Determine the cubic yard in the ground, Civil Engineering

Assignment Help:

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor excavates 100 cubic yards of loose sand and clay having a bank density of 3,400 pounds per cubic yard and a loose density of 2,700 pounds per cubic yard. A ton of this material will occupy nearly how many cubic yards in the ground? and, in the truck?

Solution:

Two-thousand pounds of this material would occupy 0.59 (2000 / 3400 = 0.59) cubic yard in the ground and 0.74 (2000 / 2700 = .74) cubic yard in the truck. This results in a swell factor of 26%. The contractor will have to haul 126 cubic yards of this material for every 100 cubic yards in the ground.


Related Discussions:- Determine the cubic yard in the ground

Check rail on curve, Check Rail on Curve - Check Rails are basically p...

Check Rail on Curve - Check Rails are basically provided on sharp curves to reduce the lateral wear on the outer rail. They also prevent the outer wheel flange from mounting o

Structural analysis and design, Scenario You are working as a structural...

Scenario You are working as a structural technician and have been charged with a range of jobs   involving analysis and design of a number of structural members. Task 1 a)

Illustrate weld failures in track, Q. Illustrate Weld Failures in Track? ...

Q. Illustrate Weld Failures in Track? These are failures occurring to defects in welding the joint. These defects are either because of improper composition of thermit metal or

Define truss analysis-stability, Define Truss analysis-stability   ...

Define Truss analysis-stability   Identify whether a truss is determinate or indeterminate. Identify if the truss is stable or unstable   m = number of membe

Dam, types of dam

types of dam

Explain chezy manning equation, Explain Chezy Manning Equation v = 1.49...

Explain Chezy Manning Equation v = 1.49/n (R) 0.67 (S) 0.5     R = hydraulic radius (ft) = Area/ wetted perimeter, R = D/4 for circular channels full and one-half full

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd