Determine the cubic yard in the ground, Civil Engineering

Assignment Help:

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor excavates 100 cubic yards of loose sand and clay having a bank density of 3,400 pounds per cubic yard and a loose density of 2,700 pounds per cubic yard. A ton of this material will occupy nearly how many cubic yards in the ground? and, in the truck?

Solution:

Two-thousand pounds of this material would occupy 0.59 (2000 / 3400 = 0.59) cubic yard in the ground and 0.74 (2000 / 2700 = .74) cubic yard in the truck. This results in a swell factor of 26%. The contractor will have to haul 126 cubic yards of this material for every 100 cubic yards in the ground.


Related Discussions:- Determine the cubic yard in the ground

#tile.., Material for formwork and their specifications

Material for formwork and their specifications

Define the finish to finish activity, A finish-to-finish activity is best d...

A finish-to-finish activity is best described as: The "from" activity must finish before the "to" activity can finish The "from" activity must finish before the "to" acti

Vertical curves - geometric design of roads, Vertical Curves: When tw...

Vertical Curves: When two vertical gradients meet, it is necessary to provide a vertical curve. Two types of vertical curves are used: (a) Summit curve, where the point of

Shrinkage of concrete in prestressed members, Shrinkage of concrete in pres...

Shrinkage of concrete in prestressed members The shrinkage of concrete in prestressed members results in a shortening of ensioned wires and hence contributes to the loss of st

Failure analysis in designing of a structure, Modes of failure • For sa...

Modes of failure • For safe design, a knowledge of the possible modes of failure is also necessary, e.g. failure of the structure could occur due to - Tensile fracture due t

State average increase of pressure in the clay stratum, A building was to b...

A building was to be constructed on a clay stratum. Preliminary analysis showed a settlement of 60 mm in 6 years and an ultimate settlement of 250 mm. The average enhance of pressu

Define fatigue load test of shock transmission unit, Define Fatigue load te...

Define Fatigue load test of shock transmission unit? This test was carried out for 100,000 cycles for maximum capacity of STU, assuming the worst case that the 'Lock Up Load' i

Pattern of load distribution of piles in such agreement, Question For a...

Question For a rigid pile cap with vertical piles at middle and raking piles at the sides, what is pattern of load distribution of piles in such agreement? Answer Becau

Guidelines for selection of site, Guidelines for Selection of Site: Th...

Guidelines for Selection of Site: The following are some of the guidelines for selecting the site of a bridge : (a) A site which is on a straight reach of the river is pref

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd