Q. Function of prime coat in bituminous pavement?
The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the presence of moisture affects the strength of subgrade, prevention of water entry at the time of construction is essential to avoid the failure of the pavement. In cold countries, by getting rid of moisture from subgrade, danger of frost heave can be minimized.
Prime coat is an asphalt that, when applied evenly to the surface of subgrade orsub-base, serves to seal the surface to hinder the penetration of moisture into subgrade. Vehicular traffic must be avoided on the surface sprayed with prime coat since the traction and tearing action of vehicles would damage this asphalt layer.
Fig: Position of application of prime coat
Use of Admixtures in Concrete The use of chemical admixtures may be made in prestressed concrete construction. But the admixture should not contain chlorides in any form. This
a) Certain data for the materials used in the construction of the building, e,g, insulation, building materials, air spaces, etc. b) Draw, with appropriate dimensions, the cro
Calculate the weight of the soil. Go to the first screen. 1. Establish the geometry of the member that you want to design. 2. Each member has to be designed separately.
Q. Coating on concrete – complete im-permeability to moisture? In designing protective coating on concrete structures, stoppage of water ingress by the coating is generally req
Determine the stresses set up in the brass: A compound bar is constructed from three bars 50 mm wide by 12 mm thick fastened together to form a bar 50 mm wide by 36 mm thick.
Q. What do you mean by Laying of apron in design of bridge? Width of apron laid on river bed should be 1.5 D1 where D 1 is estimated scour depth in metres below river bed. Thi
THE DESIGN PERIOD AVERAGE DAILY DEMAND CALCULATE. THE DESIGN DEMAND FOR THE WATER RETICULATION OR DISTRIBUTION PERIOD.
What is the Design Mix concrete Determination of the proportions of cement, aggregates and water to achieve the required strengths in concrete is made by designing the con
Define Seal wear test of shock transmission unit? Seal wear test: Seal prevents the leakage of silicon putty in the cylinder. The test is conducted for 30000 cycles assuming th
Q. What are advantages and disadvantage of varnishing? Varnish is a clear pale solution of a resinous substance ( like amber, common resin, copal, lac, or shellac 0 dissolved i
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd