Why this attempt at project partnering appear to be failing

Assignment Help Project Management
Reference no: EM131175941

Partnering-The Accounting Software Installation Project

Sitting in her office, Karin Chung is reviewing the past four months of the large corporate accounting software installation project she has been managing. Everything seemed so well planned before the project started. Each company division had a task force that provided input into the proposed installation along with potential problems. All the different divisions had been trained and briefed on exactly how their division would interface and use the forthcoming accounting software. All six contractors, which included one of the Big Five consulting companies, assisted in developing the work breakdown structure--costs, specifications, time. Karin hired a consultant to conduct a one-day partnering workshop attended by the major accounting heads, a member of each task force group, and key representatives from each of the contractors. During the workshop, several different team-building exercises were used to illustrate the importance of collaboration and effective communication. Everyone laughed when Karin fell into an imaginary acid pit during a human bridge-building exercise. The workshop ended on an upbeat note with everyone signing a partnering charter that expressed their commitment to working together as partners to complete the project.

Two Months Later
One task force member came to Karin to complain that the contractor dealing with billing would not listen to his concerns about problems that could occur in the Virginia division when billings are consolidated. The contractor had told him, the task force member, he had bigger problems than consolidation of billing in the Virginia division. Karin replied, "You can settle the problem with the contractor. Go to her and explain how serious your problem is and that it will have to be settled before the project is completed."

Later in the week in the lunchroom she overheard one consulting contractor badmouthing the work of another-"never on time, interface coding not tested." In the hallway the same day an accounting department supervisor told her that tests showed the new software will never be compatible with the Georgia division's accounting practices. While concerned, Karin considered these problems typical of the kind she had encountered on other smaller software projects.

Four Months Later
The project seemed to be falling apart. What happened to the positive attitude fostered at the prepartnering workshop? One contractor wrote a formal letter complaining that another contractor was sitting on a coding decision that was delaying their work. The letter went on: "We cannot be held responsible or liable for delays caused by others." The project was already two months behind, so problems were becoming very real and serious. Karin finally decided to call a meeting of all parties to the project and partnering agreement.

She began by asking for problems people were encountering while working on the project. Although participants were reluctant to be first for fear of being perceived as a complainer, it was not long before accusations and tempers flared out of control. It was always some group complaining about another group. Several participants complained that others were sitting on decisions that resulted in their work being held up. One consultant said, "It is impossible to tell who's in charge of what." Another participant complained that although the group met separately on small problems, it never met as a total group to assess new risk situations that developed.

Karin felt the meeting had degenerated into an unrecoverable situation. Commitment to the project and partnering appeared to be waning. She quickly decided to stop the meeting and cool things down. She spoke to the project stakeholders: "It is clear that we have some serious problems, and the project is in jeopardy. The project must get back on track, and the backbiting must stop. I want each of us to come to a meeting Friday morning with concrete suggestions of what it will take to get the project back on track and specific actions of how we can make it happen. We need to recognize our mutual interdependence and bring our relationships with each other back to a win/win environment. When we do get things back on track, we need to figure out how to stay on track."

1. Why does this attempt at project partnering appear to be failing?

2. If you were Karin, what would you do to get this project back on track?

3. What action would you take to keep the project on track?

Reference no: EM131175941

Questions Cloud

Identify and describe social psychological phenomena : Identify contextual variables (e.g., culture) that impact psychological adjustment. Define stress, stressors, and coping strategies, and contemplate their relationship to health and wellness. Identify and describe social psychological phenomena.
Who appears to be interested in partnering : Who appears to be interested in partnering?- What kinds of projects is partnering being applied to? - Does partnering mean the same thing to different people?
How would you account for revaluation of the assets : How would you account for the revaluation of the above assets - What would the relevant journal entries be - Determine the fair value of the debentures at the time of issue (which will also be their issue price).
What will happen to the value of money : Use the money market modelto support your argument. Be sure to label the vertical and horizontal axis in your graph.
Why this attempt at project partnering appear to be failing : Why does this attempt at project partnering appear to be failing? -  If you were Karin, what would you do to get this project back on track?
Differences between fixed price and cost plus contracts : What are the fundamental differences between fixed-price and cost-plus contracts?
Expain three films that will serve as the main event : Identify three films that will serve as the main event for the festival. Each film must relate back to the theme. In your justification, use specific scenes, rather than general plot summary, from each movie.
For what kinds of projects a fixed price contract be used : For what kinds of projects would you recommend that a fixed-price contract be used?- FC what kinds of projects would you recommend that a cost-plus contract be used?
How does earned value give a clearer picture of project : How does earned value give a clearer picture of project schedule and cost status than a simple plan versus actual system?

Reviews

Write a Review

Project Management Questions & Answers

  Determining the annual net cash flows

If the firm is in the 40 percent marginal tax bracket, determine the annual net cash flows generated by the drill press.

  The sales are anticipated to be within overseas markets

Assignment Description: Business Ethics and the Global Dimension of Business The Board of Directors for ABC Complete Kitchens, Inc. is very concerned about the international management aspects for the plant since nearly 20% of the sales are anticipat..

  Differences of profit objective

Explain what you think are the differences of profit objective between a defence contractor and an educational institution. Give examples and reasons for your choices.

  Business ethics-policy statement

Select Dell Inc. as your business and develop the environmental policy statement for that organization. The policy statement must have the following components below:

  Income tax consequences for nan

Discuss the income tax consequences for Nan if she structures her business as an S corporation versus a corporation.

  Finding npvs with differing project risks project

finding npvs with differing project risks project selectionassume the expected return on the market portfolio is 15 and

  How project management team can filter out information

Suggest how the project management team can filter out irrelevant information and target critical information provided by potential users of the new system.

  In what ways was the project scope expanded

In what ways was the project scope expanded? Would you consider this to be scope creep? Kroon Chemische Fabriek case. By Eric woodcock.

  Explanation of performance improvement projectshow a

explanation of performance improvement projectshow a performance improvement project you have been involved in or had

  Create a wbs for the scope of the project

Analyze the various activities required for this project and provide an estimate of duration for each activity based on the number of resources available for the project. Include assumptions and basis for each estimate

  Formulate this problem as a linear programming model

Formulate this problem as a linear programming model and solve it by using the computer.

  Construct an argumentfor or againstthe notion

Construct an argumentfor or againstthe notion that an individual's privacyismore importantthan any otherconsideration like security,childcare etc. in the workplace,Use ethical theory to support your position. Using APA referencing system

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd