Define the pre-tensioned concrete construction, Civil Engineering

Assignment Help:

Define the pre-tensioned concrete construction

We understand that in the pre-tensioned concrete construction, stretched tendons are provided in the concrete moulds at the time of  casting of concrete. In the post-tensioned concrete construction, this is not a requirement as the ducts are fitted inside the moulds at the time of casting of  concrete. The transfer of prestress takes place early in  the case of pre-tensioned concrete members (it
takes place at the time of cutting of  tendons after the concrete has sufficiently hardened) while the transfer of prestress, in the case of post-tensioned concrete members, takes place when tendons are placed  inside ducts and anchored in a stretched condition.


Related Discussions:- Define the pre-tensioned concrete construction

Explain about bentonite slurry and polymeric slurry, Q. Explain about Bento...

Q. Explain about Bentonite slurry and polymeric slurry? For the construction of diaphragm walls, bentonite slurry is generally used to form a filter cake on walls of trenches t

What do you mean by shallow gradient of pipes, Q. Colebrook White formula s...

Q. Colebrook White formula suitable for shallow gradient of pipes? Manning's Equation is commonly used for rough turbulent flow while Colebrook-White Equation is adopted for t

Slope protection, what is the type of slope protection that use rocks and p...

what is the type of slope protection that use rocks and put cements between those rocks??the concept is same as brick layer

Transitional jacks designed in pipe jacking projects, Question Why are ...

Question Why are transitional jacks designed in pipe jacking projects? Answer While development of pipe jacking stops, building up of confrontation is extremely

Water treatment, The transmission main from the well field to the community...

The transmission main from the well field to the community is 2500 ft, the velocity of flow at peak pumping capacity is 3.5 fps, water temperature is 10oC, and pH is 7.5. If free c

Prismatic compass, Figure, working,principle of prismatic compass

Figure, working,principle of prismatic compass

Design of the aeration basin based on solids retention time, Design of the ...

Design of the Aeration Basin Based on Solids Retention Time - sewer construction: You are provided the following information about a municipal wastewater treatment plant. That

Atomic weight of an atom is equal to, Atomic weight of an atom is equal to?...

Atomic weight of an atom is equal to? Answer: sum of the number of protons and neutrons.

Designing of pipe jacking, Question While designing of pipe jacking , ...

Question While designing of pipe jacking , what particular areas on pipe joints have to engineers make sure of? Answer While in pipe jacking, jacked pipes may well ha

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd