Q. Function of prime coat in bituminous pavement?
The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the presence of moisture affects the strength of subgrade, prevention of water entry at the time of construction is essential to avoid the failure of the pavement. In cold countries, by getting rid of moisture from subgrade, danger of frost heave can be minimized.
Prime coat is an asphalt that, when applied evenly to the surface of subgrade orsub-base, serves to seal the surface to hinder the penetration of moisture into subgrade. Vehicular traffic must be avoided on the surface sprayed with prime coat since the traction and tearing action of vehicles would damage this asphalt layer.
Fig: Position of application of prime coat
Define Unit Hydrograph Hydrograph of one inch or 1cm of precipitation over a drainage basin area (watershed). It is the base hydrograph from which other hydrographs can be dete
Define the proess of Eccentric Prestressing In this form of prestressing, the centroid of cross-sectional areas of tendons is not located at the centroid of the cross-section.
A retaining wall with a vertical back 5 m high supports cohesion less backfill of unit weight of 19 kN/m 3 . The upper surface of the backfill rises at an angle of 10° with the hor
Q. Show the Purpose of granular bedding for concrete pipes? When designing the bedding for concrete drainage pipes, granular materials are generally specified in place of soils
Test for determination of Shear Modulus Conditioning load : Bearings shall be preloaded with maximum horizontal load Htest (with Ntest or vertical load held constant) and un
please explain about system engineering in civil
Sub-base for concrete carriageway - non-strength provider Essentially sub-base for a concrete carriageway is provided for the below reasons: (i) It provides aneven and smo
find the area bounded by the curve y=3x(x-2)^2 and the x-axis
What quantity of cement will be needed to lay 2000 blocks of 9 inches using a mortar ratio of 1:6 with a thickness of 25mm in-between blocks.
Define Structural Damage - underwater inspection of bridge? Structural damage to the substructure below waterline can be classified as under: i. Construction damage or error
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd