Determine the cubic yard in the ground, Civil Engineering

Assignment Help:

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor excavates 100 cubic yards of loose sand and clay having a bank density of 3,400 pounds per cubic yard and a loose density of 2,700 pounds per cubic yard. A ton of this material will occupy nearly how many cubic yards in the ground? and, in the truck?

Solution:

Two-thousand pounds of this material would occupy 0.59 (2000 / 3400 = 0.59) cubic yard in the ground and 0.74 (2000 / 2700 = .74) cubic yard in the truck. This results in a swell factor of 26%. The contractor will have to haul 126 cubic yards of this material for every 100 cubic yards in the ground.


Related Discussions:- Determine the cubic yard in the ground

TORSION, WHAT IS TRANSVERSE AND LONGITUDINAL REINFORCEMENT?

WHAT IS TRANSVERSE AND LONGITUDINAL REINFORCEMENT?

Concreting, #question why cracks develops on the surface of concrete on the...

#question why cracks develops on the surface of concrete on the next day of casting?

Premix carpet - road pavements, Premix Carpet: An open graded premix ...

Premix Carpet: An open graded premix carpet, commonly called premix carpet (PC), is an open graded premixed material laid to a thickness of 20 mm and rolled, followed by a se

Torsion, what is torsional moment of resistance

what is torsional moment of resistance

Determine the statements about unit area or borrow pit, Determine the State...

Determine the Statements about Unit Area or Borrow Pit? Ans: I.  Sometimes called Average Depth II. Works well for volumes for building sites and surface mines III. Needs

Permanent repairs to rail fracture, Q. Permanent Repairs to rail fracture? ...

Q. Permanent Repairs to rail fracture? (i) If the fracture is such that, wide gap A T welding ban be adopted, then the total length of fractured ends to-be cut shall be equal t

What is the required bracing location for the beam, A contractor has select...

A contractor has selected a W14x74 simply supported beam for a high rise construction project.  The span length for the provided beam is set at 30 feet.  The maximum factored appli

Assignment , A cantilever beam is loaded with a concentrated. Force of 5kN ...

A cantilever beam is loaded with a concentrated. Force of 5kN at the free end. The length of the cantilever beam is 1m having cross section of 50×50mm. determine the equation for b

Fore bearing and back bearing, write a c program to calculate the included ...

write a c program to calculate the included angles for given fore bearing and back bearing.

Determine about the long-term deflections, Determine about the long-term de...

Determine about the long-term deflections For long-term deflections, the total long-term deflection due to the prestressing force, dead load and any sustained imposed load may

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd