Define factor that is not concerned with schedule control, Civil Engineering

Assignment Help:

Schedule control is concerned with all of the following except:

a. Influencing the factors which create schedule changes

b. Determining that the schedule has changed

c. Resource requirement updates

d. Managing changes when and as they occur.

Solution: C - Resource planning to meet new or additional requirements is a cost management process.


Related Discussions:- Define factor that is not concerned with schedule control

Requirements of good building stones , Requirements of Good Building Stones...

Requirements of Good Building Stones          Here described requirements of good building stones: Strength: The stone should be capable to resist the load coming on

Well foundation in bridges, what is the purpose of 6mm ms sheet for stainin...

what is the purpose of 6mm ms sheet for staining in various conditions at inner &outer of well

Construction of concrete carriageway, Question If construction of conc...

Question If construction of concrete carriageway is carried out in summer, be capable of expansion joints be omitted? Answer If construction of concrete carriageway

Seismic loading principles, Seismic loading principles Ground motion ...

Seismic loading principles Ground motion Effects of ground motion are specified as one of the acceleration delineation spectrum or time history of acceleration variation m

Invoice Method, How to raise an invoice with WCT for Civil construction job...

How to raise an invoice with WCT for Civil construction job?

Harbour, typical layout showing dock,quay.jetties,turning circle,pier

typical layout showing dock,quay.jetties,turning circle,pier

Estimating, a 45 cm deep roof beam is provided on 30 cm wall of a room size...

a 45 cm deep roof beam is provided on 30 cm wall of a room size 3.0m*5.0m . calculate the quantity of steel required in beam on percentage basis.

Traffic surveys, Traffic Surveys: The following traffic surveys are n...

Traffic Surveys: The following traffic surveys are needed for preparing a good road project: Classified Volume Counts This survey is normally carried out for 7 days,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd