Consolidated undrained or consolidated drained analysis, Civil Engineering

Assignment Help:

Question

In determining effectual stress parameters of a soil sample, which test is good, consolidated undrained analysis or consolidated drained analysis?


Answer


Effective stress parameters of a soil sample are able to be obtained from both consolidated undrained analysis and consolidated drained analysis. Though, consolidated undrained analysis is usually selected because of following reasons-

(i) Time occupied for consolidated undrained test is shorter than that of consolidated drained test. It is as consolidated drained analysis requires full dissipation of excess pore water pressure of soil throughout testing and it takes long time at what time soils of low permeability are experienced.

(ii) Useful information be capable of be obtained from stress path of consolidated undrained test.

(iii)Failure happens in worse stress level while compared with consolidated drained test.

 


Related Discussions:- Consolidated undrained or consolidated drained analysis

Define the hazard ranking system (hrs), Define the Hazard Ranking system (H...

Define the Hazard Ranking system (HRS) - A procedure for ranking uncontrolled hazardous waste sites in terms of the potential threat based upon the containment of the route of

Geotech, for zero air void line sr is

for zero air void line sr is

Spacing of manholes in straight sections, Question Spacing of manhole...

Question Spacing of manholes in straight sections for diverse pipe sizes is stated in Storm water Drainage Manual. How are figures arrived on? Answer For pipe size

Sucker deck principle for changeable depth bridge decks, Question What is t...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate

Storm water drainage - Road drainage and maintenance, Storm Water Drainage:...

Storm Water Drainage: In city streets, the disposal of rain water has to be done through a system of underground storm water drains. The water is collected at the roadside ke

Show the overlays on concrete bridge deck, Q. Show the Overlays on concrete...

Q. Show the Overlays on concrete bridge deck? After years of servicing, some overlays can be applied on the top surface of bridges. Overlays on concrete bridge decks achieve th

Determine the final volume of the compacted soil, 30,000-yd 3 of banked so...

30,000-yd 3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite.  The soil has 28% swell and shrinkage of 18%.  The final volume of the compacted so

Autocad, pls explain about this field

pls explain about this field

Inspection of girder bridge, Q. As an AEN in charge, what inspection will...

Q. As an AEN in charge, what inspection will you under taken at the time of inspection of Girder Bridge 3 x 60 feet. Please explain the important items to be o

Fillet welding, Strength of member when fillet welded

Strength of member when fillet welded

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd