Define the pre-tensioned concrete construction, Civil Engineering

Assignment Help:

Define the pre-tensioned concrete construction

We understand that in the pre-tensioned concrete construction, stretched tendons are provided in the concrete moulds at the time of  casting of concrete. In the post-tensioned concrete construction, this is not a requirement as the ducts are fitted inside the moulds at the time of casting of  concrete. The transfer of prestress takes place early in  the case of pre-tensioned concrete members (it
takes place at the time of cutting of  tendons after the concrete has sufficiently hardened) while the transfer of prestress, in the case of post-tensioned concrete members, takes place when tendons are placed  inside ducts and anchored in a stretched condition.


Related Discussions:- Define the pre-tensioned concrete construction

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

Mortar mechanism vs stone contact mechanism, "Mortar mechanism" vs. "stone ...

"Mortar mechanism" vs. "stone contact mechanism" in bituminous materials 'Stone contact mechanism' applies to well graded aggregates coated with bitumen (for example dense bit

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Mechanism of taking up loads for concrete paving blocks, Mechanism of takin...

Mechanism of taking up loads for concrete paving blocks  Paving for concrete blocks comprises closely packed paving blocks in pre-determined patterns and tiny joint spaces bet

Paint, Description of paint

Description of paint

Obtain maximum positive moment in a span of continuous beam, Reason of load...

Reason of loading on alternative spans to obtain maximum positive moment in a span of a continuous beam To attain a maximum sagging moment in a span of a continuous beam, gene

Determine the reliable moment capacity, Figure 2 details a typical T-beam u...

Figure 2 details a typical T-beam unit in a beam and slab floor with a span of L = 10 m. Determine the reliable moment capacity M ′ for the T-section shown. Take f c ′ = 32

Key reasons for conducting pull-out tests, Question What are key reason...

Question What are key reasons for conducting pull-out tests for soil nails ? Answer There are largely four bases for this examination- (i) To verify and verify bo

Maintenance of bituminous roads, Maintenance of Bituminous Roads: The...

Maintenance of Bituminous Roads: The common defects noticed in a bituminous road are : potholes cracks rutting corrugations shoving stripping and l

Vitrification, what is this process?whats its procedure?need some case stud...

what is this process?whats its procedure?need some case studies

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd