draw the precedence diagram , Computer Engineering

Assignment Help:

The desired daily output for an assembly line is 360 units. This assembly line will operate 450 minutes per day. The following table have information on this product's task times and precedence relationship.

1564_44.png

a)    Draw the precedence diagram                           
b)    What is the workstation cycle time                           
c)    Balance the line using the longest task time heuristic and determine the efficiency of the line.

 


Related Discussions:- draw the precedence diagram

Explain about candidate check, The process which is underlined throughout t...

The process which is underlined throughout the check of base data is called as candidate check. When performing candidate check performance varies either towards the positive side

#title.sequential circuit, design modulo 12 up synchronous counter using t ...

design modulo 12 up synchronous counter using t flip flop

Ready and standard mode for point-to-point message passing, Q. Ready and St...

Q. Ready and Standard mode for point-to-point message passing? Ready mode: Transmitting can be started only if matching receive has already been initiated.  Standard mode: M

Example of calculate maximum access time & cost of switch, Calculate the ma...

Calculate the maximum access time that can be permitted for the data and control memories in a TSI switch with a single input and single output trunk multiplexing 2500 channels. Al

Which is most general phase structured grammar, Which is most general phase...

Which is most general phase structured grammar? Context – Sensitive is most common phase structured grammar.

Show the instruction execution by using the micro-operations, Q. Show the i...

Q. Show the instruction execution by using the micro-operations? A simple instruction can require: Instruction fetch: fetching instructions from the memory. Instruc

client will now send ten integers , Change this program so that every clie...

Change this program so that every client will now send ten integers and receives their sum from the server. In Java, for loops can be easily executed as follows: for (int i = 0 ; i

Risk detection, what is meant by risk detection in software project managem...

what is meant by risk detection in software project management

3/16/2013 1:59:48 AM

I am facing some problems in this question. Please suggest me how to draw a precedence diagram.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd