Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt.

If an overlay is to be laid on a cracked surface, it is necessary to ensure that the cracks do not travel upwards in the newly laid material. For this purpose, a Stress Absorbing Membrane (SAM) layer or a Stress Absorbing Membrane Interlayer (SAMI) is used. SAM is an application of polymer modified bitumen and covering it with aggregate chips. SAMI is similar to SAM but is followed by an overlay. SAMI can consist of polymer modified bitumen or bitumen impregnated geotextile.

When cracks are extensive, it is preferable to treat the area with a fog seal or slurry seal. The fog seal consists of spraying a bitumen emulsion followed by blinding with graded grit of size 3 mm and lower sizes. A slurry seal is a mixture of fine aggregate, Portland cement filler, bitumen emulsion and additional water, mixed in a mobile mixer and laid to a uniform thickness of 1.5 mm - 5 mm and rolled.

When the surface of the bituminous carpet is loose or has got oxidized, it is necessary to renew the surface by a thin course, consisting of surface dressing, premix carpet, mix- seal surfacing and a semi-dense carpet, depending upon the traffic and importance of the road. The renewal is done once in 3 to 5 years. The renewal helps in restoring the riding quality.

If the surface becomes fatty, a sprinkling of coarse sand or fine chippings and rolling will help.

If the surface becomes very smooth and slippery and has lost its skid-resistance properties, an application of surface dressing can restore its anti-skid properties.


Related Discussions:- Common defects - bituminous roads

Mechanics of solids, what is difference between design moment, nominal, req...

what is difference between design moment, nominal, required, resisting and ultimate moment ?

Effect of pile installation method, Effect of pile installation method to l...

Effect of pile installation method to load carrying capacity of piles The construction of piles by driving method causes an increase in density of surrounding soils. Therefore

Explain statically indeterminate structures, Explain Statically Indetermina...

Explain Statically Indeterminate Structures  Fall into two categories:   1.  Beam problems with additional supports/restraints 2.  Axial bar members subjected

Explain the classification of solid waste, Explain the Classification of So...

Explain the Classification of Solid Waste  Solid waste can be classified in several different ways.  Putrescible waste - Animal and Vegetable waste From Cooking and

Determine the limit state of serviceability, Determine the Limit State of S...

Determine the Limit State of Serviceability Cracking Cracking of concrete should not affect the appearance or durability of the structure. The criteria of limit state of cracki

Survey, how can I use reciprocal type of leveng method to level a ground, a...

how can I use reciprocal type of leveng method to level a ground, and a procedure

Explain the aashto classification system, Explain the AASHTO Classification...

Explain the AASHTO Classification System   1.  Identify the percent passing the No.10, No. 40, and No. 200 sieves. Identify the LL and PI of the fraction passing the No. 40 sie

Chapter 9, define of window pivoted

define of window pivoted

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd