Write a project plan that includes a brief description

Assignment Help Project Management
Reference no: EM13326556

The higher management at QU has been dissatisfied with the level of technical expertise of the ITS department. Although ITS has development skills, they've been outsourcing more and more of their integration work to a third party company. At one of the strategic management meetings, it was decided that Moodle (the Open-sourcelearning platform) must be adopted so that the ITS department gain some technical experience in integrating software. So Dean Dr. Nitham Hindidecided to put in place project manager (Denis Rodman) that will oversee the process as of March 16 2014. Denis is in charge of planning and scheduling the project as well as monitoring its progress. He's also asked to report to higher management on a bi-weekly basis. The project manager sees the project as follows:

- Train4 developers on PHP and Moodle
o Training on Moodle (5 days) - all developers
o Training on PHP (5 days) - all developers

- Assign 2 business analysts to confirm feasibility of using Moodle
o Learn Moodle features (5 days) - all business analysts
o Write a report describing feasibility (3 man-days)

- Define requirements
o Update blackboard to include "course status" for online courses (10 man-days)
o Integrate courses on blackboard with Moodle (only if they're of status online) (5 man-days)
o Define requirements related to change Moodle language to Arabic (40 man-days).

- Identify any new requirements
o Meet with professors (3 man-days)
o Meet with department heads (2 man-days)
o Survey professors to validate the completeness of the new requirements (5 man-days)

- Design solution
o Design the new GUI interfaces (18 man-days)
o Rework the existing Moodle GUI interfaces (20 man-days)
o Update the Moodle database (7 man-days)
o Update the Moodle software components (25 man-days)

- Develop the new software components
o Develop the new GUI interfaces (10 man-days)
o Update Moodle GUI interfaces (20 man-days)
o Update the Moodle database (10 man-days)
o Update the Moodle software components (30 man-days)

- Manage risk
o Throw a social event to please unhappy professors (1 man-day)
o Verify that the solution meets all requirements (2 man-day)
o Verify that the software meets design (2 man-day)
o Test the software after integration (2 man-day)
o Test team to make sure they got trained well (0.5 man-day - all developers)
o Give an extra 2 days buffer after every milestone (important phase)
o Add 20 days to project time just in case.

- integrate Moodle components, new components, and with QU's blackboard (15 man-days)

- Configure software (10 man-days)

- Train users (professors)

As a project manager, Denis is also asked to define the project plan and schedule using MS project. Help Denis write a project plan that includes a brief description of the project and the project WBS and Gantt. Your document should be able to show the overall time needed for the project and the critical path. You are advised to use the international standard template (IEEE 1058) shown on the following page. You do not have to complete all sections but the ones highlighted in red are the important ones to consider.

Reference no: EM13326556

Questions Cloud

Calculate the current and voltage : A 1.5-V battery is connected in series with a 3.3-k? resistor, a 4.7-k? resistor, and a 1.0-k? resistor. Calculate the current (in mA) through and the voltage (in V) across each resistor
What are likely causes of these problems : Describe the problems characterized in this case and what are the likely causes of these problems - what are consequences of these problems for investors, Czech companies, and the Prague Stock Exchange?
Impact of the information age on business : When considering the impact of the information age on business, what are some issues business owners should address in deciding to use information technology. Would the type of business determine the appropriate information system?
Find the current through the ammeter : In the circuit shown in the figure, the 6.0 ohm resistor is consuming energy at a rate of 23.0 J/s, Find the current through the ammeter in amps
Write a project plan that includes a brief description : Help Denis write a project plan that includes a brief description of the project and the project WBS and Gantt.
Determine the value of the current in the circuit : A battery provides a voltage of 10.0V and has unknown internal resistance Rint. If the external resistance is then changed to R2 = 7.00? , what is the value of the current I2 in the circuit
Order of sharps and flats : Draw the circle of 5ths complete with the major and minor keys plus the sharps and flats and the order of sharps and flats.
How long are the skid marks : A 2000kg car traveling at a speed of 12m/s skids to a halt on wet concrete where ?k = 0.50. How long are the skid marks
Calculate your apparent weight at the top of a ferris wheel : Calculate your apparent weight at the top and bottom of a Ferris wheel, given that the radius of the wheel is R meters, it completes one revolution every T seconds

Reviews

Write a Review

Project Management Questions & Answers

  Acceptance rate for applicants with similar qualifications

Jim is considering pursuing an MS in Information Systems degree. He has applied to two different universities. The acceptance rate for applicants with similar qualifications

  Why are accurate estimates critical

Explain why are accurate estimates critical to effective project management and what steps can project managers take to improve the accuracy of estimating projects?

  Hiring project manager for most challenging projects

If you were in charge of hiring a Project Manager for one of the world's most challenging projects, what well known person would you choose to lead it and why?

  Concept of summary tasks can be used effectively

Can you please provide an example of how the concept of summary tasks can be used effectively?

  Show the aspects of project management

Aspects of project management and the most time consuming - In your organization, what aspects of the change management process are the most time-consuming?

  How to save project which is over budget and past due date

Describe how you would go about saving project - you can comprise all the things that you would require (Hardware? Software? Management structure, etc - socio-technical system).

  Manage contingency allowance - risk protection

Show how you have used or might use risk protection and risk transfer in a situation

  How do you exchange business cards

How should you handle the introduction, greeting, and handshaking and how do you exchange business cards

  Describe the levels of uncertainty

Describe the levels of uncertainty and complexity for the project and determine what the project manager should communicate to the customers about the project unknowns.

  Multiple choice questions - project management

A benchmarking effort that is limited to studying the purchasing department of another firm is referred to as benchmarking.

  Process involved in building the wbs

Is there the same kind of team process involved as in building the WBS?

  Amount to use as annual sales figure when evaluating project

This extension would cost $1 million. If annual revenues for Shoe-tek total $80 million, what is the amount to use as the annual sales figure when evaluating this project? Why?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd