Budgeted cost of work performed (bcwp), Project Management

Assignment Help:

Budgeted cost of work performed (BCWP), or "earned value" (EV), in project management is the budgeted cost of work that has truly been done in carrying out a scheduled task in a particular time period. NASA's definition of the BCWP is the sum of the budgets for completed work packages and completed parts of open work packages, plus the applicable part of the budgets for level of effort and apportioned effort. BCWP is an Earned value management word and it is dissimilar from:

  • Budgeted cost of work scheduled (BCWS) : the approved budget that has been assigned to complete a scheduled task within a specific time period.
  • Actual Cost of Work Performed (ACWP) : the actual cost that has been used up, rather than the budgeted cost.

As example of the difference assume that a schedule contains:

  • a work "Test hardware" that is budgeted to cost $1000 to be done, and
  • is probable to begin at the start of January 1 and
  • Finish at the end of January 10.

At the end of January 5, the work is scheduled to be 50% complete (5 days of the scheduled 10 days). So, at the end of January 5,

  • the BCWS is $1000 (the budgeted cost) times 50% (the scheduled completion percentage), or $500.

Assume that by the end of January 5, the work is just only 30% complete. In this situation,

  • the BCWP would be $1000 (budgeted cost) times 30% (the actual completion percentage), or $300.

Also, assume that to reach the 30% complete level at the finish of January 5, $250 was actually spent.

  • Then, the ACWP would be $250.

Related Discussions:- Budgeted cost of work performed (bcwp)

Explain the event and the ideal target group, Question 1: a) As an eve...

Question 1: a) As an event organiser you need to target the right audience/visitor group. Taking a festival [local, regional or national] - explain the event and the ideal t

Project manager, Understanding the different models of project manage. How ...

Understanding the different models of project manage. How is projectized different from managing and controlling task.

How are carrying costs varied with quantity order, How are carrying costs v...

How are carrying costs varied with quantity order? Carrying Costs, that vary along with quantity ordered, contained as a. There Interest on capital investment b. There Co

Review of design, Before the preliminary design has progressed further i...

Before the preliminary design has progressed further it should be subjected to a critical review by all those who are connected with the product such as quality engineers

Kaizen, what is a benefit of a kaizen event?

what is a benefit of a kaizen event?

What are the skills required by a project manager, Question: a) What ...

Question: a) What are the skills required by a project manager? b) What are the basic principle stages in a project life cycle? c) Suppose you are involved in the pl

What is the important role of planning in the management, What is the impor...

What is the important role of planning in the management? Planning: Planning can be described as deciding in advance regarding the goals to be pursued through the enterpris

Why is necessary to plan an is project in detail before work, Give three re...

Give three reasons why this is necessary to plan an IS project in detail before starting work on this. Only the simplest projects that probably imply one developer working for

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd