An earthwork contractor encountered a location within the borrow area where the geological conditions changed. Instead of encountering 100 cubic yards of wet clay, the contractor excavates 100 cubic yards of loose sand and clay having a bank density of 3,400 pounds per cubic yard and a loose density of 2,700 pounds per cubic yard. A ton of this material will occupy nearly how many cubic yards in the ground? and, in the truck?
Solution:
Two-thousand pounds of this material would occupy 0.59 (2000 / 3400 = 0.59) cubic yard in the ground and 0.74 (2000 / 2700 = .74) cubic yard in the truck. This results in a swell factor of 26%. The contractor will have to haul 126 cubic yards of this material for every 100 cubic yards in the ground.
Passenger Terminal Building: Importance In a civil airport, the passenger terminal building is the centre of all activities. It services both inbound and outward boun
how can i get results of this
types,
briefly explain about c tokens ?
Q. Utilisation of Buoyancy Effect? Submerged part of the substructure will be subjected to buoyancy effect. The uplift pressure from the ground water can be utilised by constru
Define Abrasion - underwater inspection of bridge? Deterioration of substructures by abrasion is caused by wave action, the velocity of the currents and the action of suspended
design procedure
Define Remedial measures for Problems in Turbid Water - Absorption? The process of absorption of light can be overcome by using higher powered lighting, or by using more light
Question How does an engineer determine digit of cells for concrete box girder bridges ? Answer If depth of a box girder bridge exceeds 1/6 or 1/5 of bridge width, then it is o
Question Why are voids filled with lightweight infilling material in raft base of pumping stations ? Answer To decrease dead load and therefore to decrease settleme
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd