Functions of different reinforcement in a typical pile cap
Loads from columns transferring to pile cap persuade tensile forces at the bottom of cap. For example, by using truss analogy to analyse a pile cap sitting on two piles with a column at the centre of pile cap, tensile force at the bottom is proportional to pile spacing and is inversely proportional to depth of pile cap. Bottom reinforcement is designed to resist the tensile stressed produced from loads in columns.
Side reinforcement may not be essential in pile cap. As a matter of fact, primary aim of the side reinforcement is to control cracking. Though as most pile caps are hidden from view and it's considered not essential to provide side reinforcement to pile caps based on aesthetic reason.
Occasionally reinforcement can be designed at the top of pile caps that serve as compression reinforcement. This kind of reinforcement is essential in case there is a limitation on the depth of pile caps. Likewise shear reinforcement is introduced to the pile caps just in case there is a restriction to depth of pile caps.
base course material specification?
what are the cement testing?
Torpedo splice triple wedges In a Torpedo splice triple wedges, shown in Figure, are provided to firmly hold tendon wires. Whole assembly of the splice is housed in a sleeve. L
closed traverse ABCDE form a regular polygon with fore bearing of line is 35 find the bearing of other lines
Pipelines: Use of Pipelines in Transport Pipelines are used for transporting liquids (petroleum products for example), gases and solids in slurry form (for example ir
Explain the Non Destructive Inspection Steel/Cast Iron Substructures Some of the structural defects in steel structures may not be visible during visual inspection. In that eve
1) A propped cantilever beam ABC is 7m long.It has the point C fixed and Point A on a roller support.It carries a 200Kn point load at a distance 3m from A.There is a moment of 80KN
Discuss about the post-tensioning systems In most of post-tensioning systems, when the cable is tensioned and the jack is released to transfer prestress to concrete, the fricti
The load from a continuous footing of 1.8 metres width, which may be considered to be a strip load of considerable length, is 180 kN/m 2 . Verify the maximum principal stress at 1.
Question What is key function of packing resources in joint of concrete pipes in pipe jacking ? Answer Packing resources are about 10 to 20mm broad and are usually mad
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd