Q. Function of prime coat in bituminous pavement?

The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the presence of moisture affects the strength of subgrade, prevention of water entry at the time of construction is essential to avoid the failure of the pavement. In cold countries, by getting rid of moisture from subgrade, danger of frost heave can be minimized.

Prime coat is an asphalt that, when applied evenly to the surface of subgrade orsub-base, serves to seal the surface to hinder the penetration of moisture into subgrade. Vehicular traffic must be avoided on the surface sprayed with prime coat since the traction and tearing action of vehicles would damage this asphalt layer.

477_Function of prime coat in bituminous pavement.png

Fig: Position of application of prime coat


Related Discussions:- Function of prime coat in bituminous pavement

Determine the equivalent of free float, The free float is equal to: a. L...

The free float is equal to: a. Latest allowable event occurrence time + Early finish time b. Earliest event occurrence time + early finish time c. Latest allowable event o

Explain census of traffic at level crossings, Q. Explain Census of Traffic ...

Q. Explain Census of Traffic at Level Crossings? Periodical census of traffic at all level crossings, unmanned/manned should be taken at least once in five years to review the

Sub-base for concrete carriageway - non-strength provider, Sub-base for con...

Sub-base for concrete carriageway - non-strength provider Essentially sub-base for a concrete carriageway is provided for the below reasons: (i)  It provides aneven and smo

Compatibility condition, Compatibility Condition: Total strain in ste...

Compatibility Condition: Total strain in steel = Total strain in copper i.e. 3 × 10 -4 + 1.965 × 10 -5 P s   = 4.5 × 10 -4 + 1.8421 × 10 -5 P c Recognising that P

Importance of racking load for a pre-stressed concrete beam, Importance of ...

Importance of racking load for a pre-stressed concrete beam Evaluation of cracking load for a pre-stressed concrete beam member is important for the following cases/reasons.

Explain the modular incinerators, Explain the Modular Incinerators 1. P...

Explain the Modular Incinerators 1. Prefabricated units with capacities of 4.5 to 107 tons of solid waste/day 2. Most use a system involving two combustion chambers.

Define categories of scaling-underwater inspection of bridge, Define the Ca...

Define the Categories of Scaling? Scaling is classified into following three categories: i. Light scale - loss of surface mortar up to 5 mm deep, with surface exposure of co

Column estimat, how maney point in columan parking estimate

how maney point in columan parking estimate

Gg, ggggggggggg

ggggggggggg

Remedial measures for problems in turbid water - absorption, Define Remedia...

Define Remedial measures for Problems in Turbid Water - Absorption? The process of absorption of light can be overcome by using higher powered lighting, or by using more light

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd