and 3.5 m wide at the base and is 5.0 m high. It retains a sand fi

Zero energy building , this is our final year project .please help me to gu...

this is our final year project .please help me to guide about it

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd