What do you mean by depth of scour, Civil Engineering

Assignment Help:

Q. What do you mean by Depth of Scour?

The maximum scour depth in a stream can be ascertained when ever possible by actual sounding at or near the site proposed for the bridge during or immediately after a flood. Before the scour holes have had time to silt up due to allowance should be made in the observed depth for increase in scour resulting from-

  1. The designed discharge being greater than the flood discharge during which the scour was observed.
  2. The increase in velocity due to the obstruction in flow caused by construction of the bridge.

Where the above practical method of determining scour is not possible the following theoretical method may be used as a guide when dealing with natural streams is alluvial beds.      

D = 0.473 [ Q / F ]? 

Where D = Depth of scour below HFL for regime conditions in a stable channel in meters.

           Q = Design discharge in cumecs.  

           F= Silt factor = 1.76 √m , m is the mean diameter of particles in mm.


Related Discussions:- What do you mean by depth of scour

Stone, Explain the crushing strength test

Explain the crushing strength test

Precast pile, when a precast pile is single point lifting and when double p...

when a precast pile is single point lifting and when double point lifting- what are the moment coefficient of them?

Define factor that is not concerned with schedule control, Schedule control...

Schedule control is concerned with all of the following except: a. Influencing the factors which create schedule changes b. Determining that the schedule has changed c.

Determine the uniformly distributed load, A rectangular area 4 m × 6 m carr...

A rectangular area 4 m × 6 m carries a uniformly distributed load of 100 kN/m 2 at the ground surface. Estimate the vertical pressure at a depth of 6 m vertically below the centre

Show the differences between GGBS and PFA, Q. Show the Differences Between ...

Q. Show the Differences Between GGBS and PFA? The use of GGBS as substitute of cement improves smaller reliance on PFA. Particularly GGBS is supposed to be more compatible with

Highway Engg, what are lab and field test carried on soil subgrade

what are lab and field test carried on soil subgrade?

Underwater problems in bridge construction, Q. Underwater problems in bridg...

Q. Underwater problems in bridge construction? The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as binding

DC POWER SUPPLY, DESIGN A LINEAR DC POWER SUPPLY WITH THE FOLLOWING SPECIFI...

DESIGN A LINEAR DC POWER SUPPLY WITH THE FOLLOWING SPECIFICATION,SHOW DETAILS STEPS AND CALCULATION...Vload :12v Iload :0.07A Vripple load(p-p) :0.01v TA :45 DEGREE CELCUS

Structures, Derivation of Moment-Area Method

Derivation of Moment-Area Method

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd