Question
In determining effectual stress parameters of a soil sample, which test is good, consolidated undrained analysis or consolidated drained analysis?
Answer Effective stress parameters of a soil sample are able to be obtained from both consolidated undrained analysis and consolidated drained analysis. Though, consolidated undrained analysis is usually selected because of following reasons-
(i) Time occupied for consolidated undrained test is shorter than that of consolidated drained test. It is as consolidated drained analysis requires full dissipation of excess pore water pressure of soil throughout testing and it takes long time at what time soils of low permeability are experienced. (ii) Useful information be capable of be obtained from stress path of consolidated undrained test. (iii)Failure happens in worse stress level while compared with consolidated drained test.
Q. Underwater problems in bridge construction? The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as binding
advantage of concrete floor
friction circle method of stability of slope
Total loss of prestress The total amount of losses of prestresses may be accounted for in a prestressed concrete member by adding different losses which may take place for tha
Tube levels explains
Q. How can you design Side Slope of bank? Angle of bank should be flatter than angle of repose of pitching material. Angle of repose of sand is 2:1 while that of stone is about
Question Throughout concreting of diaphragm walls , three tremie pipes are used in single time. But, only one concrete truck is obtainable. How have to concreting works been a
A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of
Given for the section shown in Figure, M * = 250 kNm, f sy = 500 MPa and f c ′ = 25 MPa. Compute A st and (if necessary) A sc . You may assume that eac
State the use of reinforced concrete The use of reinforced concrete may not solve all the problems. For example, a very long reinforced concrete member, which may be subjected
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd