PART - A
1. Can you enumerate the benefits of individual wall method of estimation?
2. Estimate the single room of size 3m x 4m x height 3m using individual wall method?
3. Which method you will choose - center line method or individual wall method for estimation of buildings?
PART - B
4. Write the parameters you should keep in mind while estimating the RCC structures?
5. A singly reinforced concrete beam is 200 mm wide and 400mm deep to the center of the tension reinforcement which consists of 4 bars of 16mm diameter. If the stresses in concrete and steel are not to exceed 5N/mm2 and 140 N/mm2, Estimate the various materials for the said beam?.
6. A single room has four columns of size 400mm x 600mm x 3m. Estimate the total concrete required? Also estimate the various constituents of concrete? Use M20 grade of concrete? Assume the suitable data.
what is the type of slope protection that use rocks and put cements between those rocks??the concept is same as brick layer
Question What are designing considerations for dowel bars in joints of concrete carriageway? Answer Behaviour of dowel bars resembles that of piles in soils subject
compare 2 numbers and print either the message identifying the greater than number(or) the message starting that both number are equal
What do you understand by Pressure line If we determine the locations of resultant force at various sections of a pre-stressed beam, as in Example, we can draw a curve showing
semi dense bitumnous concrete overlays for roads
Define the Design of Piers and Abutments Erected in Water? All piers and abutments erected in water are generally designed to be protected from scour or erosion. However, both
A clay stratum of 18 metres thickness was found above a sand stratum when a boring was made. The clay was consolidated under the present overburden pressure. The hydrostatic pressu
Explain equation for Change Interval y = t + v / 2a + 64.4G Where: y = length of yellow interval (sec) t = driver perception/reaction time (1.0 sec generally used)
whatis difference between premix asphalt carpeting and asphalt concrete pavement
Why hoisting and conveying equipment is very important in civil engineering?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd