Estimate the activity durations - construction management, Civil Engineering

Assignment Help:

Estimate the Activity Durations

The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this nonstop project.  The number of work days the roadway was shut down is most nearly:

Solution:  Assigning duration of actives is the estimated or actual time that it will be required to complete it. Accordingly:

  Total labor cost ÷ crew-hour cost = total crew-hours

  $5,716,440 ÷ $15,879 = 360 crew-hours

Nonstop project constitutes work at 24-hr 7-days/week

Total crew hours ÷ 24-hrs/day = project days

360 crew-hour ÷ 24-hrs/day = 15 days


Related Discussions:- Estimate the activity durations - construction management

Designing lateral resistance of piles, Question While designing later...

Question While designing lateral resistance of piles , have to engineers only use earth pressure against pile caps simply? Answer In case of designing lateral loa

Wearing course or additional thickness be designed on piers, Question S...

Question Shall layer of wearing course or additional thickness be designed on surface of piers ? Answer In designing of piers , considerations have to be given to

Illustrate concept of filter design, Q. Illustrate Concept of filter design...

Q. Illustrate Concept of filter design? The material used for filter should satisfy the following normal criteria a. Filter material is more pervious than the base material

Purpose of the gap in the road on this bridge, What is the purpose of the g...

What is the purpose of the gap in the road on this bridge? Ans) Purpose of the gap in the road is to permit the road to expand and contract with temperature alters without causi

Determine the meaning of prestressed concrete, Determine the meaning of Pre...

Determine the meaning of Prestressed Concrete It is a type of concrete in which permanent internal stresses of  a suitable nature, magnitude and distribution are intentionally

Designing of watermain, Question In designing of watermain , regular p...

Question In designing of watermain , regular practice is to use supple iron for pipe size less than 600mm and to use steel for pipe size additional than 600mm. Give some speci

Theory on the horizontal reactions of portal frames, Determine the horizont...

Determine the horizontal abutment reaction of a rectangular portal frame under increasing central concentrated load

Laplace transform, Using Laplace transfom, the following differential equat...

Using Laplace transfom, the following differential equation d y dy dt reduces to the algebraic equation of the form Resolve y(s) into partial fractions

Difference between normal bolts and high friction grip bolts, Question ...

Question What is key difference between normal bolts and high friction grip bolts ? Answer High friction grip bolts are usually used in structural steelwork. They i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd