Derive the relation among void ratio (e), specific gravity of particles (G) and moisture content at full saturation (w).

A certain sample of saturated soil in a container weighs 0.65 N. On drying in an oven in the container it weighs 0.60 N.

The weight of container is 0.35 N. The grain specific gravity is 2.65. Verify the void ratio, water content, and bulk unit weight.

 


Related Discussions:- Verify the void ratio and water content

Construction of parabolic shapes, construct parabolic shapes using the enve...

construct parabolic shapes using the envelop method and the offset method with dimensions 80 by 120

Explain the dynamic or vibration tests, Explain the Dynamic or Vibration Te...

Explain the Dynamic or Vibration Tests Tests of this type, also known as sonic integrity test, involve sub- jecting the element to a single impulsive blow or cyclic load, and

Survey question, Sir morng..i know about WCB AND RB.With diagram..pls help ...

Sir morng..i know about WCB AND RB.With diagram..pls help me sir

What is preset mean while installation of bridge bearings, What is preset m...

What is preset mean while installation of bridge bearings ?

Foundation depth and arrangement, Foundation Depth and Arrangement: Th...

Foundation Depth and Arrangement: There are two types of foundations, viz, (a) Shallow foundations, also known as open foundations, and (b) Deep foundations. Slab cul

Explain the departure of a line - transportation, Explain the Departure of ...

Explain the Departure of a line - Transportation Departure of a line is the distance that the line extends in an east or west direction. A line that runs towards east has a pos

Physical classification of stones, Physical Classification Based on the...

Physical Classification Based on the structure, the rocks can be classified as following: Stratified rocks Un -stratified rocks A.   Stratified Rocks: These ro

Define project scheduling - types of methods, Define Project Scheduling - T...

Define Project Scheduling - Types of Methods Project Scheduling - Distinction between the Major Types of Schedule Diagrams Precedence Diagrams (PDM)   a) Activ

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd