Estimate the activity durations - construction management, Civil Engineering

Assignment Help:

Estimate the Activity Durations

The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this nonstop project.  The number of work days the roadway was shut down is most nearly:

Solution:  Assigning duration of actives is the estimated or actual time that it will be required to complete it. Accordingly:

  Total labor cost ÷ crew-hour cost = total crew-hours

  $5,716,440 ÷ $15,879 = 360 crew-hours

Nonstop project constitutes work at 24-hr 7-days/week

Total crew hours ÷ 24-hrs/day = project days

360 crew-hour ÷ 24-hrs/day = 15 days


Related Discussions:- Estimate the activity durations - construction management

How do we calculate absolute pressure, Absolute is equivalent to gauge pres...

Absolute is equivalent to gauge pressure plus atmospheric.

Couple, Properties of a couple

Properties of a couple

Calculate the invert elevation of the sewer pipe, 1. The center line elevat...

1. The center line elevation of the proposed roadway at station is 345+25.50 is 327.36-ft.   The existing ground top of cut elevation (ft) is most nearly: 2. A design engineer c

What is shock transmission unit in bridges, Q. What is Shock transmission u...

Q. What is Shock transmission unit in bridges? Shock transmission unit is fundamentally a device connecting separate structural units. It's characterized by its ability to tran

Explain the contracted rectangular weir, Explain the Contracted Rectangular...

Explain the Contracted Rectangular Weir Weir plate has sides which extend above the maximum water surface, directing the flow through an opening (b = weir length). Typically th

Colour code, in colour working drawing what are the colour code?

in colour working drawing what are the colour code?

Grouting in segmental linings in tunnels, Q. Grouting in segmental linings ...

Q. Grouting in segmental linings in tunnels? Grouting is typically carried out under pressure in segmental linings at the time of tunnel construction due to the below reasons:

Centroid, How to calculate the centroid of parabola?

How to calculate the centroid of parabola?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd