Estimate the activity durations - construction management, Civil Engineering

Assignment Help:

Estimate the Activity Durations

The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this nonstop project.  The number of work days the roadway was shut down is most nearly:

Solution:  Assigning duration of actives is the estimated or actual time that it will be required to complete it. Accordingly:

  Total labor cost ÷ crew-hour cost = total crew-hours

  $5,716,440 ÷ $15,879 = 360 crew-hours

Nonstop project constitutes work at 24-hr 7-days/week

Total crew hours ÷ 24-hrs/day = project days

360 crew-hour ÷ 24-hrs/day = 15 days


Related Discussions:- Estimate the activity durations - construction management

Determine the value of the coefficient of permeability, Determine the value...

Determine the value of the coefficient of permeability A glass cylinder 5 cm internal diameter with a screen at the bottom is used as a falling head permeameter. The thickness

Planning and scheduling tutorial, Am looking for .planning and scheduling...

Am looking for .planning and scheduling tutorial , cost engineering tutorials

., WHAT IS PILE CORROSION

WHAT IS PILE CORROSION

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

RISE AND FALL METHOD, WHAT IS THE PURPOSE OF USING THE RISE AND FALL METHOD...

WHAT IS THE PURPOSE OF USING THE RISE AND FALL METHOD IN LEVELLING?

Define concrete substruct - underwater inspection of bridges, Define Concre...

Define Concrete substruct - underwater inspection of bridges? Plain, reinforced, and pre-stressed concrete are used for construction of underwater elements. Since the majority

Write briefly for trolley permits, Q. Write briefly for Trolley Permits? ...

Q. Write briefly for Trolley Permits? It is the permit given to the Moter Trolley / Push Trolley, Cycle / Moped Trolley. It is essential to have Trolley Permit before taking t

Steel design, have a beam with one lateral restraint at bottom and top flan...

have a beam with one lateral restraint at bottom and top flange and load on top flange, should I use 2 segments or one segment of the beam ignoring bottom restraint as it is not in

Hydraulics, What is the head loss in 350 ft of 12 inch diameter 20 years ol...

What is the head loss in 350 ft of 12 inch diameter 20 years old cast iron pipe carrying 1.2 MGD?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd