Explain the statements about construction contract process, Civil Engineering

Assignment Help:

Explain the Statements about the Construction Contract Process

I. Surety bond assures the project owner a guarantee of funds equivalent to a promissory note. The surety bond is a promise to pay the owner a certain amount if the contractor fails in fulfilling the terms of a contract.

II. Performance bond is a surety bond issued by an insurance company or a bank to guarantee satisfactory completion of a project by a contractor. Performance bonds are issued upon Contract award and cost approximately 0.50% to 1.25% of the total contract value.

III. Builder's risk insurance is a special type of property insurance which indemnifies against damage to buildings while they are under construction. Risk insurance of Builder is coverage that protects a person's or an organization's insurable interest in materials, fixtures and/or equipment being utilized in the construction or renovation of a building or structure should those items sustain physical loss or damage from a covered cause

IV. A bid bond is issued as part of a bidding process by the surety to the project owner, to assurance that the winning bidder will undertake the contract under the terms at that they bid. The cash deposit is subject to full or partial forfeiture if the winning contractor fails to either execute the contract or provide the required performance and/or payment bonds. The bid bond assures and assurance that should the bidder be doing well, the bidder will execute the contract and provide the required surety bonds.

V. Bonds are not insurance. Bonds are a guarantee to pay made by a cosigner who is liable only if the principal fails to discharge the obligations under the Contract.


Related Discussions:- Explain the statements about construction contract process

Environmental engineering, A nearly horizontal, 12 ft wide rectangular chan...

A nearly horizontal, 12 ft wide rectangular channel carries 60 cfs at a depth of 3.0 ft. The width of the channel is smoothly contracted to 6 ft at the downstream section. (a) Dete

Key functions of changed components of paint, Question What are key fun...

Question What are key functions of changed components of paint? Answer For regular paint application, there are largely three key components of paint, namely primer, u

Drawbacks of curing by ponding and polythene sheets, Question What are the ...

Question What are the main drawbacks of curing by ponding and polythene sheets ? Answer Purpose of curing is to decrease the speed of heat loss of freshly placed concrete to atm

Aggregate value, how to calibrate AGGREGATE IMPACT VALUE TESTING MACHINE

how to calibrate AGGREGATE IMPACT VALUE TESTING MACHINE

Determine the uniformly distributed load, A rectangular area 4 m × 6 m carr...

A rectangular area 4 m × 6 m carries a uniformly distributed load of 100 kN/m 2 at the ground surface. Estimate the vertical pressure at a depth of 6 m vertically below the centre

Foundation, classification of foundation

classification of foundation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd