Q. Function of prime coat in bituminous pavement?
The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the presence of moisture affects the strength of subgrade, prevention of water entry at the time of construction is essential to avoid the failure of the pavement. In cold countries, by getting rid of moisture from subgrade, danger of frost heave can be minimized.
Prime coat is an asphalt that, when applied evenly to the surface of subgrade orsub-base, serves to seal the surface to hinder the penetration of moisture into subgrade. Vehicular traffic must be avoided on the surface sprayed with prime coat since the traction and tearing action of vehicles would damage this asphalt layer.
Fig: Position of application of prime coat
Preparation for Underwater Inspection - Availability of Tools and Equipment The engineer-in-charge, before taking up the inspection, should list out the complete equipment req
Explain the Basic requirement of Design of shock transmission unit? The STU must withstand the specified design load. The stroke of the piston must be bigger than the movement
what is a causeway
A retaining wall is battered away from the fill from bottom to top at an angle of 15° with the vertical. Height of the wall is 6 m. The fill slopes upwards at an angle 15° away fro
Define the term - pre- tensioning It is a method of prestressing in which tendons are placed, inside ducts or passages provided in concrete, after concrete gains sufficient str
Horizontal Curves: When a vehicle of mass m moves on a curve of radius R with a speed of v (m/sec) (as shown in Figure 1) it is subjected to a centrifugal force equal to:
Solve the following three questions of the beam ABCD. Note that A is a fixed end; B is apin connection; C is a roller support; and D is a free end. 1) Sketch the quantitative
Q. By which Materials Shank of a spur construct? Shank of a spur is constructed of sand core and its exposed faces are protected by stone pitching. The attack at nose is very h
Explain step by step procedure involved in the analysis and design of balanced cantilever bridge.
Define the Ignitability - Hazardous Waste - is a liquid with flash point - Not a liquid and capable of spontaneous and sustained combustion under normal conditions - Ign
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd