Common defects - bituminous roads, Civil Engineering

Assignment Help:

Common defects - bituminous roads:

Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt.

If an overlay is to be laid on a cracked surface, it is necessary to ensure that the cracks do not travel upwards in the newly laid material. For this purpose, a Stress Absorbing Membrane (SAM) layer or a Stress Absorbing Membrane Interlayer (SAMI) is used. SAM is an application of polymer modified bitumen and covering it with aggregate chips. SAMI is similar to SAM but is followed by an overlay. SAMI can consist of polymer modified bitumen or bitumen impregnated geotextile.

When cracks are extensive, it is preferable to treat the area with a fog seal or slurry seal. The fog seal consists of spraying a bitumen emulsion followed by blinding with graded grit of size 3 mm and lower sizes. A slurry seal is a mixture of fine aggregate, Portland cement filler, bitumen emulsion and additional water, mixed in a mobile mixer and laid to a uniform thickness of 1.5 mm - 5 mm and rolled.

When the surface of the bituminous carpet is loose or has got oxidized, it is necessary to renew the surface by a thin course, consisting of surface dressing, premix carpet, mix- seal surfacing and a semi-dense carpet, depending upon the traffic and importance of the road. The renewal is done once in 3 to 5 years. The renewal helps in restoring the riding quality.

If the surface becomes fatty, a sprinkling of coarse sand or fine chippings and rolling will help.

If the surface becomes very smooth and slippery and has lost its skid-resistance properties, an application of surface dressing can restore its anti-skid properties.


Related Discussions:- Common defects - bituminous roads

Determine the interdependent phases of investigation, Determine the interde...

Determine the interdependent phases of investigation The following are the interdependent phases of investigation: i)  Stratigraphical survey, ii) Physical survey, and

Bridge, Explain economical span if bridges

Explain economical span if bridges

Show the specification of bricks, Q. Show the Specification of Bricks? ...

Q. Show the Specification of Bricks? Specification of Ist class Bricks- 1. Table moulded and wire cut. 2. It should have edges and parallel faces. 3. If struck with ha

Sir I want to do assignments, sir I want to do assignments which were provi...

sir I want to do assignments which were provided by you sir could you please check with that

Discuss about the term - end zone, Discuss about the term - End Zone It...

Discuss about the term - End Zone It is the length of a post-tensioned concrete member, at the end, which is required to get a distribution of prestress over the whole of the c

Define rotation - actions in pot bearings, Define Rotation - Actions in POT...

Define Rotation - Actions in POT Bearings? POT bearings are associated with large rotations which are accommodated by the deformation of elastomeric pad. Large cyclic rotations

Vacancy for teaching?, I am a civil engineer and interested to teach.Is the...

I am a civil engineer and interested to teach.Is there any vacancy?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd