A Project Manager wants to pick the most efficient vendor to test a new prototype. He has previous experience with 3 testing companies. Prototype testing is a highly variable activity as shown in the table below. (HINT: For example, Company X completes testing in 40 hours in 60% of cases while it takes 90 hours in the remaining 40% of tests).
Company Probability Hours Required Cost / Hour X 60% 40 $12 40% 90 Y 10% 10 $11 20% 20 30% 60 40% 100 Z 50% 25 $10 40% 90 10% 200 a. Which testing company should be picked if the Project Manager is primarily interested in completing the task in the shortest time?b. Which testing company should be picked if the Project Manager is primarily concerned with completing the task for the lowest cost?
one of the risks you anticipated for a project was the late delivery of the prototype from the vendor. you adjusted
Prepare a performance statement report for the Humphrey Catalog project.
Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the eight tasks that make up the job
How would applying the core values and concepts of the Baldridge Health Care Criteria for performance Excellence improve health care quality
Show the primary function of a project plan and explain the nine categories of information in a project master plan.
part 1 it project proposal ltbrgt ltbrgtprepare an it-related project proposal for approval. the submitted proposal
dq 1 imagine you are adjunct professor teaching project management to a group of international mba candidates. you
terrys sales presentation amp the engineering groupyou just had terry one of your team members from marketing give a
Develop a cost schedule for total project cost from finishing in the normal time to maximum crashing, ie. cost to finish in normal time , cost if crashed one week, cost if crashed two weeks, etc. to minimum time to complete.
Cost in Project Management - Why is it important for management to understand the forecasted cost at completion (FCAC)?
What steps can a project manager take to minimize the possibility of unforeseen restraints cropping up in the middle of a project?
Expert response to - Project Management - In my role as project manager for my group called the the PROVISION Healthcare Technologies.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd