Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Find out the smallest force, Find out the smallest force: A block weig...

Find out the smallest force: A block weighing 800 N is raised up with the help of two 6o wedges B and C of negligible weights as illustrated in Figure. If the coefficient of s

Determine the work done, Determine the work done per minute by a punch tool...

Determine the work done per minute by a punch tool making 20 working strokes min when a 30 mm diameter hole is punched in 5 mm thick plate with ultimate shear strength of 450 MPa i

Determine the cycle efficiency, A simple Rankine cycle works between pressu...

A simple Rankine cycle works between pressures 28 bar and 0.06 bar, the initial condition of steam being dry saturated. Determine the cycle efficiency, work ratio and specific st

Flux shielded arc welding, FLUX SHIELDED ARC WELDING This process is p...

FLUX SHIELDED ARC WELDING This process is popularly known as Submerged Arc Welding (SAW).This is a fully mechanised welding process. The electrode is a continuous metallic sol

Capacitor discharge welding, Capacitor Discharge Welding This is used ...

Capacitor Discharge Welding This is used for welding of studs, welding of thermocouples, etc. on the base metal. A low voltage, high amperage electrical discharge from a capac

Governor, sensitivity of governors

sensitivity of governors

Calculate values of ki - thick cylinder, Calculate values of KI - thick cyl...

Calculate values of KI - thick cylinder: If cracks of 6 mm and 12 mm length are separately present only one side of inner surface in radial direction find two values of KI.

Plant layout and equipment spacing, Q. Plant layout and equipment spacing? ...

Q. Plant layout and equipment spacing? Layout refers to the location of plants (and process/power units within the plants and associated utilities (or balance of plant)) as wel

Stress distribution diagram, why stress distribution diagram is different f...

why stress distribution diagram is different for I section, T section andcircular section?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd