Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Rolling - binder, Rolling - Binder: The layer thickness is 40-50 mm. R...

Rolling - Binder: The layer thickness is 40-50 mm. Rolling is done in three stages : Initial Rolling By 80-100 kN smooth wheeled roller. Intermediate Rolling B

Define the meaning of circular prestressing, Define the meaning of circular...

Define the meaning of circular prestressing In circular prestressing, tendon wires are wrapped under tension over the concrete pipes which are pre-cast. The tension in the ten

Define masonry substructure- underwater inspection of bridge, Define Masonr...

Define Masonry substructure- underwater inspection of bridge? In early days, masonry, particularly stone masonry was extensively used for bridge piers and abutments. Typically,

What is preset in bridge bearing, Q. What is Preset in bridge bearing? ...

Q. What is Preset in bridge bearing? 'Preset' is a method to decrease the size of upper plates of sliding bearings in order to save cost. Normal length of an upper bearing plat

Designing level of landings in piers, Question What is designing leve...

Question What is designing level of landings in piers? Answer Landings are designed as resting place for passengers throughout berthing and deserting of vessels. I

Water technology, Explain with lime soda process?cold lime soda process&hot...

Explain with lime soda process?cold lime soda process&hot lime soda process and it''s equations?

Resting on several raking piles, Question Should dolphins be designed i...

Question Should dolphins be designed in a rigid manner such as resting on several raking piles? Answer While designing dolphins, they are normally supported on a syste

Key functions of changed components of paint, Question What are key fun...

Question What are key functions of changed components of paint? Answer For regular paint application, there are largely three key components of paint, namely primer, u

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd