Schedule control is concerned with all of the following except:

a. Influencing the factors which create schedule changes

b. Determining that the schedule has changed

c. Resource requirement updates

d. Managing changes when and as they occur.

Solution: C - Resource planning to meet new or additional requirements is a cost management process.


Related Discussions:- Define factor that is not concerned with schedule control

Timber, uses of timber in civil engineering field and its physical state an...

uses of timber in civil engineering field and its physical state and chemical formula or symbol?

Define lead lag relationships - construction management, Define Lead Lag Re...

Define Lead Lag Relationships 1. A lead is when the successor task begins before the predecessor task is complete 2. A lag is when a successor task does not

Centroid, How to calculate the centroid of parabola?

How to calculate the centroid of parabola?

Vitrification, what is this process?whats its procedure?need some case stud...

what is this process?whats its procedure?need some case studies

Alluvial streams, Alluvial Streams: In alluvial streams, the regime w...

Alluvial Streams: In alluvial streams, the regime width of a river is calculated from the Lacey's formula : W = 4.8 Q ½ where  W = Regime width in m, and Q = Discha

Corrosion, Distinguish between dry and wet corrosion

Distinguish between dry and wet corrosion

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd