Question 1 of 16 4.0 Points

Six (6) samples of size five (5) were used to collect the data presented below:
sample number

1

2

3

4

5

6
sample mean (x-bar)

8.0

8.1

7.9

8.2

7.8

8.0
sample range (R)

1.8

2.4

1.9

1.8

2.1

2.0

The lower control limit (LCL) an x-bar-chart is.
A. LCL = 7.800
B. LCL = 7.034
C. LCL = 6.846
D. LCL = 21.000
E. LCL = 0.000
Reset Selection

Question 2 of 16 4.0 Points

Twenty samples of size six (6) were collected for a variable measurement. Determine the upper control limit (UCL) and lower control limit (LCL) for an R-chart if the average range, Rbar, is 4.4.
A. LCL = 0.3344, UCL = 9.3016
B. LCL = 0.0000, UCL = 1.4696
C. LCL = 1.826, UCL = 6.974
D. LCL = 0.0000, UCL = 8.8176
E. LCL = 0.0000, UCL = 176.3520
Reset Selection

Question 3 of 16 4.0 Points
Twenty-five samples of size thirty (30) were collected and a total of 48 nonconforming items were found yielding p-bar = 0.064. The three sigma upper control limit (UCL) for a p control chart would be
A. 0.833
B. 0.211
C. 0.198
D. 0.091
E. None of the above
Reset Selection

Question 4 of 16 2.0 Points

A company has calculated its CFE to be 700 and its MADt is 20. Which one of the following is the resulting TS?
A. About 0.05
B. About 20
C. About 35
D. More than 35
E. Cannot be calculated based on this information
Reset Selection

Question 5 of 16 2.0 Points
If you were trying to select a forecasting model based on a MAD statistic, which of the following MAD values reflects the most accurate model?
A. 0.425
B. 0.877
C. 2.000
D. 4.599
E. 100
Reset Selection

Question 6 of 16 3.0 Points

Given the following weekly demand and forecast figures:
Week

Demand

Forecast
1

20

40
2

25

20
3

35

30

The MAD is:
A. 0
B. -10
C. 30
D. 10
E. none of the above
Reset Selection

Question 7 of 16 3.0 Points


Given the following weekly demand and forecast figures:

Week

Demand

Forecast
1

20

40
2

25

20
3

35

30

The mean square error is:
A. -10
B. 15
C. 30
D. 150
E. 450
Reset Selection

Question 8 of 16 3.0 Points


A company wants to forecast its demand using the Simple Moving Average and has the following demand data.

Week

Demand
1

120
2

100
3

140
4

120
5

200


Which of the following is the four-period moving average forecast for period 6?


A. 120
B. 136
C. 140
D. 170
E. none of the above
Reset Selection

Question 9 of 16 3.0 Points
A company wants to forecast its demand using the Weighted Moving Average. The company uses two prior yearly sales values (i.e., Year 1 = 110 and Year 2 = 130). Using weights 0.9 and 0.1 with largest weight to demand assigned to the most recent period, which of the following is the two-period Weighted Moving Average forecast for Year 3?
A. 112
B. 117
C. 120
D. 128
E. none of the above.
Reset Selection

Question 10 of 16 3.0 Points
In Period 7 the exponentially smoothed forecast was 50 and the actual demand was 60. If alpha = 0.1, what is the exponentially smoothed forecast for Period 8?
A. 49
B. 50
C. 51
D. 59
E. 61
Reset Selection

Question 11 of 16 3.0 Points

Monthly demand for a product has been as follows in the last 2 months.
July

60 units
August

62 units

What is the forecast for September using exponential smoothing with alpha = 0.2 if the forecast for July was 50 units?
A. 54
B. 53
C. 52
D. 51
E. 50
Reset Selection

Question 12 of 16 4.0 Points

The following table gives the demand and production plan for an organization.

January February March
Demand 900 900 1,500
Production plan 1,100 1,100 1,100

The initial inventory is zero. The inventory holding cost is $1 per unit per month. The total inventory holding cost for the plan is:
A. $400
B. $600
C. $800
D. $1,200
E. None of the above
Reset Selection

Question 13 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The production requirement for the month of February is
A. 300
B. 100
C. 225
D. 250
E. none of the above
Reset Selection

Question 14 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The beginning inventory for the month of March is
A. 60
B. 75
C. 100
D. 150
E. none of the above
Reset Selection

Question 15 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The number of units current work force of 12 workers can produce in a month during regular time is
A. 960
B. 800
C. 640
D. 600
E. none of the above
Reset Selection

Question 16 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The number of workers needed to produce 960 units in a month is
A. 18
B. 16
C. 15
D. 12
E. none of the above
Reset Selection









Related Discussions:- answers Please

Activities of a maintenance schedule, Question: (a) Which are the bodi...

Question: (a) Which are the bodies responsible for policies and decisions on the exploitation and use of water resources. Explain their respective roles and functions? (b)

Screening information or steps, SCREENING INFORMATION OR STEPS : Some ...

SCREENING INFORMATION OR STEPS : Some of  the references identified may not be relevant, readers  can usually judge  the  relevance  of the  reference quickly based  on abstra

Geometry of regression, Geometry of Regression Since graphical portraya...

Geometry of Regression Since graphical portrayal brings an added dimension to the understanding of the regression line we will go through the regression line for various values

Disadvantages of ordering procedure, Disadvantages: When subscribed th...

Disadvantages: When subscribed through an agent, it will not be possible to correspond with the publishers regarding the missing issues of periodicals in the absence of detail

Merger process, T he merger process We learnt how to aligning M and A ...

T he merger process We learnt how to aligning M and A with corporate strategy. Now, let us study how the merger process takes place. The merger process is carried out in two w

Catalogue as a search tool, Catalogue as a Search Tool   Remember that ...

Catalogue as a Search Tool   Remember that not often can we recollect all particulars of a document like author, title, subject, series, etc., when we search for it. Further, w

Reengineering, Reengineering The Reconceptualizing and restructuring bu...

Reengineering The Reconceptualizing and restructuring business procedure and practices with the intention of increasing quality, efficiency, and employee and customer satisfact

How the production manager would achieve his goal, Question : a) The m...

Question : a) The major concern of a production manager is to determine when to produce and how much to produce. It involves all the processes such as how much to procure, man

Change owner, T he change owner The change owner is the person assigne...

T he change owner The change owner is the person assigned to essentially arrange and then make the approved changes to the system. The change owner is consulted about the foll

Show crisis management from a pr perspective, Question 1: Management ne...

Question 1: Management needs help when confronted by sudden crisis. It is required that crises be managed intelligently and forthrightly with the news media, Employees and the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd