Schedule control is concerned with all of the following except:
a. Influencing the factors which create schedule changes
b. Determining that the schedule has changed
c. Resource requirement updates
d. Managing changes when and as they occur.
Solution: C - Resource planning to meet new or additional requirements is a cost management process.
Explain briefly physical classifications of stone
Question While select screw pumps in polder scheme projects , what are factors that affect design facility of screw pumps? Answer Commonly used angles of inclination
Q. Show the Direction of gunning in shotcreting? At the time of the construction of shotcrete, it is intended at gunning the full thickness in one single operation and this hel
(a) Relate dissimilar formations of soils to the geological aspects. (b) Explain different types of texture and structure of soils. (c) Bring out the typical characteristics
what is the advanantage& dis advantage
what is the allwoable combined aggregates Fineness Modulus
name of types of piles?
Question In case if there is a delay of bituminous laying on top of sub-base, have to tack coat be applied on the top surface of sub-base? Answer When there is a d
description of instruments used transfer upper floors *plumb-bob method *theodolite method *theodolite and target method *optical plumbing method
what is the classification of lintel
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd