Specification of water bound macadam road, Civil Engineering

Assignment Help:

Q. Specification of Water bound macadam road?

Formation - The embankment for road shall be made to the cross section shown on the drawing. The bank shall be raised in regular layers & rolled & consolidated by the action of rain. The surface of the formation must be barreled to template before any metal laid.
Soling - For roads over which heavy traffic is probable soling of hand packed rubble will first be laid and consolidated with a road roller.

Metal - The metal shall be of a close, tough hard texture and be broken so as to pass in any direction through a five-cm. square mesh for under layers and through a 4 cm. Square mesh for the surface each piece should be squared and sharp. No rounded pebbles angular, chips or flakes shall be used.

Gravel and sand, Moorum -Gravel shall be composed of large coarse grains free from dirt & impurities. Sand used for blinding road surface shall be sharp gritty and clean and quantity used must not exceed in depth. Moorum shall be good, hard, clean & free from clay.

Stacking - The material shall be stacked in continuous heaps of such size and uniform dimension and height not less 60 cm. That each running meter will contain the quantityrequired a running meter of road. The metal for the lower and upper layer will be stacked on opposite sides of the road.

Consolidation - The lower layer of the metal will first be watered and consolidated the upper layer will than be laid the surface being dressed true to template shown on the drawing and consolidated a sufficient blinding of sand or moorum will be used to ensure the metal blinding and through watering and rolling continued until the surface is hard and smooth. Rolling will be done with a road roller weighting 8 To 10 Tones.


Related Discussions:- Specification of water bound macadam road

Assessing maintenance needs, Assessing Maintenance Needs: Maintenance...

Assessing Maintenance Needs: Maintenance needs can be assessed by a careful inspection of roads at regular intervals, observing defects such as : potholes cracks

Structures, What is the economic span of a bridge

What is the economic span of a bridge

Concrete, whats the role of gypsum in concrete?

whats the role of gypsum in concrete?

Guidelines for selection of site, Guidelines for Selection of Site: Th...

Guidelines for Selection of Site: The following are some of the guidelines for selecting the site of a bridge : (a) A site which is on a straight reach of the river is pref

Difference between compaction and consolidation of soil, Briefly explain th...

Briefly explain the difference between compaction and consolidation of soil. What is the effect of compaction on soil properties? Ans.- Compaction - The process of increas

Determine the term - final tension, Determine the term - Final Tension ...

Determine the term - Final Tension The tension in tendons after losses of prestress have taken place is called as final tension. Final tension is taken to be corresponding  to

Rb slab, #questionshow me picture..

#questionshow me picture..

Roads, how to calculate number of passes while compaction

how to calculate number of passes while compaction

What is the required bracing location for the beam, A contractor has select...

A contractor has selected a W14x74 simply supported beam for a high rise construction project.  The span length for the provided beam is set at 30 feet.  The maximum factored appli

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd