Concrete cracking, Civil Engineering

Assignment Help:

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.


Related Discussions:- Concrete cracking

. determine the permeability of the aquifer, An unconfined aquifer is calle...

An unconfined aquifer is called to be 32 m thick below the water table. A constant discharge of 2 cubic metres per minute is pumped out of the aquifer by a tubewell till the water

Surveying, Describe the two fundamental purposes of surveying

Describe the two fundamental purposes of surveying

Timber, uses of timber in civil engineering field and its physical state an...

uses of timber in civil engineering field and its physical state and chemical formula or symbol?

Engineering economics, Ask quA contractor has both a 3-cy and a 5-cy shovel...

Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 worki

Explain sedimentation, Explain Sedimentation 1. Sedimentation bas...

Explain Sedimentation 1. Sedimentation basin or clarifier is used to remove particles that will settle in a reasonable time period 2. Basins are usually rectangular or

Explain strain compatibility in mini-piles, Q. Explain Strain compatibility...

Q. Explain Strain compatibility in mini-piles? In designing the axial capacity of mini-piles, grout can be taken into account in the contribution of axial load capacity. Though

Bituminous Macadam, What is the difference between Dense bituminous Macadam...

What is the difference between Dense bituminous Macadam and bituminous macadam

Manhole covers finished of cast iron same as ductile iron, Question Why are...

Question Why are manhole covers finished of cast iron as same are through of ductile iron ? Answer Usually, manholes covers are made of cast iron. Though, in viewpoint of pipe

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd