Why do you think it is common for defense contractors

Assignment Help Project Management
Reference no: EM133609435

Case Study: In 2003, shipbuilders at Navantia, Spain's state-owned shipyard, welcomed a contract from their navy to construct four state-of-the-art submarines. The S-80 class was going to be an engineering marvel, filled with the latest and most cutting-edge technology, including a diesel-electric propulsion system that would be 20% lighter than other ships, while delivering 50% more power. As the list of upgrades and new technical gadgetry grew, the delivery date for the Isaac Peral-the lead ship in the S-80 class-continued to ship further behind schedule.

Nevertheless, it wasn't the continuous upgrading and addition of new equipment that finally slammed the brakes on the project; it was the startling warning from Navantia's engineers that the Isaac Peral was not seaworthy. The submarine, named in honor of the - Spanish man credited by some as the inventor of the underwater vessel, was 75-100 tons overweight, an excess that could make it difficult or impossible for the submarine to surface after submerging. As a result, the Spanish navy was faced with the challenge of fixing a submarine that ran the risk of disaster whenever it decided to submerge!

Navantia admitted the existence of "deviations related to the balance of weight" in the vessel and estimated it would take up to two years more to correct the problem, pushing the new delivery date to late 2018. The firm's engineers are trying to determine their best options at this point. It appears that two choices are most likely: Find a way to trim the design of the overall ship, which would be very difficult at this stage in construction or lengthen the hull of the already 233-foot submarine to compensate for the extra weight. The problem with this option is that designers have estimated that for every meter the hull is lengthened, it will end up costing nearly 10 million additional euros (about $14 million dollars). Unfortunately for the Spaniards, independent agencies report that they have already sunk the equivalent of $680 million into the Isaac Peral, and a total of $3 billion into the entire quartet of S-80 class submarines.

The buoyancy problem is not the only difficulty facing the program; an analyst said that that submarine's air-independent propulsion (AIP) system reactor is also underperforming. A Strategic Studies Group spokesperson said that the AIP system has been designed to enable the submarine to operate underway for 28 days but is currently able to manage only one week. The Group's memo suggests, "The buoyancy problem alone could cost up to half a billion euros to cover redesign and extra construction, without considering the propulsion problem."

The submarine setback couldn't have come at a worse time for Prime Minister Mariano Rajoy, who was already caught up in a corruption scandal and saw his approval rating hit a record low in 2013. Because of the poor shape of Spain's economy, Rajoy's austerity cuts trimmed the Spanish military budget by 30 percent in 2012, leaving much less room for added ballast. With reports that the S-80

How did such an expensive project get funded at a time when the Spanish military's entire special weapons program received a 98% cut? Sheer pride seems to have been a factor: Spain hoped the S-80 class would be a new homegrown breakthrough achieved without foreign help. Now that Navantia has entered into a $15 million contract with the Electric Boat Division of America's General Dynamics to help with the redesign, that dream seems dead in the water.*' ; program will be delayed an estimated two years and another general election looming in 2015, Rajoy likely will not see the submarines through to successful launch.

Question:

1- Why do you think it is common for defense contractors to add new features and modifications to current programs? In other words, why do defense agencies contract for one project, only to see it often evolve into something new by the time it is launched? |

2- 2. If you were an advisor brought in by the Spanish government, what advice would you offer them in managing their defense projects in regards risks, scope, and cost?

Reference no: EM133609435

Questions Cloud

What reactions are the authors hoping to get from audiences : Who is the intended audience for these pieces of literature? What reactions are the authors hoping to get from their audiences?
Discuss aspects of how the solider is feeling : Discuss aspects of how the solider is feeling, what they are encountering, what they may want to know about that is going on at home.
Challenge are with engaging diverse populations in community : If you are unable to find any, explain what you think the challenges are with engaging diverse populations in your community.
How the us represents the invasion : Consider the historical context, what you see, and how the US represents the invasion. End the first paragraph with a thesis statement.
Why do you think it is common for defense contractors : Why do you think it is common for defense contractors to add new features and modifications to current programs? In other words, why do defense agencies
What is and describe a technological innovation : what is and Describe a technological innovation not discussed in the chapter and identify where you think it lies on the control continuum between
What is the overall description of the product cooking oil : What is the overall description of the product cooking oil? what is the initial competitive intelligence needed through environmental scanning to forecast
What is the minimum score a person must have to qualify for : If test scores are normally distributed with a mean of 100 and a standard deviation of 5, what is the minimum score a person must have to qualify for
To what extent could the entire gilded age be understood : To what extent could the entire Gilded Age be understood as time of great upheavals, from working people's perspective? Bring in specific examples from reading.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd