Estimate the activity durations - construction management, Civil Engineering

Assignment Help:

Estimate the Activity Durations

The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this nonstop project.  The number of work days the roadway was shut down is most nearly:

Solution:  Assigning duration of actives is the estimated or actual time that it will be required to complete it. Accordingly:

  Total labor cost ÷ crew-hour cost = total crew-hours

  $5,716,440 ÷ $15,879 = 360 crew-hours

Nonstop project constitutes work at 24-hr 7-days/week

Total crew hours ÷ 24-hrs/day = project days

360 crew-hour ÷ 24-hrs/day = 15 days


Related Discussions:- Estimate the activity durations - construction management

States of stress - principal stresses, States of stress - principal stresse...

States of stress - principal stresses: Now let us consider a few cases of solids of the similar material (mild steel) under various states of stress as display in Figure. The

Surveying, description of instruments used transfer upper floors *plumb-bob...

description of instruments used transfer upper floors *plumb-bob method *theodolite method *theodolite and target method *optical plumbing method

House, how to make a home

how to make a home

Steel truss 15 m span, types of truss of 15 m cantilever with 1000 kg on fr...

types of truss of 15 m cantilever with 1000 kg on free end. May be steel or any lightest material aluminium anodized truss. thanks

Traditional marine piling system of steel tubular pile, Question What i...

Question What is problem in traditional marine piling system of steel tubular pile with concrete infill and what are key possible remedial measures? Answer In design

Describe the terms inside clearance and outside clearance, a) Explain with ...

a) Explain with a neat sketch how will you carry out the wash boring method of soil exploration. What are its merits and demerits? b) Describe the terms 'inside clearance' and '

Aggregaters, What Aggregate''s class III

What Aggregate''s class III

Define types of inspection of bridge, Define Types of Inspection of Bridge?...

Define Types of Inspection of Bridge? Underwater inspections are generally categorised into five types: - Inventory - Routine - Damage - In-depth - Interim

Explain dissolved impurities in water, Q. Explain Dissolved Impurities in w...

Q. Explain Dissolved Impurities in water? The impurities which are caused by the action of water and water forming Acids with organic matter and carbon dio

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd