An earthwork contractor encountered a location within the borrow area where the geological conditions changed. Instead of encountering 100 cubic yards of wet clay, the contractor excavates 100 cubic yards of loose sand and clay having a bank density of 3,400 pounds per cubic yard and a loose density of 2,700 pounds per cubic yard. A ton of this material will occupy nearly how many cubic yards in the ground? and, in the truck?
Solution:
Two-thousand pounds of this material would occupy 0.59 (2000 / 3400 = 0.59) cubic yard in the ground and 0.74 (2000 / 2700 = .74) cubic yard in the truck. This results in a swell factor of 26%. The contractor will have to haul 126 cubic yards of this material for every 100 cubic yards in the ground.
define dence bituminous course..
Measurement of cement and aggregates - by weight vs. by volume Measurement of constituents for concrete is usually carried out by weight since of the following reasons: (i)
The transmission main from the well field to the community is 2500 ft, the velocity of flow at peak pumping capacity is 3.5 fps, water temperature is 10oC, and pH is 7.5. If free c
Debonding
Question Given a 1meter high staircase resting on solid concrete, could it be adequate to design nominal reinforcement for staircase? Answer For design of staircase,
Define Construction damage - underwater inspection of bridge? Construction damage can result from improper procedures during the construction phase. Some examples are: - P
what are the uses of retaining wall?!
Q. Specification of Water bound macadam road? Formation - The embankment for road shall be made to the cross section shown on the drawing. The bank shall be raised in regular
1. Draw the projections of a line AB that is 50 mm long and is parallel to both the HP and the VP. The line is 40 mm above the HP and 25 mm in front of the VP. 2. A line AB, 50 mm
A flow rate of 200 gpm of oil with u=1.5 x 10-3 lb-sec/ft2 and p=1.7 slug/ft3 occurs in a 4-in pipe. Determine the Reynolds number. Classify the flow as laminar or turbulent. What
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd