Estimate the activity durations - construction management, Civil Engineering

Assignment Help:

Estimate the Activity Durations

The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this nonstop project.  The number of work days the roadway was shut down is most nearly:

Solution:  Assigning duration of actives is the estimated or actual time that it will be required to complete it. Accordingly:

  Total labor cost ÷ crew-hour cost = total crew-hours

  $5,716,440 ÷ $15,879 = 360 crew-hours

Nonstop project constitutes work at 24-hr 7-days/week

Total crew hours ÷ 24-hrs/day = project days

360 crew-hour ÷ 24-hrs/day = 15 days


Related Discussions:- Estimate the activity durations - construction management

General about tests, 1. All testing shall be done at room temperature. 2...

1. All testing shall be done at room temperature. 2. No bearing shall be tested earlier than a week after vulcanization. 3. Bearing sections shall be cut from test bearings w

Explain the properties of poly tetra fluoro ethylene, Explain the Propertie...

Explain the Properties of Poly Tetra Fluoro Ethylene? PTFE is a linear chain polymer of great molecular strength, known for its chemical inertness and low coefficient of fricti

Difference between road gullies and catch pits, Q. Difference between road ...

Q. Difference between road gullies and catch pits? Both road gullies and catchpits are the two fundamental types of drainage inlets of drainage system. However they are designe

Smallest size of a325 bolts needed for two plates in tension, What is the s...

What is the smallest size of A325 bolts required for the two plates in tension noted below, assuming the thickness of each plate is 1.0-in. and the applied force at each end is P=2

Important parts of road pavements, Important parts of road pavements: ...

Important parts of road pavements: Prime Coat : Application of a low viscosity bituminous binder over a granular base to fill up the voids. Tack Coat : Application of b

Minimisation of differential settlement, Minimisation of Differential Settl...

Minimisation of Differential Settlement You are aware that differential settlement causes more distress to the structure, when compared with that of total settlement. The var

Distance between concrete columns in 5 story building, distance between con...

distance between concrete columns in 5 story building and if there is distance 15 feet than what should be the column size and how many bars and diameter of each bar ?

Purpose of using capping layers in pavement construction, Q. Purpose of usi...

Q. Purpose of using capping layers in pavement construction? When California Bearing Ratio of subgrade is checked to be below a specific percentage (for example 5%), a capping

Bridge, how to account for density?

how to account for density?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd