Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

Solid mensuration, a street light is 15 ft directly above the curb. a 6 ft ...

a street light is 15 ft directly above the curb. a 6 ft man starts 10 ft down the street from the light and walks directly across the street which is 10 ft wide. when he reaches th

Engineering Mechanics, the jet transport B is flying north with a velocity ...

the jet transport B is flying north with a velocity vB = 600 km/h when a smaller aircraft A passes underneath the transport headed in the 60 degree direction shown. To passengers i

Construction, #questidisadvantage of steelon..

#questidisadvantage of steelon..

#title.long span truss design, what are the step by step process of designi...

what are the step by step process of designing steel long span trusses?

Surveying, define surveying and where it is involved

define surveying and where it is involved

Road binders - bitumen, Road Binders: Bitumen: Bitumen is a viscous, s...

Road Binders: Bitumen: Bitumen is a viscous, semi-solid material, dark in color, having adhesive properties, and derived from the distillation of petroleum crude in a refinery

Advantages associated with this kind of material, Question In pumping s...

Question In pumping stations one of choices for the material of water tanks is fibre-reinforced plastic. What are main advantages associated with this kind of material? An

Steel tubular marine piles, Question Give genuine reason that why are ...

Question Give genuine reason that why are steel tubular marine piles often driven open-ended? Answer In marine structure where piles are constantly topic to major la

#title beam design, how to calculate loads acting on a simple supported bea...

how to calculate loads acting on a simple supported beam of 220width by 425 depth #Minimum 100 words accepted#

What is switch and expansion joint, Q. What is Switch and Expansion Joint? ...

Q. What is Switch and Expansion Joint? Switch Expansion, Joint (SEJ) is an expansion joint installed at each end of LWR/CWR to permit expansion/contraction of the adjoining bre

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd