Fixed and pinned connection between piles and pile caps, Civil Engineering

Assignment Help:

Q. Fixed vs pinned connection between piles and pile caps?

The type of connection amid piles and pile caps affects the load carrying capacity of pile groups. Fixity of pile head into pile cap, in place of pinning into pile cap, improves higher lateral stiffness of the pile groups. For example, for same deflections, a cap with fixed connected piles can withstand far more loads than that of pinned connected piles. To satisfy criteria of fixed connection, minimum embedded length of piles into pile caps must be at least two times the diameter of piles. 

Furthermore the fixed connection of piles at pile caps allows significant bending moment to be transmitted through the connections when compared with pinned connections.


Related Discussions:- Fixed and pinned connection between piles and pile caps

.., Ask questiPermanent Way:on #Minimum 100 words accepted#

Ask questiPermanent Way:on #Minimum 100 words accepted#

Define steel substructure - underwater inspection of bridge, Define Steel s...

Define Steel substructure - underwater inspection of bridge? Steel is used as a structural material and as external protective cladding on concrete foundation elements. Steel f

Explain ductile iron pipes and mild steel pipes, Ductile iron pipes vs. mil...

Ductile iron pipes vs. mild steel pipes as pressurized pipelines For water main pipe size less than 600mm, ductile iron is generally used since internal welding for steel pipe

Cost estimating, I would like to know if anyone can help me with my const e...

I would like to know if anyone can help me with my const estimating project

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Higway engineering, Ask question Design the pavement by group index method ...

Ask question Design the pavement by group index method for heavy traffic using following subgrade data Soil passing 75micron sieve =65%,liquid limit =40%plastic limit =20% #Min

Explain hot weather patrolling, Q. Explain Hot weather Patrolling ? Hot...

Q. Explain Hot weather Patrolling ? Hot weather Patrolling is done for LWR and CWR tracks when the rail temperature reaches td + 20 0 C and above and td + 14 0 C for Central

Mr Kamal Saxena, What is WBM road. How it is constructed?

What is WBM road. How it is constructed?

Tests on cement, Tests on Cement: The following tests are conducted o...

Tests on Cement: The following tests are conducted on cement in a project site: Setting Time Initial setting time Final setting time Compressive Streng

Determine the allowable bearing pressure of the sand, Two load tests were c...

Two load tests were conducted at a site-one with a 0.5 m square test plate and the other with a 1.0 m square test plate. For a settlement of 25 mm, the loads were found to be 60 kN

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd