Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Beam, Beam: What do you mean by Beam, and Shear force and bending mom...

Beam: What do you mean by Beam, and Shear force and bending moment diagrams? Sol.: A beam is structural member whose longitudinal dimensions (that is width) is large co

Calculate the displacement of a particle, Calculate the displacement of a p...

Calculate the displacement of a particle: The displacement of a particle is given by the equation, x = 10 t 3  - 7 t 2   + 6 t + 2       I.            Calculate its d

Thermit welding, Thermit Welding This process utilises the intense hea...

Thermit Welding This process utilises the intense heat developed during the reaction between iron oxide and aluminium. When a mixture of three parts of iron oxide and one part

High temperature materials in boilers, Q. High temperature materials in Boi...

Q. High temperature materials in Boilers? A thin refractory layer between the shield and boiler tube is recommended in areas subject to moderate temperatures and levels of corr

Determine the loss of information during exchange in iges, Determine the Lo...

Determine the Loss of Information During Exchange in IGES Loss of Information During Exchange : Information would inevitably be lost when information is passed between two CAD

Computer aided manufacturing, Computer systems to plan manage, and control...

Computer systems to plan manage, and control the operations of a manufacturing plant through either direct or indirect computer interface with the plants production resource

Evaluate bending moment for overhanging beam, Evaluate Bending moment for o...

Evaluate Bending moment for overhanging beam: Draw the shear force & bending moment diagrams for 15 m span overhanging beam, that overhangs on both sides. This is subjected to

System of parallel forces - mechanics, System of parallel forces: A r...

System of parallel forces: A rigid body is subjected to system of parallel forces as shown in the figure. Reduce this system to, ( i ) A single force system ( i

Determine the convection coefficient associated with airflow, An experiment...

An experiment to determine the convection coefficient associated with airflow over the surface of a thick stainless steel casting involves insertion of thermocouples in the casting

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd