What do you mean by depth of scour, Civil Engineering

Assignment Help:

Q. What do you mean by Depth of Scour?

The maximum scour depth in a stream can be ascertained when ever possible by actual sounding at or near the site proposed for the bridge during or immediately after a flood. Before the scour holes have had time to silt up due to allowance should be made in the observed depth for increase in scour resulting from-

  1. The designed discharge being greater than the flood discharge during which the scour was observed.
  2. The increase in velocity due to the obstruction in flow caused by construction of the bridge.

Where the above practical method of determining scour is not possible the following theoretical method may be used as a guide when dealing with natural streams is alluvial beds.      

D = 0.473 [ Q / F ]? 

Where D = Depth of scour below HFL for regime conditions in a stable channel in meters.

           Q = Design discharge in cumecs.  

           F= Silt factor = 1.76 √m , m is the mean diameter of particles in mm.


Related Discussions:- What do you mean by depth of scour

Surveying, difference between observed magnetic bearing and true magnetic b...

difference between observed magnetic bearing and true magnetic bearing

Grades of concrete, mixing ratio of different type of ready mix concrete.(R...

mixing ratio of different type of ready mix concrete.(RMC)

Explain the unit hydrograph - hydrology, Define Unit Hydrograph Hydrogr...

Define Unit Hydrograph Hydrograph of one inch or 1cm of precipitation over a drainage basin area (watershed). It is the base hydrograph from which other hydrographs can be dete

Street originate in the plumbing term street ell, How did street originate ...

How did street originate in the plumbing term street ell? Ans) A "street ell" may have gotten its name due to it describes a 90° fitting particularly useful in tight, street dit

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Define the both inside clearance and outside clearance, The inner diameters...

The inner diameters of a sampling tube and that of a cutting edge are 70 mm and 68 mm correspondingly, their outer diameters are 72 and 74 mm respectively. Verify the inside cle

What are moment of inertia, The moment of inertia calculates the opposition...

The moment of inertia calculates the opposition any kind of body will have against a certain momentum (along that similar axis) trying to rotate that body.

Particle size distribution - soil compaction, Particle Size Distribution (G...

Particle Size Distribution (Gradation): The particle size distribution is determined by passing the aggregates through a set of standard IS sieves (Figure) and determining th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd