Q. Function of prime coat in bituminous pavement?
The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the presence of moisture affects the strength of subgrade, prevention of water entry at the time of construction is essential to avoid the failure of the pavement. In cold countries, by getting rid of moisture from subgrade, danger of frost heave can be minimized.
Prime coat is an asphalt that, when applied evenly to the surface of subgrade orsub-base, serves to seal the surface to hinder the penetration of moisture into subgrade. Vehicular traffic must be avoided on the surface sprayed with prime coat since the traction and tearing action of vehicles would damage this asphalt layer.
Fig: Position of application of prime coat
The discharge of water collected from a constant head permeameter in a period of 15 minutes is 500 ml. The internal diameter of the permeameter is 5 cm and the measured difference
Riveted and Welded Joints: This theory deals with riveted and welded connections. In riveted connections, you have learnt different types of rivet and various parameters perta
stress
Q. Roadworks - filler and binder in bituminous pavement? In bituminous materials, course aggregates perform the bulking action of mixture and contributes to stability of result
Q. Explain about Catch Sidings? Normally all catch sidings except those which are sanded shall be kept alive. On sanded catch siding, the rails shall be kept clear of sand for
dowel or aggregate interlock ?how to decide?
shear stress numerical of T section & I section to find maximum shear stress
design of irrigation channel permissible velocity table
The state of a pure substance of given mass is defined by specifying two appropriate properties provided that 1. The system is in equilibrium 2. Gravity, motion, electricity,
With a clear sketch indicate the system of protection of line for works of short duration where ‘ Stop dead restriction' need to be observed on a single line section on a BG track.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd