Determine the cubic yard in the ground, Civil Engineering

Assignment Help:

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor excavates 100 cubic yards of loose sand and clay having a bank density of 3,400 pounds per cubic yard and a loose density of 2,700 pounds per cubic yard. A ton of this material will occupy nearly how many cubic yards in the ground? and, in the truck?

Solution:

Two-thousand pounds of this material would occupy 0.59 (2000 / 3400 = 0.59) cubic yard in the ground and 0.74 (2000 / 2700 = .74) cubic yard in the truck. This results in a swell factor of 26%. The contractor will have to haul 126 cubic yards of this material for every 100 cubic yards in the ground.


Related Discussions:- Determine the cubic yard in the ground

Define recommendations for ptfe, Define Recommendations for PTFE? (a) I...

Define Recommendations for PTFE? (a) It can be either of the two forms given below: (i) Dimpled large sheet It may be circular or rectangular divided maximum into four pa

State the problem and phases of site investigation, State the Problem and p...

State the Problem and phases of site investigation The site investigation is to be performed to obtain the solution for the following problems: i)  Foundation problems ii

Major differences between sureties and security, Question What are majo...

Question What are major differences between sureties and security ? Answer During construction contracts, if a contractor fails to carry out works, employer would e

Water treatment, The transmission main from the well field to the community...

The transmission main from the well field to the community is 2500 ft, the velocity of flow at peak pumping capacity is 3.5 fps, water temperature is 10oC, and pH is 7.5. If free c

DC POWER SUPPLY, DESIGN A LINEAR DC POWER SUPPLY WITH THE FOLLOWING SPECIFI...

DESIGN A LINEAR DC POWER SUPPLY WITH THE FOLLOWING SPECIFICATION,SHOW DETAILS STEPS AND CALCULATION...Vload :12v Iload :0.07A Vripple load(p-p) :0.01v TA :45 DEGREE CELCUS

Surveying, obstacle to ranging but not chaining inthat when line may not vi...

obstacle to ranging but not chaining inthat when line may not visible from intermediate point pls if required explain with diagram

Calculate the amount of import or export, Calculate the Amount of Import or...

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

Raised check rails for obtuse crossing, Raised Check Rails for obtuse cross...

Raised Check Rails for obtuse crossing In order to provide guided path way in throat portion of 1 in 8 1/2 BG obtuse diamond crossing, the check rails are raised by welding of

Cleaning and greasing of steel sliding bearings, Cleaning and greasing of s...

Cleaning and greasing of steel sliding bearings : Following equipments are required for greasing of steel sliding bearings: 1. Jacks (50 ton capacity) - 2 nos. 2. Hard wo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd