Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Firing rate demand for steam generator, Q. Firing Rate Demand for Steam Gen...

Q. Firing Rate Demand for Steam Generator? The firing rate for each Steam Generator is proportional to the feedwater flowing into that Steam Generator. Thus, the sum of the pa

Shaft, Shaft: What is shaft? What duty is performed by shaft? What is...

Shaft: What is shaft? What duty is performed by shaft? What is the usual cross section and of what material it is generally made? Sol.: The shafts are generally cylindr

Explain clamping devices, Explain Clamping Devices A clamp is a d...

Explain Clamping Devices A clamp is a device that holds the work piece firmly against the locators provided and also resists all forces generated by the cutting action of

Illustrate the importance of aesthetic consideration, You as design Enginee...

You as design Engineer, Describe how you would decide a suitable factor of safety for the design of a new mechanical elements. Illustrate the importance of aesthetic considerati

Explain fundamental of metal casting, Q. Explain Fundamental of metal casti...

Q. Explain Fundamental of metal casting? (1)Melting the material (2)Allowing the molten metal to cool and solidify in the mould "A plane where the castings are made is ca

What are wall footings, What are wall footings? Explain in short. Gener...

What are wall footings? Explain in short. Generally wall footings are required to support direct concentric loads. However, an exception is the wall footings for retaining wall

Calculate the angle of heel, a) Derive a mathematical expression for stabil...

a) Derive a mathematical expression for stability of an automobile while accelarating in a curved path? b) A motorcycle and its rider together have a mass of 250Kg and their cen

Shear force and bending moment, Shear Force and Bending Moment: Shea ...

Shear Force and Bending Moment: Shea r Force (S.F.) Algebraic sum of all vertical forces at any section of beam to the right or left of the section is known as shear for

Compressive strength, I have some plastic tube .5 OD .44 ID .5 long I put t...

I have some plastic tube .5 OD .44 ID .5 long I put them in a vise end to end (sealing the inside of the tube) THen using a torque wench crush them to see when they fail. I get rea

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd