How to design banks, Civil Engineering

Assignment Help:

Q. How to design banks?

When approach banks are of medium height upto 3 m, the material may be homogeneous. For bigger heights zoned section with impervious core and pervious outer sections may be desirable.

Foundation should provide a stable support for overlaid bank and should resist harmful percolation. Unconsolidated material in foundation is liable to settlement and percolation of water. Cut off trenches backfilled with rolled impervious material, sheet pile cut off, grouting, clay blanket on upstream side and inverted filter on downstream side are helpful in minimising harmful effect of percolation.


Related Discussions:- How to design banks

Define the void ratio and specific gravity of particles, Derive the formula...

Derive the formula among soil moisture content (w), degree of saturation (S), specific gravity (G), and void ratio (e). Saturated clay has a water content of 40% and bulk specif

What is the specific gravity of the soil, An oven-dried soil weighing 1.89 ...

An oven-dried soil weighing 1.89 N is placed in a pyknometer which is then filled with water. The total weight of the pyknometer with water and soil is 15.81 N. The pyknometer fill

Good surface regularity for sub-base in concrete pavement, Q. Good surface ...

Q. Good surface regularity for sub-base in concrete pavement? Surfaces of sub-base material for concrete carriageway must be built in a regular manner due to the following reas

Deflection in concrete structures, Tension reinforcement leads to increasin...

Tension reinforcement leads to increasing deflection in concrete structures? In BS8110 a modification factor is applied to span/depth ratio to take into account effect of tens

Determine about the prestressed concrete, Determine about the Prestressed c...

Determine about the Prestressed concrete Prestressed concrete is a special type of concrete in which internal stresses of a suitable nature, magnitude and distribution are int

Rcc lintel, how to make a leakproof joint with existing lintel

how to make a leakproof joint with existing lintel

Application of quadratic equation, list some applications of quadratic equa...

list some applications of quadratic equation in civil engineering

Sucker deck principle for changeable depth bridge decks, Question What is t...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate

Quality control in flexible pavements, Quality Control in Flexible Pavement...

Quality Control in Flexible Pavements: The quality control needed for Flexible Pavements covers the following tests : (a) Density and Moisture content of sub-grade. (b)

Brick mansory, Aim,materials or tools required,procedure for constructing e...

Aim,materials or tools required,procedure for constructing english bond bricks

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd