Budgeted cost of work performed (bcwp), Project Management

Assignment Help:

Budgeted cost of work performed (BCWP), or "earned value" (EV), in project management is the budgeted cost of work that has truly been done in carrying out a scheduled task in a particular time period. NASA's definition of the BCWP is the sum of the budgets for completed work packages and completed parts of open work packages, plus the applicable part of the budgets for level of effort and apportioned effort. BCWP is an Earned value management word and it is dissimilar from:

  • Budgeted cost of work scheduled (BCWS) : the approved budget that has been assigned to complete a scheduled task within a specific time period.
  • Actual Cost of Work Performed (ACWP) : the actual cost that has been used up, rather than the budgeted cost.

As example of the difference assume that a schedule contains:

  • a work "Test hardware" that is budgeted to cost $1000 to be done, and
  • is probable to begin at the start of January 1 and
  • Finish at the end of January 10.

At the end of January 5, the work is scheduled to be 50% complete (5 days of the scheduled 10 days). So, at the end of January 5,

  • the BCWS is $1000 (the budgeted cost) times 50% (the scheduled completion percentage), or $500.

Assume that by the end of January 5, the work is just only 30% complete. In this situation,

  • the BCWP would be $1000 (budgeted cost) times 30% (the actual completion percentage), or $300.

Also, assume that to reach the 30% complete level at the finish of January 5, $250 was actually spent.

  • Then, the ACWP would be $250.

Related Discussions:- Budgeted cost of work performed (bcwp)

What are the main factors in organisation structure included, What are the ...

What are the main factors in organisation structure included? The structure gives an appropriate frame work for authority and responsibility relationships among different posit

Cost benefit analysis, How to determine which project have larger net benef...

How to determine which project have larger net benefit between two projects

Stakeholder management, 3. What are some ways to manage a stakeholder rela...

3. What are some ways to manage a stakeholder relationship closely? Give examples of how you might manage relationships differently based on the unique personalities of different

What is working of definition phase in project management, What is the work...

What is the working of definition phase in the project management? Definition phase: After the project plan that developed into the initiation phase, has been approved, a

What are the techniques used for a post completion review, What are the tec...

What are the techniques used for a post completion review? Techniques used for a PC (post completion) review: a. End user satisfaction surveys regarding to the quality of th

Construct a network diagram showing the critical path, ST is the operations...

ST is the operations director of F Bakery. He is in the process of putting together a project plan for the introduction of a latest production plant that will enable the bakery to

Greater possibility of space utilization, Greater Possibility of Space Util...

Greater Possibility of Space Utilization There will be a greater productive utilization of the floor area under this type of layout. Due to lesser need for temporary storage o

Classical and neo-classical theory of of organisation, What are the differe...

What are the differences between classical theory and neo-classical theory of organisation? Difference between classical theory and neo-classical theory of organisation: The cl

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd