Determine equipment purchase yields a minimum 15% return, Civil Engineering

Assignment Help:

A contractor established a policy to purchase equipment over leasing only if the return is a minimum of 15%. Given the following conditions, the contractor's decision based on the policy reveals that:

1401_Calculate equipment purchase yields.png

a. The equipment purchase yields a minimum 15% return

b. The equipment purchase yields less than a minimum 15% return

c. The purchase yields a neutral or $0 return

d. Cannot be determined without additional information

Solution:

The contractor's goal is to accept a purchase with Internal Rate of Return (IRR) larger than the discount rate in which he can borrow money. The first step is to identify the rate of return on the investment. An example would be to use a geometrically rising series of values.  

 A typical means of computing IRR is to identify the discount rate that sets the Net Present Value (NPV) to $ 0 (zero dollars).  

 Applying the concept yields an Internal Rate of Return (IRR) that must satisfy the Contractor's goal.

 Find the NPV using a 15% IRR by establishing a zero sum equation  

  $0  = - $20,000 + $5,600 (P/A, IRR%, 5) +  $4,000 (P/F, IRR%, 5)

 $0 = +$760   

Therefore, $0 IRR = $760 which is > 15% IRR; the purchase is justified.


Related Discussions:- Determine equipment purchase yields a minimum 15% return

Edge piles take up more loads than central piles, Edge piles take up more l...

Edge piles take up more loads than central piles in rigid cap Because of the effect of interaction of individual piles, central piles tend to settle more than the edge piles w

Defaults for precast concrete pipes made by spinning, Q. Defaults for preca...

Q. Defaults for precast concrete pipes made by spinning? Small diameter precast concrete pipes are generally manufactured by spinning method. The spinning method fundamentally

Water piped scheme, how to use mood diagram to get f and other Re

how to use mood diagram to get f and other Re

What are probable solutions to rectify the situation, Question If in ca...

Question If in case mud waves occur during reclamation, what are probable solutions to rectify the situation? Answer (i) Option 1 - Complete Removal of All Disturb

State the procedure of prestressing, State the procedure of prestressing ...

State the procedure of prestressing When these wires cool down, concrete is poured in the moulds in which these tendons are provided in a stretched condition. Using this proces

STRUCTURAL DYNAMICS, Consider a diver weighing 200 Ib at the end of a divin...

Consider a diver weighing 200 Ib at the end of a diving board that cantilevers out 3 ft. The diver oscillates at a frequency of 2 Hz. What is the flexural rigidity E I of the divin

Surveying, Distance ABC was measured with a 30m. Chain tested and found to ...

Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was

Erosion ocntrol, java program to design a SD-3 sediment pond per Georgia er...

java program to design a SD-3 sediment pond per Georgia erosion control manual

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd