Q. Function of prime coat in bituminous pavement?
The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the presence of moisture affects the strength of subgrade, prevention of water entry at the time of construction is essential to avoid the failure of the pavement. In cold countries, by getting rid of moisture from subgrade, danger of frost heave can be minimized.
Prime coat is an asphalt that, when applied evenly to the surface of subgrade orsub-base, serves to seal the surface to hinder the penetration of moisture into subgrade. Vehicular traffic must be avoided on the surface sprayed with prime coat since the traction and tearing action of vehicles would damage this asphalt layer.
Fig: Position of application of prime coat
Landing Systems: There are two basic types of landing, viz : (a) visual landing, when the weather conditions are favourable, and (b) instrumented landing, when the weat
what is shear failure and shear force please explian?
Q. Explain Strain compatibility in mini-piles? In designing the axial capacity of mini-piles, grout can be taken into account in the contribution of axial load capacity. Though
Determine the concept of Shrink-fitting of metal tyres Shrink-fitting of metal tyres on the wheels of bullock carts is well known. As the hot metal tyre rings cool down, they a
what will be the w/c ration and cement/fly ash ration for the particular mix design
Q. What do you mean by M A S Accounts? This stands for material at site account. This is a suspense head of account that is maintained to watch actual consumption of materials
Q. One-way pre stressing vs two-way pre stressing? At the time of pre-stressing operation at one end, frictional losses will take place and the prestressing force decreases alo
Ground Water Levels The location of the ground water level is essential for deep excavation, water-logged areas. The existing wells in the nearby vicinity of the proposed site
Unsealed contraction joints in concrete pavement For unreinforced concrete pavement, contraction joint is an approximately 3mm wide groove with a depth of about one-third to o
Types and components of pavement
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd