Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Crankshaft, what is the use of crankshaft?

what is the use of crankshaft?

Explain index jig, Explain Index Jig? 1. This type of jig, as the...

Explain Index Jig? 1. This type of jig, as the name suggests, incorporate a suitable indexing mechanism, by means of which the work piece can be indexed to required posit

Evaluate the dynamically equivalent two mass system, A Small connecting rod...

A Small connecting rod 220mm long between the centres has a mass of 2kg and mass moment of inertia of 0.02 kg- m² about its centre of gravity. The centre of gravity is located at a

marginal rate of technical substitution?, Assume the production function f...

Assume the production function for a rm is given by the equation Q = L √K. Graph the isoquants corresponding to Q = 10, Q = 20, and Q = 50. Do these isoquants exhibit diminishing

Design square footing with plan area and soil reaction, A square column 410...

A square column 410 x 410 mm (along with 4 No. 16 mm bars) carries a dead load of 1020 kN and an imposed load of 410 kN. The foundation soil has a safe bearing capacity of 200 kPa.

Cold service insulation on pipe, Q. Cold service insulation on pipe? Fa...

Q. Cold service insulation on pipe? Factory fabricated sectional pipe insulation shall be applied in staggered joint construction. On multiple layer construction, all joints sh

ENGINEERNING DRAWNING, HOW TO PREPARE A DRAWING IN FIRST ANGLE PROJECTION A...

HOW TO PREPARE A DRAWING IN FIRST ANGLE PROJECTION AND THIRD ANGLE PROJECTION AND WHAT IS THEIR BASIC PRINCIPLE AND WE DO NOT MAKE DRAWING IN 2ND ANGLE PROJECTION AND 4TH ANGLE PRO

Wind induced vibration of vertical vessels, Q. Wind Induced Vibration of Ve...

Q. Wind Induced Vibration of Vertical Vessels? Vertical vessels having a height-to-diameter ratio (h/D) (does not include insulation thickness but does include skirt height) gr

New rule with local one step ahead prediction: wls rule, New Rule with Loca...

New Rule with Local One Step Ahead Prediction: WLS Rule Along with an observation to improve the performance measure of the system, a dynamic posteriori rule, the WLS that is

Explain the conventional frame, Show schematic diagram showing the layout o...

Show schematic diagram showing the layout of transmission system of four-wheel driven car. Explain briefly the following types of frame: (a) Conventional frame (b) Integra

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd