Define the approach velocity, Civil Engineering

Assignment Help:

Define the Approach Velocity

Typical problems have negligible approach velocity.  v1 = Q/A, where A = the cross-sectional area of flow in the channel. The value is not the velocity of the flow falling over the top of the weir plate (nappe).


Related Discussions:- Define the approach velocity

How can you design side slope of bank, Q. How can you design Side Slope of ...

Q. How can you design Side Slope of bank? Angle of bank should be flatter than angle of repose of pitching material. Angle of repose of sand is 2:1 while that of stone is about

Determine the bar sizes and spacing, Referring to problem 1, in order to me...

Referring to problem 1, in order to meet a 1-hour fire code rating the slab thickness must be at least 4.00. Based on the information given in problem 1 and with a slab thickness o

Tack rivet, tack rivet figures with connections

tack rivet figures with connections

Concrete compaction in piling works, Question What is the reason that v...

Question What is the reason that vibrators not used in concrete compaction in piling works ? Answer Concrete for piles must be a high-slump self-compacting mix that i

Explain remote sensing technique, Q. Explain Remote sensing technique? ...

Q. Explain Remote sensing technique? Remote sensing is a science or an art of obtaining the information about an object, area or a phenomenon through analysis of data acquired

Principle for conducting surface regularity test, Question What is dist...

Question What is distinction in principle for conducting surface regularity test and sand test? Answer Purpose of surface regularity test is to assess riding quality

Estimation specification and costing, Estimate the single room of size 3m x...

Estimate the single room of size 3m x 4m x height 3m using individual wall method?

Elimination of formwork with reasons, Question For a l ong slender structur...

Question For a l ong slender structure similar to beams, propping is compulsory after elimination of formwork with reasons? Answer After concreting, time at which arresting of

Two pegs test, the distance between two pegs M and N is 7,063 as measured o...

the distance between two pegs M and N is 7,063 as measured on a slope. the height measured on the pegs are that M=1.814M and N=0.5687M

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd