Determine the cubic yard in the ground, Civil Engineering

Assignment Help:

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor excavates 100 cubic yards of loose sand and clay having a bank density of 3,400 pounds per cubic yard and a loose density of 2,700 pounds per cubic yard. A ton of this material will occupy nearly how many cubic yards in the ground? and, in the truck?

Solution:

Two-thousand pounds of this material would occupy 0.59 (2000 / 3400 = 0.59) cubic yard in the ground and 0.74 (2000 / 2700 = .74) cubic yard in the truck. This results in a swell factor of 26%. The contractor will have to haul 126 cubic yards of this material for every 100 cubic yards in the ground.


Related Discussions:- Determine the cubic yard in the ground

Present worth of an infinite series of annual amount, The construction of a...

The construction of a new bakery requires the property development firm to pay the municipality the cost to expand its sewage treatment plant. In addition to the expansion costs, t

Cement bag question., composition of cement in cover bag should be written ...

composition of cement in cover bag should be written or not/ If written which country uses ?please specify the name ?

Engineering mechanics, Characteristics of couple #Minimum 150 words accepte...

Characteristics of couple #Minimum 150 words accepted#

Determine the plastic limit of the soil, The liquid limit of a clay soil is...

The liquid limit of a clay soil is 56% and its plasticity index is 15%.  (a) Name the state of consistency is this material at a water content of 45% ? (b) Determine the plas

Large scale integration chips have between the components, Large scale int...

Large scale integration chips have between the  components? Answer : It is between 100 and 1000 components.

#surveying & levelling, expressions for calculating corrections for earth c...

expressions for calculating corrections for earth curvature

Theodolote, List out the permanent adjustments of dumpy level.

List out the permanent adjustments of dumpy level.

Determine the equivalent of free float, The free float is equal to: a. L...

The free float is equal to: a. Latest allowable event occurrence time + Early finish time b. Earliest event occurrence time + early finish time c. Latest allowable event o

Strength of materials, what are the different between stress and strain

what are the different between stress and strain

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd