Q. Function of prime coat in bituminous pavement?

The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the presence of moisture affects the strength of subgrade, prevention of water entry at the time of construction is essential to avoid the failure of the pavement. In cold countries, by getting rid of moisture from subgrade, danger of frost heave can be minimized.

Prime coat is an asphalt that, when applied evenly to the surface of subgrade orsub-base, serves to seal the surface to hinder the penetration of moisture into subgrade. Vehicular traffic must be avoided on the surface sprayed with prime coat since the traction and tearing action of vehicles would damage this asphalt layer.

477_Function of prime coat in bituminous pavement.png

Fig: Position of application of prime coat


Related Discussions:- Function of prime coat in bituminous pavement

Discuss about the term - end zone, Discuss about the term - End Zone It...

Discuss about the term - End Zone It is the length of a post-tensioned concrete member, at the end, which is required to get a distribution of prestress over the whole of the c

Example, slope deflection with settlement

slope deflection with settlement

Consideration of hazards in design, • Gas turbines produce noise, heat radi...

• Gas turbines produce noise, heat radiation and exhaust gas emissions that are potentially a danger to health • Fuel is flammable and there are hot surfacesand moving parts

Define Carbonate hardness (ch) - water softening, Carbonate Hardness (CH) -...

Carbonate Hardness (CH) - Water Softening Ca +2 , Mg +2 combining with alkalinity (OH - , CO 3 -2 , HCO 3 - ). If alkalinity is present in water the CH wil

Analyse the state of stress at the critical section, Analyse the state of s...

Analyse the state of stress at the critical section: A prismatic bar of circular section with 80 mm diameter is subjected to bending moment of 5 kN-m and a torque of 7 kN-m. A

Importance of general and subsidiary rules, Q. What is the importance of Ge...

Q. What is the importance of General and subsidiary rules. What is the main differences between the two. Ans.- Importance of General and subsidiary  rules - General and su

Prime coat - road pavements, Prime Coat: A prime coat is the applicat...

Prime Coat: A prime coat is the application of a low viscosity binder, usually a bituminous emulsion, to a gravel, WBM or WMM surface, to enable the binder to fill up the voi

Chemistry, What is the difference between scale and sludge

What is the difference between scale and sludge

Design, what is the procedure to design the beam and column?

what is the procedure to design the beam and column?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd