Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Determine the work done, Determine the work done per minute by a punch tool...

Determine the work done per minute by a punch tool making 20 working strokes min when a 30 mm diameter hole is punched in 5 mm thick plate with ultimate shear strength of 450 MPa i

Can you explain investment casting, Q. Can you explain Investment casting? ...

Q. Can you explain Investment casting? -Investment casting produces very high surface quality and dimensional accuracy. -Investment casting is commonly used for precision eq

What is the full form of step, What is STEP The STEP (Standard for Exte...

What is STEP The STEP (Standard for External Representation of Product Data) project is supported by the ISO workgroup TC 184/SC4. it is also sometimes called Standard for Exch

Solve the gauss elimination method, a) By Gauss elimination method, solve ...

a) By Gauss elimination method, solve x+2y+z =3 ; 2x+3y+3z =10 ; 3x-y+2z =13 b) Write a ‘C' program to find the solution of the above system of equations by Gauss Jordan meth

Advantages of using cam, 1. Greater Design Freedom : Any changes that are ...

1. Greater Design Freedom : Any changes that are required in design can be incorporated at any design stage without worrying about any delays since there would hardly be any i

Closed, Closed, open and isolated system-Thermodynamics system: Sol: ...

Closed, open and isolated system-Thermodynamics system: Sol: In thermodynamics the system can be defined as the quantity of matter or region in space upon which attention is

When was pddi developed, When was PDDI developed The PDDI interface was...

When was PDDI developed The PDDI interface was developed in connection with the ICAM project which was funded by the Air Force in order to improve the manufacturing methods in

Fourth gear position - shifting of gear, Fourth Gear Position: When g...

Fourth Gear Position: When gear M4 on the main shaft is in mesh with gear C4 on the countershaft then this is known as fourth gear position. The free gear M4 rotates with the

Copper and its production, Copper And Its Production Copper is marked ...

Copper And Its Production Copper is marked via a host of good engineering properties. The foremost is copper's good electrical conductivity and bulk of copper is utilized as e

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd